3
|
Tuesday, February 14, 2012, 15:40 |
Grant Minor | Trolley | Standard Operation | 2C Removal - all 4 QDLs were actuated remotely this year! | Today Remote Handling staff (Maico Dalla
Valle, Travis Cave) used the Remote Handling
2C probe removal trolley to remove the probe |
|
7
|
Tuesday, January 29, 2013, 18:49 |
Grant Minor | Elevation Jack | Standard Operation | Lid-up complete - summary notes | Lid-up was first attempted yesterday (Jan
28th) by Dan Louie, Arthur Leung, and Maico
Dalla Valle. They experienced problems |
|
8
|
Wednesday, January 30, 2013, 14:44 |
Grant Minor | Elevation Jack | Standard Operation | Further lid-up notes from Dan Louie | Dan Louie's e-mail comments from 30 Jan
2013 are attached.
- Grant |
|
14
|
Wednesday, February 27, 2013, 12:08 |
Travis Cave | Cyclotron | Standard Operation | Installation of 2C | 2C has been installed located on all QDLs
and all the numbers, continuity check done
and passed. Bridge has been removed from |
|
15
|
Tuesday, March 05, 2013, 14:11 |
Travis Cave | Cyclotron | Standard Operation | Setup and the Installation of the HE 1 probe. | Setup of the HE 1 probe is difficult has
we have no mockup of it to properly setup
cameras and equipment for it. This is problem |
|
19
|
Friday, March 15, 2013, 08:39 |
Don Jackson | Cyclotron | Standard Operation | Pre Lid Down In Tank Video Survey | In tank survey completed. A few items
of interest were found. Ladders need
to moved manually outboard to #5 resonators |
|
20
|
Friday, March 15, 2013, 15:18 |
Grant Minor | Cyclotron | Standard Operation | Lid Down Successful - Mechanical Counter Readings | Prior to the lid-down operation today,
the Cyclotron was lowered by 0.75" and
then raised again to confirm that the upper |
|
22
|
Tuesday, March 19, 2013, 19:17 |
Grant Minor | Elevation Jack | Standard Operation | Re-indexing of all jack station "zero" yoke elevations | The dimension between the yokes and the
Cyclotron upper structure primary beams was
set to .25" nominal at all jack stations |
|
26
|
Friday, January 17, 2014, 07:53 |
Travis Cave | Trolleys serviced | Standard Operation | Trolley checks | All trolleys work electrically and control
wise. One encoder was found non functioning
on the upper resonator trolley for the vertical |
|
27
|
Monday, January 20, 2014, 12:00 |
Grant Minor | Elevation Jack | Standard Operation | Indexing Check of Cyclotron Jack Stations | Maico Dalla Valle and Grant Minor, supported
by Dan Louie and Arthur Leung, entered the
Cyclotron Vault on January 15th, 2014 to |
|
28
|
Thursday, January 23, 2014, 18:47 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Up Report - 22 Jan 2014 | Yesterday Grant Minor (me), Maico Dalla
Valle, Dan Louie, and Arthur Leung worked
with Operations to perform the Cyclotron |
6x |
29
|
Friday, January 24, 2014, 14:10 |
Travis Cave | Cyclotron | Standard Operation | Copper blockers | The copper blockers have been removed from
the cyclotron and placed into the coffins. |
|
30
|
Monday, January 27, 2014, 14:42 |
Travis Cave | Shielding | Standard Operation | shields and radiation survey | The cyclotron radiation survey was aborted
due to the orbit not working recording the
numbers correctly. One shield has been in |
|
31
|
Tuesday, January 28, 2014, 14:59 |
Travis Cave | Shielding | Standard Operation | shields | 200's, 400's, 500's, 600's, and a pallet
of 700's have been installed |
|
32
|
Wednesday, January 29, 2014, 15:08 |
Bevan Moss | Cyclotron | Standard Operation | Shielding and Port Hole Covers | The Shielding and the Port Hole Covers
have all been installed. No issues with the
installation have caused any problems. This |
|
33
|
Thursday, January 30, 2014, 13:47 |
Travis Cave | Cyclotron | Standard Operation | shields | All shields, pothole covers, and ladders
have been installed into the cyclotron. |
|
34
|
Friday, January 31, 2014, 10:07 |
Travis Cave | Cyclotron | Standard Operation | 2C removal | 2C has been successfully removed from the
cyclotron and is now currently sitting in
the B2 level of the RH building. A tank access |
|
35
|
Friday, February 07, 2014, 10:50 |
Travis Cave | Cyclotron | Standard Operation | 2C install | 2C has been installed into the cyclotron. |
|
36
|
Friday, February 21, 2014, 11:05 |
Bevan Moss | Cyclotron | Standard Operation | Old Monitor Box Removed, New installed | One of the beam spill monitor boxes
was removed and placed into a lead coffin.
The fields around the coffin prior to the |
7x |
37
|
Friday, February 21, 2014, 15:58 |
Bevan Moss | Cyclotron | Standard Operation | Old Monitor Box Removed, New installed | During the electrical test the was no contact.
To help investigate further the Montitor
box was removed from the Cyclotron. It was |
|