644
|
Thursday, August 31, 2023, 07:09 |
Darwin Ortiz Rosales | TaC | 45447-4 | HP-FEBIAD | Done | TaC coating sintering | Thursday, August 31, 2023, 07:07
The coated container was wrapped in 3 Ta foil heatshields.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~500A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1= 7.7e-07 Torr
Thursday, August 31, 2023, 12:29
OMEGA=1238 C
IGP1=1.4e-06 Torr
Continue ramp
ramp @ 4A/min (2A/30s)
Thursday, August 31, 2023, 12:50
IGP1= 2.23e-06 Torr
OMEGA=1392 C
Thursday, August 31, 2023, 13:04
IGP1=2.7e-06 Torr
OMEGA=1443 C
Thursday, August 31, 2023, 13:18
IGP1= 3.8e-06 Torr
OMEGA=1537 C
Thursday, August 31, 2023, 14:38
OMEGA=1852C |
645
|
Tuesday, September 12, 2023, 09:54 |
Darwin Ortiz Rosales | TaC | 41369-2 | HP-SIS | Done | TaC coating sintering | Tuesday, September 12, 2023, 09:51
The coated container was wrapped in 3 Ta foil heatshield and left in evap2 over night to attain vacuum.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~700A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1= 2.7e-06 Torr
Tuesday, September 12, 2023, 7:00
Started autoramp @1A/min to 120A on both TGHT and TBHT
Tuesday, September 12, 2023, 09:53
Heating ramp set to 230A for both TGHT and TBHT. Rate at 2A/min for both heaters.
Tuesday, September 12, 2023, 11:21
Continued ramp on TGHT at 2A/min to 335A and now setting to 3A/min (1.5A/30s)
Tuesday, September 12, 2023, 11:47
|
TGHT |
|
Temperature ( C ) |
Voltage (V) |
Current (A) |
1205 |
5.5 |
392.0 |
Continue ramping @3A/min on TGHT
Tuesday, September 12, 2023, 13:33
Reached 1840 C at TGHT =677A and 10.5V
Will keep for 4 hours |
648
|
Friday, October 20, 2023, 07:24 |
Darwin Ortiz Rosales | TaC | 45447-11 | LP-SIS | Done | TaC coating sintering | Friday, October 20, 2023, 07:20
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial = 9.9 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 4A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Friday, October 20, 2023, 07:24
Starting initial ramp
Vacuum IGP1 initial = 9.9 e-07 Torr
Friday, October 20, 2023, 08:55
After initial pressure bump continued heating at 1A/min to 120A to observe any other possible pressure bump.
Friday, October 20, 2023, 09:05
increased ramp to 4A/min to 400 TGHT and 230 TBHT
Friday, October 20, 2023, 09:35
OMEGA=1280 C
TGHT= 221.5 A, 3.24V
TBHT=228.9, 3.9V
Friday, October 20, 2023, 10:22
OMEGA 1852 C at TGHT = 390A, 6.5 V ; TBHT = 232 A, 4.0 V
Will leave for 4 hours
Friday, October 20, 2023, 14:16
About to start rampdown
TGHT @ -2A/min
TBHT@ -1A/min
Final OMEGA = 1840 C
IGP1 = 1.83e-06 Torr |
649
|
Monday, November 06, 2023, 14:07 |
Darwin Ortiz Rosales | Empty | 45220-4 | LP-SIS | Done | TaC coating sintering | Monday, November 06, 2023, 09:59
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =3.1 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 2A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Monday, November 06, 2023, 14:07
OMEGA =1852 C
IGP1= 3.14e-06 Torr
TGHT= 399A, 6.6V
TBHT= 233A, 4.1V
Tuesday, November 07, 2023, 12:28
Cooled down previous evening and took out today.
rampdown was @-2A/min for TGHT and -1A/min TBHT |
650
|
Wednesday, December 06, 2023, 09:57 |
Darwin Ortiz Rosales | SiC | 45447-4 | HP-FEBIAD | Done | 231204SiC conditioning | Wednesday, December 06, 2023, 09:47
Target number of foils:370
Analysis discs 16 A and 16B interspersed on the end further from the laser
A are discs produced using new method and B are discs produced using milling.
