  375   Tuesday, June 04, 2013, 15:34 Bevan MossConditioning StationRepair  Relay replacedESC was called out again to inspect the
chiller as it was showing the same problem
as before. This time when started one fan
  
  374   Tuesday, June 04, 2013, 12:36 David WangITEStandard OperationTM4 5 shielding blocks are transferred from ITW to ITEDan an I  transferred 5 shielding
blocks from ITW to ITE. The ITE is configured
to take proton beam.
  
  373   Friday, May 31, 2013, 11:19 Travis CaveSpent Target VaultStandard Operation SiC#28 (RFQ Target)Spent target moveSpent target SiC#28 (RFQ Target) has been
moved from the south hot to the storage vault.
The target was placed in pail #105 in spot
 Vault_Storage_May_31_2013.pdf 
  372   Wednesday, May 29, 2013, 12:07 chad fisherSouth Hot-CellDevelopment SiC#28 RFQRFQ AutopsyMajor portions of the RFQ target have now
been sucessfully dismantled. More minor dismantling
with conclude this afternoon.
  
  371   Wednesday, May 29, 2013, 06:32 David WangITEStandard OperationTM4Ta#40TM4 has been connected in ITE.TM4 has been connected in ITE. The pumping
down is fine so far.TM4 water interlock check
was done yesterday.
  
  370   Tuesday, May 28, 2013, 10:42 Travis CaveSouth Hot-CellStandard OperationTM4Ta#40Electrical checkResults of the electrical check on 
TM#4 with Ta#40, it passed. See attached
PDF for results.
 TM#4_Ta#40_SIS_Target_Elec_Chk.PDF 
  369   Tuesday, May 28, 2013, 10:37 Travis CaveITEStandard OperationTM4Ta#40module moveTM#4 with Ta #40 moved from the conditioning
station to the east target station, move
went well.
  
  368   Monday, May 27, 2013, 16:36 Bevan MossConditioning StationStandard OperationTM4Ta#40Argon Venting Started Argon venting has started. It will
be left to vent over night. 
  
  367   Monday, May 27, 2013, 16:07 Bevan MossConditioning StationStandard OperationTM4Ta #40HV conditioning The HV conditioning reached a maximum
of 44kV today before a spark took out the
canbus card. I will attach the data once
  
  366   Monday, May 27, 2013, 16:01 Bevan MossConditioning StationRepair  CanBUS card During HV conditioning of TM4 with
Ta#40 there was a spark at ~43 kV that caused
the Bias card to "fry". Dave Morris
  
  365   Monday, May 27, 2013, 15:59 Bevan MossConditioning StationRepair  Compressor fault Once again the 7.5 compressors are
tripping due to faults. I believe it is due
to over pressure as a result of the chiller
  
  364   Monday, May 27, 2013, 11:55 chad fisherSouth Hot-CellStandard Operation  Special Tooling for RFQ targetThe special tool made for the RFQ target
autopsy has been inserted into the hot cell.
 
  
  363   Monday, May 27, 2013, 10:37 Bevan MossConditioning StationMaintenanceTM4 Cooling Systems topped offRob walker has flushed and refilled the
primary side of the system (note the water
still looks nasty). This morning the primary
  
  362   Monday, May 27, 2013, 10:35 Bevan MossConditioning StationStandard OperationTM4Ta #40Pumps Started HV testing to followThe pumps have been turned on at ~9:30
this morning. Current values are 6.61 Mohm
TCS:DIC1 @19.4 C. HV testing will start momentarily.
  
  361   Thursday, May 23, 2013, 14:12 Bevan MossConditioning StationMaintenance  Primary Circuit Drained and Flushed Rob Walker has drained the primary
side of the conditioning station. It will
be flushed, filled  and chemically treated.
  
  360   Thursday, May 23, 2013, 14:08 Bevan MossConditioning StationStandard OperationTM4Ta #40Turbo Pumps on The turbo pumps have been turned
on and are running
  
  359   Thursday, May 23, 2013, 14:07 Bevan MossConditioning StationRepair  Chiller Unit Repaired ESC came today and "repaired"
the chiller. There was something wrong with
the VFD controller. The were able to get
  
  358   Thursday, May 23, 2013, 11:14 David WangSouth Hot-CellStandard OperationTM4TA#40 TM4 TA# 40 HS leak check at SHCTM4 Ta#40 HS leak check is done at SHC
. No leak has been found so far. There will
be  a helium pressure test on it at
  
  357   Thursday, May 23, 2013, 09:51 Travis CaveConditioning StationStandard OperationTM4Ta#40module moveTM#4 with Ta#40 has been moved from the
south hot cell to the conditioning station.
  
  356   Wednesday, May 22, 2013, 14:11 chad fisherSouth Hot-CellStandard OperationTM4Ta#40Ta#40 installedTa#40 has been installed.
Leak checking and high voltage tomorrow
before the move.
  