  21   Monday, March 18, 2013, 15:12 Isaac EarleCyclotronMaintenanceCyclotron Magnet Face Gap MeasurementsMeasurements of the cyclotron magnet face
gap were taken on March 15, 2013 at two locations
around the tank with the cyclotron lid in
 8x 
  23   Thursday, April 11, 2013, 19:00 Grant MinorElevation JackMaintenanceUpper Bearing at Jack Station 9 + Fall Protection UpgradesThere was a brief access period to the
Cyclotron vault during April 9 to 12, 2013
due to other Cyclotron issues.
 station_9_ceiling_anchors_SRLs_10april2013-002.JPGstation_9_ceiling_anchors_SRLs_10april2013-003.JPGstation_9_ceiling_anchors_SRLs_10april2013-004.JPGstation_9_ceiling_anchors_SRLs_10april2013-006.JPG 
  24   Monday, September 30, 2013, 14:02 Travis CaveService BridgeMaintenancenew festooningThe festooning and bearings for the festooning
cars for both outriggers has been replaced
and it is in working order.
  
  25   Thursday, January 16, 2014, 08:46 maicodallavalleTrolleys servicedMaintenancePre Cyclotron work servicing and checkingThis is a list of all the trolleys and
other equipment witch were checked and serviced
prior to work in the Cyclotron.
  
  43   Monday, April 28, 2014, 10:20 Dan McDonaldService BridgeMaintenanceBridge orbit reduction boxNoticed oil leaking out of reduction box,
scan and swipe, disconnect e motor and all
related cables from bridge, remove motor
  
  47   Friday, January 23, 2015, 10:27 maicodallavalleElevation JackMaintenance2015 Jack Maintenance - Stations #4 and Station #9The Cyclotron Elevating System Shut Down 
work done this year was done on Station #4
and Station #9.
  
  48   Monday, January 26, 2015, 07:57 maicodallavalleElevation JackMaintenanceFall arrest Platform RailingAll of the Fall arrest Platform Railing
has been Collapsed for Cyclotron Lid up.
  
  56   Tuesday, February 17, 2015, 07:10 Dan McDonaldTrolleys servicedMaintenancePre shut down trolley serviceRoutine maintenance as per Mike Gallop's
written procedure took place in December
with the only non routine service being the
  
  60   Monday, March 09, 2015, 11:55 chad fisherElevation JackMaintenanceChecking for contamination on fall arrest equip.Fall equipment from the lockers in the
RH shop have been checked for contamination
and the lockers themselves have been swiped.
  
  61   Tuesday, March 10, 2015, 10:24 chad fisherElevation JackMaintenanceContaminated equipment updateThe harness, carabineer, and shock packed
used during the ISAC hot cell swipe have
been checked seperately by Mike and he has
  
  62   Tuesday, March 17, 2015, 13:04 maicodallavalleCyclotronMaintenanceUpper Bearings Station #5 and #10The Upper bearings on Station #5 and Station
#10 have been serviced. The Upper Bearing
were disassembled. The old gear was removed
  
  68   Thursday, April 16, 2015, 15:26 Grant MinorElevation JackMaintenanceCyclotron Elevating System Maintenance Rotation Record - Updated 16 Apr 2015   Cyclotron_Elevating_System_Maintenance_Rotation_Record_16Apr2015.pdf 
  69   Tuesday, July 28, 2015, 11:47 Dan McDonaldTrolleyMaintenanceCamera trolley serviceServiced the Camera trolley this morning
as per Mike Gallops service outline.
  
  70   Thursday, September 17, 2015, 18:38 Grant MinorElevation JackMaintenanceStation 9 Jack Worm Gear Inspection - unusual wear markings 16Sept2015Unusual wear markings were observed on
the Station 9 jack (not sure if L or R jack?)
during a visual inspection.
 8x 
  76   Wednesday, January 27, 2016, 10:51 maicodallavalleElevation JackMaintenance2016 Cyclotron Elevation System Maintenance The Cyclotron Elevating System Shut Down 
work done this year was done on Station #9
and Station #10.
  
  79   Friday, February 05, 2016, 14:57 Travis CaveService BridgeMaintenanceoutrigger problemoutrigger 1 had a power failure, bridge
was removed power restored and outrigger
parked, outrigger will be looked at once
  
  89   Thursday, June 30, 2016, 13:47 Dan McDonaldTrolleyMaintenanceLift trolleyMaintenance has been performed on the lift
trolley, re sealed the main drive gear box
it was quite dry inside and in need of new
  
  90   Wednesday, September 14, 2016, 11:30 Dan McDonaldElevation JackMaintenanceJack station 10BAnnual jack maintenance : Jack 10b upon
inspection it was found that the output shaft
seal on 10b was in need of replacement. In
 14x 
  92   Monday, February 06, 2017, 20:32 Jason KapalkaElevation JackMaintenance2017 Cyclotron Elevating System Maintenance The Cyclotron Elevating System planned maintenance
work this year was performed on Jack Station
#3, #8, #9, and #10.
 Cyclotron_Elevation_Maintenance_Rotation_Record_20170829.xlsx 
  100   Tuesday, March 14, 2017, 17:07 Jason KapalkaProbeMaintenanceLE probe removal simulation exerciseA simulated removal of the LE2 Probe from
the Cyclotron tank was performed by the RH
and Probes group using the 
  