Entry  Tuesday, May 23, 2017, 15:51, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, In progress, processing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS UCxFlk_16_temp_readout.jpg
    Reply  Friday, May 26, 2017, 15:23, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Problems, processing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS 6x
       Reply  Friday, May 26, 2017, 16:09, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, In progress, processing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS 
          Reply  Monday, May 29, 2017, 08:54, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Problems, processing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS evap1_tripped_off_roud2_UCxFlk_16.jpgevap1_tripped_off_roud2_UCxFlk_16(2).jpg
             Reply  Tuesday, May 30, 2017, 07:43, Laura Lambert, UO2/C, 40282-1, TARGET BOAT, Done, processing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS 
Message ID: 152     Entry time: Tuesday, May 30, 2017, 07:43     In reply to: 151
Author: Laura Lambert 
Target Material: UO2/C 
Target Oven W.O#: 40282-1 
Source: TARGET BOAT 
Status: Done 
Subject: processing UC2Flk_16 - 1ST TEST CHANGING VACUUM LIMITS 

Laura Lambert wrote:

Laura Lambert wrote:

Laura Lambert wrote:

Laura Lambert wrote:

 Tuesday, May 23, 2017, 14:42

UO2/C green was prepared May 16th, 2017.

The cast peeled off the glass nicely May 17th, 2017.

Initial UO2 powder used = 50.25g (Inventory R-01032A, UO2 + bottle = 876.80g before use)

Graphite powder used = 10.32g

Green cast dried UO2/C + organic mass = 61.70g 

The green was rolled up and wrapped in a piece of graphite sheet.

The Ta-target boat was wrapped with 1 long layer of heat shield and installed in evap1 today.

Chamber pumped down today.

Target boat will be ramped up to 520A at the rate of 0.1A/min.

Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr.

IG1 = 4.80e-6 Torr

Tapped up to 30A, 0.45V

Waited ~1hr, vacuum stable.

IG1 = 8.3e-6 Torr

Initiating auto-ramp


 Wednesday, May 24, 2017, 09:26

IG1 = 5.5e-5 Torr

TGHT = 64A, 0.72V

Vacuum currently yo-yo-ing.

Changing vacuum limits to attempt to speed up process.

Vacuum limit stop at 1.0e-4 Torr, backing off at 5.0e-4 Torr.

Once vacuum settles and vacuum starts to drop will adjust limits again accordingly.


 Wednesday, May 24, 2017, 11:17

IG1 = 1.2e-4 Torr

TGHT = 69A, 0.74V

TGHT direct readout = 66A, 0.73V

Thermometer attached to TP = 41.0C

Room temp = 24.0C


Wednesday, May 24, 2017, 13:16 

Vacuum going well.

Stable yo-yo-ing at current vacuum limit.

TP = 41.5C, RT = 23.9C

IG1 = 1.2e-4 Torr

TGHT = 71A, 0.77V

Increasing vacuum limit stop to 2.0e-4 Torr.


Thursday, May 25, 2017, 13:03

Vacuum has stabilized.

TGHT = 188A, 1.85V

IG1 = 2.2e-5 Torr.

Adjusting vacuum limits so when 2nd phase starts, vacuum does not spike.

Vacuum limit stop at 5.0e-5 Torr, backing off at 1.0e-4 Torr.


 

 Friday, May 26, 2017, 13:40

Everything tripped off this morning at around 4:30am

This was not due to the vacuum spiking as one would expect.

No power bumps according to  ISAC controls.

Looking back on elogs  [see elog i.d. 145] evap1 had also tripped off during the last round of carbonizing UO2, however last time everything tripped off ~60A.

For last trip off the water valve remained open and on.

This time  WV1 showed yellow in the TGHT epics box, off under WV epics box, but black [open] in the WV epics box diagram [see screenshot for better understanding].

Water valves are closed - confirmed in person - water wheels not turning.

Trip-off occured ~275A.

Vacuum was stable at trip-off point; IG1 ~6e-6 Torr 

Reason: currently unknown.


 

 

 

 Friday, May 26, 2017, 15:43

Starting pumping down again this afternoon while trying to understand trip-off - no progress on that end.

IG1 = 4.9e-6 Torr

Tapped up to 40A, 0.24V

Vacuum spiked to 2e-5 Torr

Backed off to 35A, 0.20V

Showing lower voltage output than the last round that had tripped off...but ramping is so early on/ low current, hard to tell...

Vacuum stable.

IG1 = 5.4e-6 Torr

Target boat will be ramped up to 275A [trip-off point] at the rate of 0.1A/min.

Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr.

