Wednesday, November 23, 2022, 13:52, Aaron Schmidt, , , , , , 44378-14, In progress, FEBIAD Coil Tests
|
Sam G. & Navid N.
Work Permit# C2022-11-23--1
Wednesday, November 23, 2022, 13:51 FS#5 on (HS bypassed with a water loop) |
Monday, December 05, 2022, 15:41, Aaron Schmidt, , , , , , , , Source tray insulator replacement 7x
|
Monday, December 05, 2022, 15:38: Source Tray TGHT & TBHT insulators replaced.
Torqued @ 75 in-lbs. (Reference image attached)
|
Tuesday, December 06, 2022, 11:20, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Tests
|
Thermocouples installed:
O - O
O - Anode |
Tuesday, December 13, 2022, 16:12, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 2
|
Thermocouples installed (X):
O - O
O - Anode |
Friday, December 16, 2022, 10:32, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 3
|
Thermocouples installed (X):
O - O
O - Anode |
Thursday, January 12, 2023, 09:04, Aaron Schmidt, , LP-SIS, , , 44691-14, 44378-20, In progress,
|
Test for Aurelia L. Empty LP-SIS w/ end caps in. Right side expanded.
Thermocouples installed (R - L):
X & Y For the (V) checks. |
Monday, January 16, 2023, 16:02, Aaron Schmidt, , HP-FEBIAD-CTL, , , , , In progress, HP-FEBIAD tests
|
Extra wraps of foil around the center block (6) + 3 full wraps around the shield.
Monday, January 16, 2023, 15:40: Roughing.
Monday, January 16, 2023, 16:10: TP1B on. |
Tuesday, January 17, 2023, 09:48, Aaron Schmidt, , , , , , , Problems/Solutions, TMS:RP2 Failure
|
Tuesday, January 17, 2023, 09:48: TMS:RP2 off. Audible failure was in progress. Also observable on the strip tool. Vacuum group contacted.
|
Tuesday, January 31, 2023, 10:42, Aaron Schmidt, , LP-SIS, , , 44062-1-SK, 45235-7, In progress, Conditioning UC#x assembly
|
SK Series of LP-SIS targets are for conditioning only.
Tuesday, January 31, 2023, 10:39: Roughing. (Took quite a bit of effort to get the doors to shut. It's colder than usual in here. The seals were
stiff) |
Thursday, February 02, 2023, 12:44, Aaron Schmidt, , LP-SIS, , , 44062-1-SK , 45235-1, In progress, Conditioning UC#x assembly
|
SK Series of LP-SIS targets are for conditioning only.
Thursday, February 02, 2023, 12:41: Roughing.
Thursday, February 02, 2023, 12:43: BV1A open. |
Wednesday, March 29, 2023, 12:22, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-7, 45235-20, Failed, Conditioning TiC#5
|
Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22: TP1B on.
Wednesday, March 29, 2023, 12:40: TP1A on. |
Thursday, April 13, 2023, 11:07, Aaron Schmidt, , , , , , , In progress, Installation of new IDP-15 TMS:TP2
|
IDP15 Scroll Pump, Std w/ inlet.
TMS:RP2
PN: X3815-64010 |
Monday, April 17, 2023, 14:08, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6
|
Monday, April 17, 2023, 14:03: Roughing.
Monday, April 17, 2023, 14:08: BV1A open.
Monday, April 17, 2023, 14:32: TP1B on. |
Wednesday, April 26, 2023, 08:46, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-6, 45235-20, , Testing TiC#5 assembly w/ an empty target
|
Anode remade with a ceramic "elbow-cube". Empty target oven in use for testing.
Wednesday, April 26, 2023, 08:44: BV1B open. Roughing.
Wednesday, April 26, 2023, 08:46: BV1A open |
Monday, May 01, 2023, 14:31, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-5, 45235-20, In progress, Conditioning TiC#5
|
New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B on |
Friday, May 05, 2023, 06:49, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6
|
Ceramic elbow installed on the anode.
Friday, May 05, 2023, 06:47: Roughing.
Friday, May 05, 2023, 07:24: TP1B on. |
Tuesday, May 09, 2023, 10:40, Aaron Schmidt, SiC#45, HP-SIS, ITE, TM4, 44692-3, 45235-8, In progress, Conditioning SiC#45
|
Tuesday, May 09, 2023, 10:28: Roughing.
Tuesday, May 09, 2023, 11:25: TP1B on.
Tuesday, May 09, 2023, 12:38: TP1A on. |
Tuesday, May 16, 2023, 14:00, Aaron Schmidt, Ta#65, LP-SIS, ITE, TM4, 45220-7, 45235-2, In progress, Conditioning Ta#65
|
Calibrated window installed on the beam line.
Tuesday, May 16, 2023, 13:45: Roughing both the chamber & beam line.
Tuesday, May 16, 2023, 14:00: TMS:TP6 on. |
Thursday, May 25, 2023, 13:47, Aaron Schmidt, , , , , , , , Rough down empty chamber
|
Thursday, May 25, 2023, 13:47: Roughing. |
Wednesday, May 31, 2023, 15:19, Aaron Schmidt, SiC#46, HP-SIS, , , 44692-2, 45235-6, In progress, Conditioning SiC#2023A (Spare, renamed SiC-23B) - No salts
|
(Spare HP-SIS SiC SiC-23B)
Wednesday, May 31, 2023, 15:18: Roughing.
Thursday, June 01, 2023, 07:30: TP1B on. |
|