  84   Friday, April 17, 2015, 15:11 Keith C NgM9Developmentm9 t2 alignment jobToday: Restored filler shielding in T2
M9 Q1Q2 hole.
- Blocks marked with beam direction
 6x 
  85   Friday, January 29, 2016, 17:08 Keith C NgPrimary BeamlinesMaintenance4VVR1 RemovalToday:
Disconnected and removed 4VVR1 gate
valve and removed from beamline.
  
  86   Friday, February 05, 2016, 08:48 Keith C NgPrimary BeamlinesMaintenance4VVR1 RemovalReturned work permit C2016-01-27-2 due
to tank lid being raised and elevated fields
make the work area un-favourable to work
  
  87   Thursday, February 18, 2016, 16:34 Keith C NgPrimary BeamlinesDevelopmentVault beam line 4V disassemblyDisconnected all 4V beamline joints. Parts
for indium joints removed except for the
Q1 to downstream monitor box and monitor
  
  88   Friday, February 19, 2016, 14:03 Keith C NgPrimary BeamlinesDevelopment4V CM1 blankingContinued with work blanking off CM1 flange.
- Placed lead shot on left and right
side of the CM1 flange to lower fields. No
 20160219_beamline4v_P1030499.JPG 
  89   Monday, February 22, 2016, 16:09 Keith C NgPrimary BeamlinesDevelopment4V CM1 blanking 
Rolled
indium into new blanking plate turned down
 20160222_beamline4v_P1030502.JPG20160222_beamline4v_P1030511.JPG20160222_beamline4v_P1030505.JPG20160223_4VCM1_blank_off_inspection_report.pdf 
  90   Friday, March 04, 2016, 16:05 Keith C NgPrimary BeamlinesDevelopmentvault beamline 4 disassembly 
Attempted
to remove RH parts between Q1, 2 and monitor
  
  93   Thursday, March 31, 2016, 15:32 Keith C NgPrimary BeamlinesDevelopment1VM3 to 1VQ4 joint.Re-installed indium vacuum joint for 1VQ4,
routing installation. R. Kuramoto sprayed
silicone grease on to the threads and bushings
  
  94   Monday, January 30, 2017, 12:01 Keith C NgM9DevelopmentT2 leak check with vac groupWeek
of Jan 23 to 27:
 
  
  95   Wednesday, February 01, 2017, 15:34 Keith C NgM9DevelopmentT2 M9 SetupFinished setting up work area around T2
M9 front end.
 
 t2m920170201_143714_1032.jpg 
  96   Friday, February 03, 2017, 14:57 Keith C NgM9DevelopmentRemoving shield blocks and leak check results.Removed temporary shielding blocks from
M9 hole and placed in temporary bunker. Capped
with 18' shielding block. Blank off ready
 t2m920170203_140114_0604.jpgt2m920170203_120314_0686.jpgLocal_leak_check_Jan_27_2017.pdf 
  97   Tuesday, February 07, 2017, 15:36 Keith C NgM9Developmentt2 m9 job - Removed blank off from t2 m9 port,
had to pry off with screw driver via spring
ears. Clean removal it seems.
 20170207_rh_shutdown_log.pdf 
  98   Thursday, February 09, 2017, 16:14 Keith C NgM9Developmentt2 m9 alignmentPrepared m9 and b1 flanges for accepting
their target jigs. The target jigs need to
be reset by alignment group, 15" was
 20170209_t2m9alignment_P1030588.JPG20170209_t2m9alignment_P1030586.JPG 
  99   Friday, February 10, 2017, 15:53 Keith C NgM9Developmentt2 m9 jobInstalled all jigs and Alignment group
did their shoots successfully. Used individual
pins on the 15" target jig and worked
 20170210_t2m9alignment_P1030604.JPG 
  100   Tuesday, February 14, 2017, 16:08 Keith C NgM9DevelopmentT2 M9 2015 vs 2017 comparisonAttached a quick comparison of M9 exit
port flanges WRT indium remnants: looks roughly
the same. Will attempt to install blanking
 20170214_t2m9alignmentflangecomparison.pdf 
  101   Wednesday, February 15, 2017, 15:36 Keith C NgM9Developmentt2 m9 blank offInstalled the blank off on the T2
M9 exit port:
 20170215_shutdown_log_photos.pdf 
  102   Friday, February 17, 2017, 13:33 Keith C NgM9DevelopmentT2 M9 vacuumLeak checked the blank off at T2 M9 exit
port with Dimo Y. and Edi D.V. (Vac Group)
and they confirm it is leak tight. Blank
  
  103   Monday, February 20, 2017, 15:58 Keith C NgM9Developmentt2 m9 job wrap upRestored shielding to T2 M9 void, blocks
seem more crooked compared to previous years.
 20170220_t2m9alignment_P1030616.JPG20170220_t2m9alignment_P1030621.JPG 
  104   Wednesday, March 08, 2017, 16:05 Keith C NgPrimary BeamlinesRepaircollimator joint repairStarted uncovering the area above the T2
to Q13 joint:
 
 t2m920170308_114226_1136.jpgt2m920170308_151426_1438.jpg 
  105   Thursday, March 16, 2017, 15:50 Keith C NgPrimary BeamlinesRepaircollimator b transition to t2On Monday found leaking joint was the ring
directly downstream of T2. Vacuum group has
been spraying Vacseal (http://www.vacseal.net/Pages/default.aspx)
 20170316_collimatorb_RHB_8023.JPG20170316_collimatorb_RHB_8025.JPG 