Message ID: 237     Entry time: Friday, January 18, 2013, 11:17
Author: David Wang 
Category: South Hot-Cell 
Type: Standard Operation 
Module: TM4 
Target/Number: dummy target 
Subject: TM4 heat shield circuit leak check with dummy target on. 

Chad and i did a leak check on TM4 heat shield circuit with installed dummy target at SHC today. The leak detector is pumped to 0.0xE-9atm.cc/sec.Chad sprayed helium twice on each  VCR joints .There is no any response had been found on the leak detector during each 45 seconds waiting time. The TM4 heat shield circuit with dummy  target is leak tight so far.  