Friday, February 16, 2024, 11:11, Adam Newsome, Trolley, Repair, Lift Trolley: vertical motion failure, motor relays replaced
|
Today (2024-02-16) when operating the lift trolley to install shields in the cyclotron, the vertical motion was observed to be intermittently working.
When the trolley was out of the cyclotron tank and on the carrier, troubleshooting showed that it was likely an issue with the motor relays. The relay
box was removed and the relays showed signs of wear due to ageing. The relays were replaced with new ones, and the box was reinstalled. The vertical motion |
Monday, February 26, 2024, 11:52, Adam Newsome, Cyclotron, Repair, Controls issue - CAMAC power supply
|
An issue was encountered on 2024-02-23 when attempting to operate the lift trolley.
The following symptoms were observed: |
Friday, April 19, 2024, 15:18, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2024
|
The lid down operation took place on April 19, 2024.
The system was energized a few minutes ahead of time. |
Wednesday, April 24, 2024, 14:26, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (second) - 2024
|
Due to an issue with resonator latching, there was a need to raise the cyclotron lid a second time this shutdown.
The plan at first was to raise the lid by small increments (approximately 1mm at a time up to approximately 25mm) while RF group performed some
checks. |
Tuesday, April 30, 2024, 15:00, Adam Newsome, Cyclotron, Standard Operation, Lid down operation (second) - 2024
|
A second lid down operation took place on April 30, 2024.
The system was energized a few minutes ahead of time. |
Thursday, May 02, 2024, 12:42, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (third) - 2024
|
The cyclotron lid was raised starting ~11:45am on 2024-05-02 and finishing at ~12:12pm under work permit C2024-05-02-5.
The raising was stopped a few times up until approximately 5" elevation, for RF group to perform checks, and to inspect the tank seal. |
Tuesday, May 07, 2024, 09:35, Adam Newsome, Elevation Jack, Standard Operation, Lid down operation (third) - 2024
|
A third lid down operation took place over May 6-7, 2024.
The system was energized a few minutes ahead of time. |
Wednesday, July 17, 2024, 15:02, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels
|
A safety walkaround for July 2024 was completed for the B1 and B2 levels by A. Newsome, and for the main shop and back shop by R. Sykes.
Results can be found in the master
spreadsheet |
Wednesday, July 24, 2024, 11:39, Adam Newsome, Cyclotron, Standard Operation, Investigation of faulty Al-ALCW signal
|
Fault 16710 was initially assigned to Remote Handling: IBOP0206 giving false positive - Al-ALCW water pressure shows "off" when it isn't; The safety system
is reporting that Al-ALCW water pressure is "off" (page SVG) when the system is still on and at normal operating pressure. |
Thursday, October 10, 2024, 12:30, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels
|
A safety walkaround was completed for the RH Shop, Back Shop, B1, and B2 levels.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
Wednesday, October 16, 2024, 11:37, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 2 of 2) - Complete 6x
|
See previous e-log for phase 1: e-log 134
Phase 2 of the bridge lift mechanism refurbishment was completed. The scope of work for this phase includes replacement of the hydraulic pump (including |
Friday, January 03, 2025, 10:20, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building B1 and B2 Level
|
A safety walkaround was completed for the RH building B1 and B2 levels.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
Monday, January 06, 2025, 13:57, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building Shop and Back Shop
|
A safety walkaround was completed for the RH building shop and back shop.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
|