ID Date Author Category Type Module Target/Number Subject Text Attachments
  388   Thursday, June 27, 2013, 14:21 chad fisherSouth Hot-CellStandard OperationTM1Ucx#6Ucx#6 installed Ta#39? rewmovedUcx#6 was installed on TM1 on Wednesday.
Ta#39 was removed.
  
  387   Wednesday, June 26, 2013, 11:03 David WangSouth Hot-CellStandard OperationTM1 Leak check on TM1 UCx target heat shieldChad and I leak checked the TM1 UCx target
heat shield at SHC. No leak has been found
so far.
  
  386   Tuesday, June 25, 2013, 14:56 Bevan MossConditioning StationStandard OperationTM1UCx#6Roughing Pumps Started The roughing pumps have been started
on the conditioning station. As it is late
in the day for David he will make the turbo
  
  385   Tuesday, June 25, 2013, 14:24 Travis CaveConditioning StationStandard OperationTM1UC#6module moveModule moves of TM#1 with Ta#39 from ITW
to SHC then TM#1 with UCx#6 from SHC to the
conditioning station moves went well.
  
  384   Tuesday, June 25, 2013, 13:20 Travis CaveSouth Hot-CellStandard OperationTM1UC#6Electrical checkResults from the electrical check of TM#1
with the UC#6 target. See attached PDF.
 TM#1_UC#6_SIS_Target_Elec_Chk.PDF 
  383   Friday, June 21, 2013, 09:26 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up Leak Check ResultsThe Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight!
  
  382   Thursday, June 20, 2013, 13:47 Travis CaveSpent Target VaultStandard Operation  Spent Target AssayTen targets have been assayed or had field
measurements(they were too hot to ship but
were assayed the last time an assay was done)
 Vault_Storage_June_20_2013.pdf 
  381   Wednesday, June 19, 2013, 08:15 chad fisherSouth Hot-CellDevelopmentTM3 Mock up water block connectionsAll water block connections on the mock-up
have bben achieved. It is now ready for leak
checking.
 20130619_080806[1].jpg20130619_080808[1].jpg 
  380   Tuesday, June 18, 2013, 14:00 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up testing / water block connectionsThe testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven
  
  379   Thursday, June 13, 2013, 09:21 chad fisherSouth Hot-CellDevelopment  Warm Cell Mock-upthe warm cell mock-up has been inserted
into the warm cell and final preparation
for the remote test are being made.
 20130613_084421[1].jpg20130613_084426[1].jpg 
  378   Thursday, June 13, 2013, 09:18 chad fisherSouth Hot-CellRepairTM3 Source Tray/Extraction Column RemovalTM3 Rev 2 source tray/extraction column
insertion into its storage was completed
yesterday and it was then removed from the
  
  377   Wednesday, June 12, 2013, 10:39 Travis CaveSouth Hot-CellStandard Operation  spent source tray removalThe spent source tray for TM#3 has been
removed from the south hot cell and well
be placed in the the hot cell ante room.
  
  376   Tuesday, June 11, 2013, 10:05 David WangITWStandard OperationTM1 Disconnected TM1 in ITW.Dan and I  disconnected TM1 in ITW.   
  375   Tuesday, June 04, 2013, 15:34 Bevan MossConditioning StationRepair  Relay replacedESC was called out again to inspect the
chiller as it was showing the same problem
as before. This time when started one fan
  
  374   Tuesday, June 04, 2013, 12:36 David WangITEStandard OperationTM4 5 shielding blocks are transferred from ITW to ITEDan an I  transferred 5 shielding
blocks from ITW to ITE. The ITE is configured
to take proton beam.
  
  373   Friday, May 31, 2013, 11:19 Travis CaveSpent Target VaultStandard Operation SiC#28 (RFQ Target)Spent target moveSpent target SiC#28 (RFQ Target) has been
moved from the south hot to the storage vault.
The target was placed in pail #105 in spot
 Vault_Storage_May_31_2013.pdf 
  372   Wednesday, May 29, 2013, 12:07 chad fisherSouth Hot-CellDevelopment SiC#28 RFQRFQ AutopsyMajor portions of the RFQ target have now
been sucessfully dismantled. More minor dismantling
with conclude this afternoon.
  
  371   Wednesday, May 29, 2013, 06:32 David WangITEStandard OperationTM4Ta#40TM4 has been connected in ITE.TM4 has been connected in ITE. The pumping
down is fine so far.TM4 water interlock check
was done yesterday.
  
  370   Tuesday, May 28, 2013, 10:42 Travis CaveSouth Hot-CellStandard OperationTM4Ta#40Electrical checkResults of the electrical check on 
TM#4 with Ta#40, it passed. See attached
PDF for results.
 TM#4_Ta#40_SIS_Target_Elec_Chk.PDF 
  369   Tuesday, May 28, 2013, 10:37 Travis CaveITEStandard OperationTM4Ta#40module moveTM#4 with Ta #40 moved from the conditioning
station to the east target station, move
went well.
  