Total length packed 16 cm (excluding the analysis discs)
container has 3 Ta heat shields (one inner around fins and center block, new type of 1st shield made up of three pieces)
No endcaps inserted to facilitate out-gassing
Ta coated spring at front end
ramp to 120A @ 1A/min TGHT and to 120A on TBHT hold there until pressure drop, then ramp to 500A on TGHT and 230A TBHT.
max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)
Then temperature = 1800C
TBHT will be set fixed at 230 A (max). TBHT heated manually and automatically to max.
Good vac at 5.00 e -4 Torr
Bad vac at 5.00 e-2 Torr
IGP1= 1e-06 Torr at start of initial ramp.
Wednesday, December 06, 2023, 09:56
System left to drop pressure over previous night and now at 120A. waiting for pressure drop.
Wednesday, December 06, 2023, 11:18
increased ramp rate to 2A/min
Wednesday, December 06, 2023, 14:41
increased ramp to 3A/min on TGHT and stopping to allow pressure to stabilize before taking temperature readings
Top temperature 1800C at 710 A but started dropping. Increased current to 750A and left there for 4 hours.
Cool down at -2A/min TGHT and -1A/min TBHT
|
651
|
Thursday, December 14, 2023, 09:58 |
Darwin Ortiz Rosales | SiC | 41369-2 | HP-SIS | Done | 231208SiC conditioning | Thursday, December 14, 2023, 09:53
Target left pumping down in Evap2 overnight.
Initial weight including protective jig = 1474.3 g
Total number of target foils:388
10 analysis discs: 5x 220727-2 labelled as A and 5x 231123-2 labelled as B on the right side (front) of container. Order of discs ABABABABAB.
Total length packed 15.5 cm
container has 3 Ta heat shields including the inner made of three pieces as to cover the center block.
No endcaps inserted to facilitate out-gassing
Ta coated spring at both ends
ramp to 500A @ 1A/min TGHT and to 230A on TBHT
max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)
Then temperature = 1800C
TBHT will be set fixed at 230 A (max). TBHT heated manually and automatically to max.
Good vac at 5.00 e -4 Torr
Bad vac at 5.00 e-2 Torr
IGP1= 9.3e-07 Torr at start of initial ramp.
Thursday, December 14, 2023, 09:56
Started initial ramp up 1A/min on both heaters
Thursday, December 14, 2023, 11:03
Pressure dropping. Will increase ramp speed to 2A/min on both heaters (1A/30s)
Thursday, December 14, 2023, 11:17
pressure dropping. Increase ramp to 4A/min (2A/30s)
Will stop and ramping for temperature measurements
Thursday, December 14, 2023, 13:28
Increased ramp to 5A/min (2.5A/30s)
Will heat to 703A on TGHT and leave for 4 hours |
Attachment 1: Screenshot_2023-12-14_133432.png
|
|
652
|
Friday, January 26, 2024, 07:06 |
Darwin Ortiz Rosales | TaC | 45447-1 | HP-FEBIAD | Done | TaC coating sintering | Friday, January 26, 2024, 07:05
The coated container was wrapped in 4 Ta foil heatshield and left in evap2 over night to attain vacuum.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~700A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1= 5.7e-05 Torr
Friday, January 26, 2024, 09:20
Pressure starts increasing at 125 A on TGHT and TBHT. Leaving it to equilibrate then will start ramping at 3A/min (1.5A/30s) to 700A on TGHT and 230A on TBHT
Friday, January 26, 2024, 13:18
leave sintering at 1838C . Will start rampdown at 5 pm.
IGP1= 6.10e-06 Torr
TGHT=680A, 10.14V
TBHT = 230A, 3.13V
Friday, January 26, 2024, 16:52
IGP1 = 3.0e10-6 Torr
OMEGA=1821 C
start rampdown @-2A/min TGHT and -1A/min TBHT |
653
|
Monday, January 29, 2024, 16:45 |
Darwin Ortiz Rosales | TaC | | LP-FEBIAD | Done | TaC coating sintering | Monday, January 29, 2024, 16:36
LP FEBIAD
wrapped in 4 Ta heatshields.
