91
|
Wednesday, March 16, 2016, 17:19 |
Ron Kuramoto | Primary Beamlines | Development | 4VQ3 Removal | On 8March2016, under W/P C2016-03-08-2,
4VQ3 was lifted out of BL4V with the vault
orbit crane where it was first weighed then |
|
|
92
|
Wednesday, March 16, 2016, 17:57 |
Ron Kuramoto | Primary Beamlines | Development | 4VQ1&Q2 Removal | On 14March2016, 4VQ1&Q2 were
removed from BL4V and lowered into the Vault
basement B3 level where they were stored |
13x |
|
119
|
Tuesday, April 16, 2019, 11:19 |
Ron Kuramoto | Primary Beamlines | Repair | 1AQ14 B/L Flange Broken Thermocouple | On March 7,2019 the Thermocouple (TC) cable
which monitors the temperature of the 1AQ14
B/L vacuum joint was broken when the iron |
|
|
2
|
Tuesday, February 14, 2012, 16:29 |
Keith C Ng | M20 | Repair | m20 q1 q2 repair | Warm cell reconfigured for water leak repair
at coil termination. Radiation surveys done.
M20 Q1 ready for removal of insulators. |
|
|
3
|
Thursday, February 16, 2012, 08:08 |
Keith C Ng | M20 | Repair | m20 q1 q2 repair | Insulators # 6,7,8 removed from Q1 headers
late afternoon by C Ballard. Ready for removal
and re-brazing of #7 joint some time today. |
|
|
4
|
Thursday, February 16, 2012, 16:22 |
Keith C Ng | M20 | Repair | m20 q1 q2 repair | Old #7 coil fitting removed, replaced and
re-brazed today by M Good. Insulators ready
to go back on to magnet coils to be pressure |
|
|
5
|
Friday, February 17, 2012, 15:35 |
Keith C Ng | M20 | Repair | m20 q1 q2 repair | Reinstalled ceramic insulators #6 7 8 to
Q1 magnet by C Ballard. #6 and 8 went on
with no issues. The copper tubing on insulator |
|
|
6
|
Thursday, March 01, 2012, 16:01 |
Keith C Ng | Primary Beamlines | Repair | 2C Rad Hard Valve Replacement | 4" indium flanges at the 2C rad hard
valve were cleaned of the remaining indium
by C. Ballard. Both upstream and down stream |
|
|
8
|
Thursday, October 11, 2012, 16:40 |
Keith C Ng | M9 | Repair | m9 t2 joint repair | Today:
Bridge setup complete; Noticed 12
x 3 x 3 block when placed on top of several |
|
|
9
|
Friday, October 12, 2012, 15:12 |
Keith C Ng | M9 | Repair | M9 T2 Joint Repair cont. | Joint repair continues.
Leak Check: |
|
|
10
|
Monday, October 15, 2012, 17:03 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Today:
- Removed pins and removed indium
through ring. Joint fully open at 14.5 to |
|
|
13
|
Thursday, October 18, 2012, 08:26 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Yesterday:
Installed indium blank off at M9
T2 joint and pumped down at 15:20 to 15:45 |
|
|
14
|
Thursday, October 18, 2012, 16:28 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Today:
Completed leak check of M9 T2 area:
joint(s) are He leak tight. Remote He lines |
|
|
15
|
Friday, October 19, 2012, 16:48 |
Keith C Ng | M9 | Repair | M9 T2 Joint Repair cont. | Today:
Cleaned up work site and removed
extraneous poles and tooling. Radioactive |
|
|
17
|
Monday, October 22, 2012, 15:48 |
Keith C Ng | M9 | Repair | M9 T2 clean up and shield restoration | Today;
Restoring shielding at M9 T2 area
and cleaning up RH setup. |
|
|
18
|
Wednesday, October 24, 2012, 11:53 |
Keith C Ng | M9 | Repair | M9 T2 blank off complete | Shielding around m9 t2 restored as of 11:45,
vacuum levels still the same since 19 October.
- Work permit returned. |
|
|
19
|
Friday, January 11, 2013, 15:44 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | Assisted vacuum group with removing 1AVA8:
- uncovered valve area and set up
remote handling bridge over valve. |
|
|
20
|
Monday, January 14, 2013, 16:36 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | continued with o ring replacement, replaced
all relevant o ring seals on valve (valve
body seal and actuator arm dynamic seals). |
|
|
21
|
Tuesday, January 15, 2013, 16:37 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | Job completed today and shielding block
over valve restored.
- He leak checked valve and accessible |
|
|
22
|
Wednesday, January 16, 2013, 17:03 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair | Moved 18' blocks away from triplet area
in preparation for uncovering triplet. Plastic
laid down up stream of t2 target station |
|