Message ID: 470     Entry time: Monday, November 25, 2019, 11:35
Author: Aaron Schmidt 
Target Material:  
Target Oven W.O#:  
Source:  
Status: In progress 
Subject: Flex - line HS installed 

 Leak noted on previous TaC sintering on HP FEBIAD # 42464-3.

Swapped out gaskets on HS flex line a re-tightened.

Monday, November 25, 2019, 11:31: Roughing.

Monday, November 25, 2019, 11:42: Turbo pump on. 

Monday, November 25, 2019, 13:38: Vacuum @ 7.29e-06T. 

Monday, November 25, 2019, 13:42: Waterlines opened. Vacuum slowly climbed to 7.57e-06T. Waterlines closed / purged. 

Monday, November 25, 2019, 13:47: Vacuum @ 6.83e-06T.

Monday, November 25, 2019, 13:50: Waterlines opened. Vacuum gradually climbed again. Waterlines closed / purged.

Monday, November 25, 2019, 13:51: Turbo pump off. 

Monday, November 25, 2019, 14:41: Vent. Check seals (All on HS line).

Monday, November 25, 2019, 14:48: Roughing. 

Monday, November 25, 2019, 15:06: Vacuum @ 1.22e-04T. Waterlines opened. Vacuum continued to pump down steadily to 8.86e-05T and dropping.

Monday, November 25, 2019, 15:07: Turbo pump off. 