Wednesday, November 16, 2016, 16:41, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_13
|
John Wong wrote:
|
Tuesday, November 29, 2016, 16:20, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_14
|
Tuesday, November 29, 2016, 16:13
UO2/C green was prepared Nov 23rd, 2016.
The cast peeled off the glass nicely Nov 24th, 2016 and finished drying over the weekend. |
Thursday, February 16, 2017, 15:09, Laura Lambert, UC2, 42218-12, LP-SIS, Done, Conditioning UCx#19
|
Thursday, February 16, 2017, 15:04
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block |
Friday, March 03, 2017, 15:51, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_15
|
Friday, March 03, 2017, 08:53
UO2/C green was prepared Feb 28th, 2017.
The cast peeled off the glass nicely March 2nd, 2017 and loaded into evap1. |
Thursday, April 20, 2017, 11:41, Laura Lambert, UC2, 42218-1, LP-IG-LIS, Done, Conditioning UCx#20 6x
|
Thursday, April 20, 2017, 11:31
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block |
Tuesday, May 30, 2017, 07:43, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, processing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS
|
Laura Lambert wrote:
|
Monday, June 12, 2017, 15:07, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_17
|
Monday, June 12, 2017, 11:41
UO2/C green was prepared June 7th, 2017.
The cast peeled off the glass nicely June 8th, 2017. |
Thursday, July 20, 2017, 15:57, Laura Lambert, UC2, 42218-15, LP-SIS, Done, Conditioning UCx#21
|
Laura Lambert wrote:
|
Wednesday, August 23, 2017, 15:54, Laura Lambert, UO2/C, 40282-2, TARGET BOAT, Done, Carbonizing UC2 discs for 1stepUCx in graphite sample container _#1
|
Wednesday, August 23, 2017, 15:41
2 rounds of UO2/C were cast onto a graphite sheet in the fume hood and let dry.
For this round of samples, circles from cast 1 were used |
Thursday, September 21, 2017, 11:35, Laura Lambert, Empty, , , Done, Testing TBHT [1st run!], RP [new oil] and IG [new gauge]
|
Thursday, September 21, 2017, 11:32
Copper plate attached to TBHT to allow current to be applied.
Started pumping down this a.m. |
Wednesday, September 27, 2017, 12:05, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_18
|
Wednesday, September 27, 2017, 09:25
UO2/C green was prepared Sept 20th, 2017.
The cast peeled off the glass Sept 22nd, 2017 - not quite enough 'special' ingredient. |
Tuesday, October 10, 2017, 14:16, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, Processing UC2Flk_19
|
Tuesday, October 10, 2017, 14:11
UO2/C green was prepared Oct 4th, 2017
The cast peeled off the glass nicely Oct 6th, 2017 |
Tuesday, November 07, 2017, 14:38, Laura Lambert, Empty, , LP-FEBIAD, Done, TBHT test with LP-FEBIAD
|
Tuesday, November 07, 2017, 14:34
LP-FEBIAD used several years ago for temperature measurements is used for this test.
3xTa heat shields on container, incl center block - these heat shields have remained on there since the last round of tests in 2014? |
Tuesday, November 14, 2017, 16:16, Laura Lambert, UO2/C, 40282-2, TARGET BOAT, Done, Carbonizing UC2 discs for 1stepUCx in graphite sample container _#2
|
Tuesday, November 14, 2017, 16:12
Circles from cast 1 were used, the same as the last round of 1stepUCx [see elog i.d. 164]
A 14mm punch was used to punch out circles from the cast. |
Thursday, November 23, 2017, 13:39, Marla Cervantes, UO2/C, 40282-2 , TARGET BOAT, Done, Carbonizing UO2/C discs for 1stepUCx in graphite sample container _#3
|
Thursday, November 23, 2017, 13:34
Circles from cast 1 were used, the same as the last round of 1stepUCx [see elog i.d. 164]
A 14mm punch was used to punch out circles from the cast. |
Wednesday, January 17, 2018, 13:47, Marla Cervantes, UO2/C, 40282-1, TARGET BOAT, Done, Carbonizing UO2/C discs for 1stepUCx in graphite sample container _#5
|
Monday, January 15, 2018, 13:37
35 circles of 14 mm diameter were packed into a graphite sample container.
35 x UO2/C circles = 5.58 g |
Thursday, January 18, 2018, 11:56, Marla Cervantes, UO2/C, 40282-2 , TARGET BOAT, Done, Carbonizing UO2/C discs for 1stepUCx in graphite sample container TP1-off_#4
|
Laura Lambert wrote:
|
Tuesday, January 23, 2018, 12:49, Marla Cervantes, UO2/C, 40282-2 , TARGET BOAT, Done, Carbonizing UO2/C discs for 1stepUCx in graphite sample container_#6
|
Marla Cervantes wrote:
|
Tuesday, January 30, 2018, 16:07, Marla Cervantes, UO2/C, 40282-2 , TARGET BOAT, Done, Carbonizing UO2/C discs for 1stepUCx in graphite sample container _#7
|
Marla Cervantes wrote:
|
Thursday, February 01, 2018, 13:15, Marla Cervantes, UO2/C, 40282-1, TARGET BOAT, Done, Carbonizing UO2/C discs for 1stepUCx in graphite sample container _#8
|
Thursday, February 01, 2018, 12:59
35 circles of 14 mm diameter were packed into a graphite sample container.
28 discs corresponded to cats#1 and 7 discs to cast#2 |
|