 

TP = 37.9C, RT = 25.2C


 

 Monday, May 29, 2017, 08:21

Initially it looks like not enough time had been allowed for the vacuum to settle before initiating the auto-ramp resulting in the vacuum spiking and tripping off the system.

A closer look shows that is not the case.

Note: the vacuum limits were set to stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr. 

 

The TGHT started to back off when the vacuum was ~6e-6 Torr, this is considered a good vacuum and should not have caused the system to initiate backing off yet.

Over the course of ~1min, evap1 had backed off all the way down to 0A.

At this point the vacuum was now up to ~1.75e-5 Torr and still rising.

~34min after the TGHT had reached 0A, the vacuum eventually reached 8e-4 Torr and tripped off the evaporator.

See photos attached.


 

 Tuesday, May 30, 2017, 07:41

Still unsure as to why evap1 tripped off again.

Put evap1 back under vacuum/ turned turbo pump on and opened isolation valve yesterday afternoon.

Vacuum good this morning...nothing tripped off...


 Tuesday, May 30, 2017, 08:21

IG1 = 2.3e-6 Torr

Tapped up manually to 40A, 0.24V

Waited ~1hr

IG1 = 4.5e-6 Torr

Initiated auto-ramp at 0.2A/min up to a final setpoint of 250A


 Wednesday, May 31, 2017, 09:37

IG1 = 2.4e-6 Torr

TGHT = 250A, 2.57V

Increasing max setpoint to 275A [the trip off point] at a rate of 0.2A/min

Vacuum is currently stable and low; increasing limits to:

Vacuum limit stop at 1.0e-4 Torr, backing off at 5.0e-4 Torr.


 Wednesday, May 31, 2017, 13:39

IG1 = 3.7e-6 Torr

TGHT = 275A, 2.80V

Increasing max setpoint to final setpoint of 520A at a rate of 0.2A/min

Vacuum is currently stable and low; keeping  current limits.


Wednesday, May 31, 2017, 15:57

IG1 = 8.14e-6 Torr

TGHT = 300A, 3.08V

Vacuum stable.

Decreasing ramping rate to 0.1A/min for overnight heating.

turbo pump = 40.5C; room temp = 25.1C


 Thursday, June 01, 2017, 09:00

IG1 = 4.2e-5 Torr

TGHT = 396A, 4.06V

Vacuum stable.

Increasing ramping rate to 0.2A/min.

turbo pump = 41.6C; room temp = 24.3C


 Thursday, June 01, 2017, 13:18

IG1 = 1.25e-4 Torr

TGHT = 439A, 4.48V

Vacuum stable.

Changing vacuum limits.

Vacuum limit stop at 2.0e-4 Torr, backing off at 5.0e-4 Torr.

turbo pump = 42.3C; room temp = 24.6C


 Thursday, June 01, 2017, 15:48

IG1 = 1.95e-4 Torr

TGHT = 467A, 4.81V

Vacuum stable.

Changing vacuum limits and ramping rate for heating overnight.

Decreasing ramping rate to 0.1A/min

Vacuum limit stop at 1.0e-4 Torr, backing off at 5.0e-4 Torr.

turbo pump = 44.1C; room temp = 25.3C


 Friday, June 02, 2017, 07:19

IG1 = 1.26e-4 Torr

TGHT = 473A, 4.77V

Vacuum stable.

Changing vacuum limits and ramping rate.

Increasing ramping rate to 0.2A/min

Vacuum limit stop at 2.0e-4 Torr, backing off at 5.0e-4 Torr.


 Friday, June 02, 2017, 10:18

IG1 = 2.04e-4 Torr

TGHT = 498A, 5.08V

Vacuum stable.

Changing vacuum limits.

Vacuum limit stop at 3.0e-4 Torr, backing off at 5.0e-4 Torr.

Fan has been inserted - pointed at turbo pump, TP temp's have decreased.

tp = 32.1C; rt = 24.7C


 Friday, June 02, 2017, 13:22

IG1 = 2.4e-4 Torr

TGHT = 520A, 5.40V

Vacuum stable and decreasing.

Carbonization process almost complete.

Will remain at max setpoints over the weekend.

TP = 28.2C; RT = 24.5C


 Monday, June 05, 2017, 08:51

IG1 = 1.75e-6 Torr

TGHT = 520A, 5.29V

Carbonization process complete!

Remained at max setpoints over the weekend.

Initiating auto cool at 1.0A/min


 Tuesday, June 06, 2017, 15:56

Vented in Ar and removed today.

Currently in glove box.


 Monday, June 12, 2017, 11:44

Flakes produced: 48.00g


 