Will heat at 2A/min to 95A on TGHT and TBHT
Then will heat at 3A/min to 1800 C ~400A on TGHT and 230A on TBHT
Monday, January 29, 2024, 16:45
Initial IGP1= 5e-05 Torr
Monday, January 29, 2024, 20:35
1800C was at TGHT 410A, 6.9V RD and set current 418A
TBHT= 233 RD A, 3.2V
|
654
|
Wednesday, February 07, 2024, 22:49 |
Darwin Ortiz Rosales | TiC | 44692-11 | LP TUBE | Done | 240206TiC conditioning |
Wednesday, February 07, 2024, 22:36
Ta container tube TaC coated, wrapped in 4 Ta foil heat-shields, and loaded with 320 D shaped discs in a 12mm graphite cartridge with usable 11mm
Endcaps on the graphite cartridge have holes for outgassing
initial heating @ 2A/min to 90 A then 1A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Thursday, February 08, 2024, 06:18
Starting heat ramp tght
initial pressure = 8.1e-07 Torr IGP1
Thursday, February 08, 2024, 06:54
start of gasoff observed. paused ramp and will continue at 1A/min
Thursday, February 08, 2024, 07:24
lowered TGHT current to 75 A as pressure increasing too rapidly. will leave at this current until pressure drops
Thursday, February 08, 2024, 09:11
continuing ramp to 120A on TGHT
Thursday, February 08, 2024, 09:24
Increasing ramp to 2A/min to 250A on TGHT
Thursday, February 08, 2024, 10:52
Increased ramp to 3A/min to 250A on TGHT
Thursday, February 08, 2024, 11:10
Everything looks good will continue to 300 A at 3A/min TGHT
Thursday, February 08, 2024, 11:33
Pausing heating at 285A, 4.8V TGHT
OMEGA reads 1430C
Will let pressure drop and then proceed ramping slowly @ 0.2A/min
Thursday, February 08, 2024, 13:53
IGP1= 2.4e-06 Torr
OMEGA = 1432 C
ramp at 0.2A/min towards 1550C
Thursday, February 08, 2024, 14:07
pressure very stable. will increase to 0.4 A/min
Thursday, February 08, 2024, 15:24
increasing ramp rate to 1A/min
IGP1 = 2.5e-06 Torr
Thursday, February 08, 2024, 18:05
1900 C on OMEGA
will leave 3-4 hours depending on pressure
Thursday, February 08, 2024, 21:10
No additional pressure peaks observed and pressure on IGP1= 1.9e-06 Torr
TGHT= 460 A, 8.1V
OMEGA= 1860 C
ramp down at -2A/min
|
655
|
Wednesday, February 21, 2024, 06:23 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240220TiC conditioning | Wednesday, February 21, 2024, 06:22
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with 201 D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 90 A then 1A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Wednesday, February 21, 2024, 09:12
IGP1 initial = 9e-07 Torr
Starte at 3A/min to 90A
Wednesday, February 21, 2024, 09:21
increased autoramp to 4 A/min until pressure starts rising, then will slow down or pause
Wednesday, February 21, 2024, 09:32
At 74A, paused. Will continue at 2A/min TGHT
Wednesday, February 21, 2024, 09:40
Pausing at 87A.
Wednesday, February 21, 2024, 10:34
pressure dropping. restarting ramp up to 120A at 2A/min
Wednesday, February 21, 2024, 10:37
From previous TiC 220206, will heat up fast until 250A and then at 1A/min until 300A to better resolve out-gassing profile
Wednesday, February 21, 2024, 12:05
Changed ramp to 1A/min to 300A
Wednesday, February 21, 2024, 13:10
Manually ramped up for a while
increased ramp speed to 2A/min
regression line started to match previous one after 1300C
Wednesday, February 21, 2024, 13:16
increased ramp rate to 4A/min to 420A
Wednesday, February 21, 2024, 13:37
Note: the temperature became unrealistic. suspect window condensate. Will use regression and to to 441A
Wednesday, February 21, 2024, 13:54
reached 441A, 7.6V
leaving for 3.5 hours or when pressure drops to 2-3 e-06 Torr
Wednesday, February 21, 2024, 18:56
IGP1=2.9e-06 Torr
starting rampdown at -2A/min |
656
|
Thursday, February 29, 2024, 07:40 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240228TiC conditioning | Thursday, February 29, 2024, 07:40
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Thursday, February 29, 2024, 07:43
Initial IGP1= 9.31e-7 Torr
Thursday, February 29, 2024, 17:43
Temperature profile suggests 1900 C at 400A. Now at 400A. Will keep at this current for 4 hours.
