248
|
Tuesday, February 26, 2013, 10:26 |
Travis Cave | ITW | Standard Operation | TM1 | | module move | TM1 moved from the west station to the
southwest silo. Move went well. |
|
247
|
Friday, February 22, 2013, 13:13 |
Bevan Moss | Conditioning Station | Development | TM4 | CS Test Target #1 | Broken Turbo Pump | Today while putting the cover on
the cord that goes to the controller was
bumped. This bent the connector down and |
|
246
|
Friday, February 22, 2013, 13:02 |
Bevan Moss | Conditioning Station | Development | TM4 | CS Test Target #1 | HV test with Water | Hello Ray and Yi
Completed a HV test with the water
flowing today. |
|
245
|
Thursday, February 21, 2013, 14:05 |
David Wang | ITW | Repair | TM1 | | Disconnected EXIT1 in ITW. | Disconnected EXIT1 in ITW. All cables ,
wires and air lines are label marked. |
|
244
|
Thursday, February 14, 2013, 09:31 |
David Wang | ITW | Repair | | | ITH MP1 is replaced. | Edi and I replaced the broken ITH MP1 in
target hall with a new pump. The old pump
was leak on oil. There were no oil had been |
|
243
|
Friday, February 08, 2013, 11:42 |
Grant Minor | ITE | Maintenance | | | TAPC 477 resolved - ISAC elec. room gas cylinder | See attached TAPC 477 documentation. |
|
242
|
Wednesday, February 06, 2013, 14:34 |
Bevan Moss | Conditioning Station | Development | TM4 | CS Test Target #1 | 40kV All Common w/o Water Test | Today the module was biased to 40kV
in the conditioning station. The current
draw was 0uA. Sparking started at 27 kV. |
|
241
|
Monday, January 28, 2013, 12:26 |
Travis Cave | Conditioning Station | Development | | | Switches connected | the switches and the solenoid are all wire
up to 24VDC, when you open either of the
little doors the solenoid switches this is |
|
240
|
Thursday, January 24, 2013, 13:30 |
David Wang | ITW | Standard Operation | TM1 | | ITW-TM1 2013 winter shut down leak check. | 2013 winter shut down ITW-TM1 primary vacuum
vessel, secondary vacuum vessel, and water
lines leak check: connected leak detector |
|
239
|
Friday, January 18, 2013, 17:01 |
Grant Minor | Conditioning Station | Development | TM4 | | Photos of the CS with TM4 (after the no-module HV test, only vacuum connected) | Attached are some photos of TM4 in the
Conditioning Station after the no-module
HV test completion. Only vacuum services |
|
238
|
Friday, January 18, 2013, 16:56 |
Grant Minor | Conditioning Station | Standard Operation | TM4 | | VAT valve btwn roughing and nuc. vent. closed | Bevan attempted to start pumping down on
TM4 today remotely but there was an issue.
He will report on Monday. |
|
237
|
Friday, January 18, 2013, 11:17 |
David Wang | South Hot-Cell | Standard Operation | TM4 | dummy target | TM4 heat shield circuit leak check with dummy target on. | Chad and i did a leak check on TM4 heat
shield circuit with installed dummy target
at SHC today. The leak detector is pumped |
|
236
|
Friday, January 18, 2013, 11:15 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | CS Test Target #1 | module move | TM#4 with the test target #1 is now in
the conditioning station, move went well. |
|
235
|
Friday, January 18, 2013, 09:10 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | CS Test Target #1 | Electrical check | Electrical check performed on the CS Test
Target #1 at the south hot cell. See PDF
for details. |
|
234
|
Thursday, January 17, 2013, 11:18 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | | module move | TM#4 has been moved from the SW silo to
the south hot cell, move went well. |
|
233
|
Thursday, January 17, 2013, 10:06 |
chad fisher | South Hot-Cell | Standard Operation | | | SiC Test Target for TM4/CS | I have inserted the test target for TM4
and the CS into the hot cell.
I had some concerns about the condition |
16x |
232
|
Tuesday, January 15, 2013, 14:37 |
Travis Cave | Spent Target Vault | Standard Operation | | TiC#3 | Spent target move | TiC #3 was moved from the south hot cell
in to the vault storage today, it was placed
in slot 4B and was in pail #104, it had a |
|
231
|
Tuesday, January 15, 2013, 10:49 |
David Wang | ITW | Standard Operation | TM1 | no target | TM1 vacuum system connection in ITW | I connected TM 1 vacuum system in ITW.
The TM1 and ITW will be pumped out for shut
down routine leak check. |
|
230
|
Monday, January 14, 2013, 14:09 |
Travis Cave | ITW | Standard Operation | TM1 | no target | module move | TM#1 has been moved from the south hot
hell to the west target station, move went
well. |
|
229
|
Thursday, January 10, 2013, 10:40 |
David Wang | ITW | Maintenance | | | Replaced all high active water system magnetic pedal wheels in ITW and ITE. | I replaced all high active water system
magnetic pedal wheels in ITW and ITE. This
is a preventive maintenance job we planned |
|