Wednesday, February 07, 2024, 12:04, Adam Newsome, Elevation Jack, Repair, Elevating system - brake master relay fuse issue
|
It was observed when attempting lid up operation on 2024-02-06 that the brakes for each of the jacks were not operating correctly. It appeared that power
was not being applied so the brakes were stuck in the engaged state. This ultimately resulted in issues with the lid up operation.
The issue was traced to relay A1 (the master brake power relay) not toggling as expected, despite the relevant control signals being present to |
Thursday, February 08, 2024, 08:50, Adam Newsome, Elevation Jack, Maintenance, Elevating system - station 10 motor contactor issue
|
It was observed during lid up operation on 2024-02-08, approximately halfway through raising the lid, that the motor contactor for station 10 located
within its small motor panel stopped functioning. The symptoms observed were: entire system stopped since station 10 lagged behind (approx. 150 counts
on counter), station 10 could not be jogged locally in either direction, the control signal to activate the motor was being sent to the contactor when |
Friday, February 09, 2024, 15:43, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation - 2024 
|
The cyclotron lid was raised starting ~10:30am on 2024-02-06 and finishing at ~3:30pm on 2024-02-08, under work permit C2024-02-06-4.
Upon first attempt to raise the lid, issues were encountered. The system seemed to start as expected but quickly tripped, resulting in no appreciable |
Friday, February 16, 2024, 11:11, Adam Newsome, Trolley, Repair, Lift Trolley: vertical motion failure, motor relays replaced
|
Today (2024-02-16) when operating the lift trolley to install shields in the cyclotron, the vertical motion was observed to be intermittently working.
When the trolley was out of the cyclotron tank and on the carrier, troubleshooting showed that it was likely an issue with the motor relays. The relay
box was removed and the relays showed signs of wear due to ageing. The relays were replaced with new ones, and the box was reinstalled. The vertical motion |
Monday, February 26, 2024, 11:52, Adam Newsome, Cyclotron, Repair, Controls issue - CAMAC power supply
|
An issue was encountered on 2024-02-23 when attempting to operate the lift trolley.
The following symptoms were observed: |
Friday, April 19, 2024, 15:18, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2024
|
The lid down operation took place on April 19, 2024.
The system was energized a few minutes ahead of time. |
Wednesday, April 24, 2024, 14:26, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (second) - 2024
|
Due to an issue with resonator latching, there was a need to raise the cyclotron lid a second time this shutdown.
The plan at first was to raise the lid by small increments (approximately 1mm at a time up to approximately 25mm) while RF group performed some
checks. |
Tuesday, April 30, 2024, 15:00, Adam Newsome, Cyclotron, Standard Operation, Lid down operation (second) - 2024
|
A second lid down operation took place on April 30, 2024.
The system was energized a few minutes ahead of time. |
Thursday, May 02, 2024, 12:42, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (third) - 2024
|
The cyclotron lid was raised starting ~11:45am on 2024-05-02 and finishing at ~12:12pm under work permit C2024-05-02-5.
The raising was stopped a few times up until approximately 5" elevation, for RF group to perform checks, and to inspect the tank seal. |
Tuesday, May 07, 2024, 09:35, Adam Newsome, Elevation Jack, Standard Operation, Lid down operation (third) - 2024 
|
A third lid down operation took place over May 6-7, 2024.
The system was energized a few minutes ahead of time. |
Wednesday, July 17, 2024, 15:02, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels
|
A safety walkaround for July 2024 was completed for the B1 and B2 levels by A. Newsome, and for the main shop and back shop by R. Sykes.
Results can be found in the master
spreadsheet |
Wednesday, July 24, 2024, 11:39, Adam Newsome, Cyclotron, Standard Operation, Investigation of faulty Al-ALCW signal
|
Fault 16710 was initially assigned to Remote Handling: IBOP0206 giving false positive - Al-ALCW water pressure shows "off" when it isn't; The safety system
is reporting that Al-ALCW water pressure is "off" (page SVG) when the system is still on and at normal operating pressure. |
Thursday, October 10, 2024, 12:30, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels
|
A safety walkaround was completed for the RH Shop, Back Shop, B1, and B2 levels.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
Wednesday, October 16, 2024, 11:37, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 2 of 2) - Complete 6x
|
See previous e-log for phase 1: e-log 134
Phase 2 of the bridge lift mechanism refurbishment was completed. The scope of work for this phase includes replacement of the hydraulic pump (including |
Friday, January 03, 2025, 10:20, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building B1 and B2 Level
|
A safety walkaround was completed for the RH building B1 and B2 levels.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
Monday, January 06, 2025, 13:57, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building Shop and Back Shop
|
A safety walkaround was completed for the RH building shop and back shop.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
Monday, January 20, 2025, 13:55, Adam Newsome, Elevation Jack, Maintenance, Elevating System MRO - 2025  
|
Elevating System MRO was started Jan. 16 by R. Sykes, M. Dalla Valle, P. Hall-Patch under work permit C2025-01-16-3.
The plan for this year includes:
Remove station 5 from service and move to shop for maintenance
Remove station 7 (spare) and move to station 5
|
Tuesday, January 28, 2025, 12:31, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation - 2025 
|
The lid up operation took place on Jan. 28, 2025 under work permit C2025-01-28-1
|
Wednesday, February 19, 2025, 15:29, Adam Newsome, Cyclotron, Development, Lift Trolley - upgraded controls commissioning complete
|
Newly implemented PLC-based controls hardware and software for the Lift Trolley was commissioned between January 30 - February 7, 2025, mostly under
work permit C2025-01-30-3.
|
Friday, March 21, 2025, 11:13, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2025 
|
The lid down operation took place on March 21, 2025 [slightly ahead of schedule].
|
|