manually ramped the last few amps.
TGHT= 400A, 7.3 V OMEGA = 1901C
Thursday, February 29, 2024, 22:20
IGP1=2.1e-6 Torr
started ramping down at -2A/min
|
Attachment 1: TiC_240228_Conditioning_Temperature_vs_Current.png
|
|
657
|
Wednesday, April 03, 2024, 06:46 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240402TiC | Wednesday, April 03, 2024, 06:46
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Wednesday, April 03, 2024, 06:49
initial IGP1= 1.28e-06 Torr
Wednesday, April 03, 2024, 09:26
IGP1= 2.3e-05 Torr
TGHT = 78 A, 1.3V
Will continue ramp as planned.
Wednesday, April 03, 2024, 11:37
Ramping at 2A./min to 400A
Wednesday, April 03, 2024, 14:01
expected 1900C at 401A
leaving at 402A for 4 hours. Rampdown start at 4:10 pm at -2A/min |
658
|
Thursday, April 04, 2024, 12:07 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240404TiC sintering/conditioning | Thursday, April 04, 2024, 12:06
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13 (4th conditioning with this tube)
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Mas current~400A (1900 C)
Friday, April 05, 2024, 09:04
Ramping to 85A done and pressure trending down. Will continue ramp to 120A
Friday, April 05, 2024, 16:01
Starting rampdown at -2A/min
IGP1= 3.2e-06 Torr
|
659
|
Friday, April 26, 2024, 06:19 |
Darwin Ortiz Rosales | TaC | 45447-29 | HP-SIS | Done | TaC coating sintering |
Monday, April 29, 2024, 19:50
Started coating with coating stand.
The coated container was wrapped in 3 Ta foil heatshields.
Vacuum IGP1 initial =9.1 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~700A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 2A/min to =700 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Monday, April 29, 2024, 20:25
Reached 1810 @700A
Will leave until 1230am |
660
|
Wednesday, May 01, 2024, 11:54 |
Darwin Ortiz Rosales | TaC | 25447-27 | HP-SIS | Done | TaC coating sintering | Wednesday, May 01, 2024, 11:53
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =8.1 e-06 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~500A (adjustable)
Heating autoramp starged at 3A/min(1A/30s) on TGHT 100A
Then at 2A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Wednesday, May 01, 2024, 22:19
1830C reached at 670A. 10.0V TGHT
Start cooling after 4 hours. |
661
|
Tuesday, May 07, 2024, 06:20 |
Darwin Ortiz Rosales | TaC | | TARGET BOAT | Done | Sintering TaC coating on endcaps | Tuesday, May 07, 2024, 06:16
TP was swapped on previous day (May 6th)
protective screen installed.
Loaded 9 TaC coated end caps (groups of 4 and 5) and 2 TaC coated springs.
OMEGA Slope 0.99
Will heat to 1850-1900 C and hold for 4 hours
Good Vac = 5.0e-4 Torr
Bad Vac= 5.0 e-02 Torr
Initial IGP1=6.7E-07 Torr
|
662
|
Monday, May 27, 2024, 07:12 |
Darwin Ortiz Rosales | SiC | | LP TUBE | Done | SiC (PAA dispersant experiment) | Monday, May 27, 2024, 07:09
Small graphite cartridge was loaded with SiC discs 240523-1 and 240523-2. Discs produced without milling using PAA as a dispersant.
The coated container tube was wrapped in four Ta foil heatshields.
two Tac Coated springs at the ends in case plugs are pushed outwards.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final TGHT current= ~400A (adjustable)
Heating autoramp 2A/min to 90 A
Then at 2A/min to 120A.
