458
|
Tuesday, September 17, 2019, 13:25 |
Aaron Schmidt | | | LP-SIS | Problems resolved | Turbo pump / roughing troubleshoot. | Swapped out VCRs on HS to tray connection.
(Right one felt slightly off)
Tuesday, September 17, 2019, 13:23: |
|
459
|
Thursday, September 26, 2019, 14:03 |
Aaron Schmidt | Nb | 41882-3 | TARGET BOAT | In progress | HS swap & test Nb target | HS# 42752-7
Thursday, September 26, 2019, 13:46:
Remove Flexible lines HS |
|
463
|
Tuesday, October 08, 2019, 14:16 |
Aaron Schmidt | SiC | | HP-FEBIAD | In progress | Temp measurements. | Tuesday, October 08, 2019, 14:14: Remove
Flex line HS.
HS: 42752-1 |
|
466
|
Friday, November 15, 2019, 13:26 |
Aaron Schmidt | SiC | | HP-FEBIAD | Problems resolved | Temp map testing - 1. (Leak issue) | HS 42752-5 - Setup for Temperature
mapping.
Friday, November 15, 2019, 13:26: |
|
467
|
Thursday, November 21, 2019, 08:10 |
Aaron Schmidt | SiC | | HP-FEBIAD | In progress | Temperature mapping. | Thursday, November 21, 2019, 08:09:
PS on. Leak issue resolved (Evap 2 Elog 466).
Vacuum @ 4.10e-07T. |
|
470
|
Monday, November 25, 2019, 11:35 |
Aaron Schmidt | | | | In progress | Flex - line HS installed | Leak noted on previous TaC sintering
on HP FEBIAD # 42464-3.
Swapped out gaskets on HS flex line |
|
474
|
Tuesday, December 03, 2019, 08:24 |
Aaron Schmidt | | | LP-FEBIAD | In progress | Temperature mapping. | Tuesday, December 03, 2019, 08:15: Waterlines
opened. Vacuum ok @ 4.06e-07T
Tuesday, December 03, 2019, 08:23: |
|
475
|
Wednesday, March 04, 2020, 14:33 |
Aaron Schmidt | | | | Maintenance | PS swap out | The TGHT PS was found to be defective.
It was uninstalled w/ Joel S: |
|
481
|
Wednesday, May 20, 2020, 07:18 |
Aaron Schmidt | | | | | Check Evap 2 | Gradually open waterlines under vacuum
after period of no use.
Wednesday, May 20, 2020, 07:17: Vacuum |
|
486
|
Monday, June 01, 2020, 12:03 |
Aaron Schmidt | Ta | 44139-13 | LP-SIS | In progress | Ta#60 Conditioning | Ta#60 LP-SIS target
description: |
|
489
|
Monday, July 13, 2020, 11:03 |
Aaron Schmidt | | | | | Pump down / leak / vacuum check. | Darwin reported that he was unable
to achieve vacuum of 150mTorr. The flex-line
HS had been removed last week for modifications. |
|
494
|
Wednesday, August 05, 2020, 13:38 |
Aaron Schmidt | | | | | RP Swap on EVAP 2 | BP1 swapped with RP2 (TS beamline)
U-line installed.
Wednesday, August 05, 2020, 13:37: |
|
497
|
Wednesday, August 12, 2020, 08:58 |
Aaron Schmidt | | | | In progress | Install Flex line HS | Flex line HS installed. New SS gaskets.
Wednesday, August 12, 2020, 08:56:
Roughing (Check). |
|
506
|
Thursday, September 10, 2020, 07:53 |
Aaron Schmidt | Empty | 41790-8 | LP-FEBIAD | Done | Fernando FEBIAD / Anode testing. | FEBIAD installed. Anode PS installed.
ANODE connected!.
Leak check |
|
509
|
Thursday, September 24, 2020, 13:37 |
Aaron Schmidt | Nb | | TARGET BOAT | | Nb Test SRF group | Sample loaded into a vertical target boat.
Flex line HS removed, SS waterline HS installed
-AS. |
|
513
|
Tuesday, October 06, 2020, 14:23 |
Aaron Schmidt | Ta | 44508-1 | LP-SIS | In progress | Conditioning Ta#61 | Ta#61 LP-SIS target description:
Total Ta foils = 470 [6x20 packs |
|
514
|
Wednesday, October 07, 2020, 12:25 |
Aaron Schmidt | | | | In progress | IEVAP2:TP1 Swap out. | Wednesday, October 07, 2020
TP1 was not spinning up past 4krpm.
Stalling & tripping out. Examined with |
|
519
|
Wednesday, October 21, 2020, 14:39 |
Aaron Schmidt | Nb | 44508-2 | LP-SIS | In progress | Conditioning Nb#9 | Nb#9 LP-SIS target description:
|
|
524
|
Tuesday, November 24, 2020, 08:13 |
Aaron Schmidt | | | | | Flex - line HS installed | Monday, November 23, 2020, 17:01: Flex-line
HS installed.
Tuesday, November 24, 2020, |
|
527
|
Tuesday, February 09, 2021, 06:48 |
Aaron Schmidt | | NA | | Done | Ta coating test | Monday, February 08, 2021, 17:00: Installed
brackets w/ Ta wire and a small piece of
Re to test voltage drop. |
|