Entry  Wednesday, February 07, 2024, 12:04, Adam Newsome, Elevation Jack, Repair, Elevating system - brake master relay fuse issue 
Entry  Thursday, February 08, 2024, 08:50, Adam Newsome, Elevation Jack, Maintenance, Elevating system - station 10 motor contactor issue 
Entry  Friday, February 09, 2024, 15:43, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation - 2024 Elevation_System_Checklist_-_February_2024.xlsxElevation_System_Thermal_Imaging_Report_-_Lid_Up_Feb_2024.pdf
Entry  Friday, February 16, 2024, 11:11, Adam Newsome, Trolley, Repair, Lift Trolley: vertical motion failure, motor relays replaced 
Entry  Monday, February 26, 2024, 11:52, Adam Newsome, Cyclotron, Repair, Controls issue - CAMAC power supply 
Entry  Friday, April 19, 2024, 15:18, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2024 Elevation_System_Checklist_-_2024.xlsx
Entry  Wednesday, April 24, 2024, 14:26, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (second) - 2024 Elevation_System_Checklist_-_2024_-_Second_Lid_Up.pdf
Entry  Tuesday, April 30, 2024, 15:00, Adam Newsome, Cyclotron, Standard Operation, Lid down operation (second) - 2024  Elevation_System_Checklist_-_2024_-_Second_Lid_Down.pdf
Entry  Thursday, May 02, 2024, 12:42, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (third) - 2024 Elevation_System_Checklist_-_2024_-_May.pdf
Entry  Tuesday, May 07, 2024, 09:35, Adam Newsome, Elevation Jack, Standard Operation, Lid down operation (third) - 2024  Motor_Contactor_6_-_2024.PNGElevation_System_Checklist_-_2024_Lid_down_-_third.pdf
Entry  Wednesday, July 17, 2024, 15:02, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels 
Entry  Wednesday, July 24, 2024, 11:39, Adam Newsome, Cyclotron, Standard Operation, Investigation of faulty Al-ALCW signal 
Entry  Thursday, October 10, 2024, 12:30, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels 
Entry  Wednesday, October 16, 2024, 11:37, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 2 of 2) - Complete  6x
Entry  Friday, January 03, 2025, 10:20, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building B1 and B2 Level 
Entry  Monday, January 06, 2025, 13:57, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building Shop and Back Shop 
Entry  Monday, January 20, 2025, 13:55, Adam Newsome, Elevation Jack, Maintenance, Elevating System MRO - 2025 Elevation_System_Checklist_-_2025.xlsxPXL_20250117_171031446.MP.jpgCyclotron_Jacks_History_-_updated_2025-01-24.xlsx
Entry  Tuesday, January 28, 2025, 12:31, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation - 2025 Elevation_System_Checklist_-_2025.xlsxLid_Up_2025_Thermal_Imaging.pdf
Entry  Wednesday, February 19, 2025, 15:29, Adam Newsome, Cyclotron, Development, Lift Trolley - upgraded controls commissioning complete 
Entry  Friday, March 21, 2025, 11:13, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2025 Elevation_System_Checklist_-_2025.xlsxLid_Down_2025-03-21_Thermal_Imaging_Report.pdf