Good vacuum = 5.0 e-02 Torr
Bad vacuum = 5.0E-04 Torr
IGP1 initial 4.8e-07 Torr
Monday, May 27, 2024, 09:13
Pressure started coming down. Heat at 2A/min to 120A.
Monday, May 27, 2024, 10:21
Started ramp 2A/30s to 400A will monitor temperature
stopped at 490A and will hold for 4 hours.
Monday, May 27, 2024, 12:41
temperature started creeping up past 1870C so decreased current to 461A
Current temperature is 1842 C at 461A, 7.6V
Monday, May 27, 2024, 12:55
dropped current to 441 because temperature climbed to 1899 C
Monday, May 27, 2024, 15:08
final pressure IGP1 =9.9 e-07 Torr
OMEGA= 1830 C at 410 A (reduced as needed)
Start rampdown at -2A/min
Wednesday, May 29, 2024, 10:07
Final pressure is 2.7e-7 Torr
Wednesday, May 29, 2024, 14:42
Experiment failed. Too hot probably. Bad temperature readings. Will repeat after redesigning experiment. |
663
|
Wednesday, May 29, 2024, 22:55 |
Darwin Ortiz Rosales | SiC | | LP TUBE | Done | Repeat of SiC experiment with mixed only casts | Wednesday, May 29, 2024, 22:52
Small graphite cartridge was loaded with SiC discs 240523-1 and 240523-2 and 220727-2 (baseline discs). Test Discs produced without milling using PAA as a dispersant.
The coated container tube was wrapped in four Ta foil heatshields.
two Tac Coated springs at the ends in case plugs are pushed outwards.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final TGHT current= ~400A (adjustable)
Heating autoramp 2A/min to 90 A
Then at 2A/min to 120A.
Good vacuum = 5.0 e-02 Torr
Bad vacuum = 5.0E-04 Torr
IGP1 initial 4.8e-07 Torr
Wednesday, May 29, 2024, 22:54
Kept at 400 A for 4 hours.
Starting autoramp down at -2A/min
|
664
|
Wednesday, June 05, 2024, 07:18 |
Darwin Ortiz Rosales | SiC | | LP TUBE | Done | sinterin experiment 240604 | Wednesday, June 05, 2024, 07:14
SiC discs loaded into tantalum tube. New mixing (two types) and old mixing.
The coated container tube was wrapped in four Ta foil heatshields.
Tac Coated springs at the ends in case plugs are pushed outwards.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:=* 0.980*
Target time at max temperature = 4 hours
Final TGHT current= ~400A (adjustable)
Heating autoramp 1A/min to 90 A
Then at 2A/min to 120A.
Good vacuum = 5.0 e-02 Torr
Bad vacuum = 5.0E-04 Torr
IGP1 initia1.3e-06Torr
Wednesday, June 05, 2024, 11:04
Continuing to ramp at 2A/min to 350A
Wednesday, June 05, 2024, 12:22
Leaving at 369 A for 4 hours (until 4 pm). Temperature readings do not appear good.
Wednesday, June 05, 2024, 16:01
Start rampdown at -2A/min
IGP1=2.0 e-6 Torr |
667
|
Friday, July 26, 2024, 10:05 |
John Wong | np-Ta | | TARGET BOAT | Done | Carbonization of Heat Stabilized np-Ta Fibres Disk (1st Attempt) |
Angelina Chen wrote: |
Thursday, July 25, 2024, 15:18
Target container consists of two np-Ta fibres disk samples. Both disks are made from heat stabilized np-Ta fibres (150 C for 17 hours) and were pressed at 8 tons / 300 MPa.
Sample 1 was made from np-Ta fibres spun using Dope solution #1. The sample 1 disk has an average thickness of 0.727 mm and a diameter of 17.113 mm. The mass of the green sample 1 disk is 0.1957 g.
Sample 2 was made from np-Ta fibres spun using Dope solution #6. The sample 2 disk has an average thickness of 0.688 mm and a diameter of 17.123 mm. The mass of the heat stabilized fibres used to make the green sample 2 disk is 0.1860 g. The mass loss from pressing the heat stabilized fibres was virtually zero. Therefore, while the mass of the green sample 2 disk was not measured, it can be extrapolated to be 0.1860 g.
The target container was wrapped with Ta foil. Each sample disk was wrapped in graphite foil and placed inside the target container horizontally near the center.
The Omega slope was initially set to 0.980. After reviewing previous logbook on np-Ti
The chamber is currently being pumped down. The current reading (as of 15:40) is 4.70e-05 Torr.
Two heating schedules will be tested. Heating schedule 1 entails heating both sample disks at ~1000 C until the pressure reaches below 1.00e-06 Torr. Once heating schedule 1 is completed, sample 1 will be removed. Heating schedule 2 entails heating sample 2 to ~1800 C until the pressure reaches below 1.00e-06 Torr. TGHT is estimated to be approximately 440A/7.6V to reach 1875 C (348A/5.8V to hold temperature at 1600 C). Refer to e-log ID#605.
|
Friday, July 26, 2024, 09:52
Chamber has been pumped down overnight, pressure currently at 1e-6 Torr.
Initiate auto ramping 1A/min to reach 200 A.
Good vac = 3 e-5 Torr
Bad vac = 5 e-5 Torr.
Continue to monitor.
Friday, July 26, 2024, 17:06
Gas evolution has seen observed to be completed as TGHT slowly ramping up. Temp is currently reading at 1015 C, TGHT 164A/2.43V. Pressure holding at 2.4e-6 Torr but slowly coming down, see attachment 1. Will keep this setting and cool it down on Sunday.
Sunday, July 28, 2024, 11:27
Temperature has been holding sturdy at ~1000C for over 36 hours, TGHT at 164A/2.59V (a slight increase in the voltage). Pressure is currentlyat 4.5e-7 Torr (see attachment #2 for the archiver).
Ramping down TGHT at 1A/min.
Will remove both samples on Monday to measure the mass loss. Sample 1 will be analyzed. Sample 2 will be loaded back to the Evap 2 for further heating to reach about 1800 C.
Monday, July 29, 2024, 14:29
Both samples were removed from the chamber and measured for weight loss, and Sample 2 was put back for further heating; Thanks Darwin for helping up with this.
Chamber is currently pump down, pressure at 6.0e-5 Torr. Will ramp up TGHT once the pressure has come down to 10e-6 Torr.
Monday, July 29, 2024, 16:52
Pressure at 6.5e-6 Torr. Ramping up TGHT at 2A/min to reach 164A (previous setting at ~1000C).
Tuesday, July 30, 2024, 09:02
Temperature has been holding at about 1000C. THGT at 160A(readback,, 164A setpoint)/2.56V. Pressure 7e-7 Torr.
Stepping up 1A/min in 20A increment to reach 1800C.
Continue to monitor.
Tuesday, July 30, 2024, 10:07
Plotting out THGT (readback) vs Temp:
181 A/2.91V, 1070C
206A/3.34V, 1153C
225A/3.7V, 1213C
245A/4.1V, 1277C
Wednesday, July 31, 2024, 11:26
TGHT tripped off due to HS water flow NOT oK, Attempted to clear it but did not work, see attachment #3.
Will stop the process for now and investigate the problem.
Wednesday, July 31, 2024, 12:10
Darwin helped to check the surrounding of the lab for water leaks; everything was good and the chamber remained under vacuum.
All the water paddle wheels were moving. A slight touch of the HS paddle wheel somehow cleared the interlock. Maybe the connection was loose.
We checked all the paddle wheels by shutting and opening the water valves. All the interlocks responded correctly.
Continue with the heating process...
Ramping up TGHT at 2A/min to reach 300A.
Wednesday, July 31, 2024, 15:27
TGHT vs temp:
294A/5.1V 1477C
343A/6.0A, 1633C
402A/7.2V, 1818C
Will keep TGHT at 410A (setpoint) for night.(see attachment#4)
Tuesday, August 06, 2024, 10:00
Venting Evap 2; the process is done.
The sample will be analyzed.
|