Entry  Thursday, September 29, 2022, 13:50, Aaron Schmidt, , , , , , , In progress, Pump down empty chamber 
Water loop installed.
Thursday, September 29, 2022, 13:50: Roughing

Tuesday, October 18, 2022, 11:17: Venting
Entry  Tuesday, October 18, 2022, 13:25, Aaron Schmidt, C#5, LP-SIS, , , 45235-5, 44691-13, In progress, Conditioning C#5 C#5_-_Conditioning_start_-_HV.docx
Tuesday, October 18, 2022, 13:25: Roughing.
Tuesday, October 18, 2022, 13:28: BV1A open

Wednesday, October 19, 2022, 12:14: TP1B on.
Entry  Wednesday, October 19, 2022, 12:16, Aaron Schmidt, , , , , , , , Test Stand controls changed 
genepicsas.triumf.ca
x11 enabled.
Then use login credentials.
Entry  Tuesday, November 15, 2022, 11:24, Aaron Schmidt, UC#41 assembly, LP-SIS, ITE, TM4, 45220-8, 45235-4, In progress, Conditioning UC#41 assembly UC#41_assembly_conditioning.docx
 LP-SIS 45220-8 is empty & for testing only.
Tuesday, November 15, 2022, 11:00: Roughing.
Tuesday, November 15, 2022, 11:21: BV1A open. 
Entry  Wednesday, November 16, 2022, 13:28, Aaron Schmidt, , , , , , , Problems/Solutions, TSG:TP1A Replaced 
 See elog 944
Wednesday, November 16, 2022, 13:23: TP1 A replaced
Wednesday, November 16, 2022, 13:25: Roughing.
Entry  Wednesday, November 23, 2022, 13:52, Aaron Schmidt, , , , , , 44378-14, In progress, FEBIAD Coil Tests 
Sam G. & Navid N.
Work Permit# C2022-11-23--1
Wednesday, November 23, 2022, 13:51 FS#5 on (HS bypassed with a water loop)
Entry  Monday, December 05, 2022, 15:41, Aaron Schmidt, , , , , , , , Source tray insulator replacement 7x
 Monday, December 05, 2022, 15:38: Source Tray TGHT & TBHT insulators replaced. 
Torqued @ 75 in-lbs. (Reference image attached)
 
Entry  Tuesday, December 06, 2022, 11:20, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Tests Re-routed_Anode_FEBIAD_12-2022_Test_1.docxITS_FEBIAD_measurements_12-2022_Test_1.xlsx
Thermocouples installed:
O - O
O - Anode
Entry  Tuesday, December 13, 2022, 16:12, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 2 Re-routed_Anode_FEBIAD_12-2022_Test_2.docx
Thermocouples installed (X):
O - O
O - Anode
Entry  Friday, December 16, 2022, 10:32, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 3 
Thermocouples installed (X):
O - O
O - Anode
Entry  Thursday, January 12, 2023, 09:04, Aaron Schmidt, , LP-SIS, , , 44691-14, 44378-20, In progress,  
Test for Aurelia L. Empty LP-SIS w/ end caps in. Right side expanded.
Thermocouples installed (R - L):
X & Y For the (V) checks.
Entry  Monday, January 16, 2023, 16:02, Aaron Schmidt, , HP-FEBIAD-CTL, , , , , In progress, HP-FEBIAD tests 
Extra wraps of foil around the center block (6) + 3 full wraps around the shield.
Monday, January 16, 2023, 15:40: Roughing.
Monday, January 16, 2023, 16:10: TP1B on.
Entry  Tuesday, January 17, 2023, 09:48, Aaron Schmidt, , , , , , , Problems/Solutions, TMS:RP2 Failure 
Tuesday, January 17, 2023, 09:48: TMS:RP2 off. Audible failure was in progress. Also observable on the strip tool. Vacuum group contacted.
Entry  Tuesday, January 31, 2023, 10:42, Aaron Schmidt, , LP-SIS, , , 44062-1-SK, 45235-7, In progress, Conditioning UC#x assembly 
SK Series of LP-SIS targets are for conditioning only.
Tuesday, January 31, 2023, 10:39: Roughing. (Took quite a bit of effort to get the doors to shut. It's colder than usual in here. The seals were
stiff)
Entry  Thursday, February 02, 2023, 12:44, Aaron Schmidt, , LP-SIS, , , 44062-1-SK , 45235-1, In progress, Conditioning UC#x assembly 
SK Series of LP-SIS targets are for conditioning only.
Thursday, February 02, 2023, 12:41: Roughing.
Thursday, February 02, 2023, 12:43: BV1A open.
Entry  Wednesday, March 29, 2023, 12:22, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-7, 45235-20, Failed, Conditioning TiC#5 TiC#5_conditioning.docx
Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22: TP1B on.
Wednesday, March 29, 2023, 12:40: TP1A on.
Entry  Thursday, April 13, 2023, 11:07, Aaron Schmidt, , , , , , , In progress, Installation of new IDP-15 TMS:TP2 
IDP15 Scroll Pump, Std w/ inlet.
TMS:RP2
PN: X3815-64010
Entry  Monday, April 17, 2023, 14:08, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6 
Monday, April 17, 2023, 14:03: Roughing.
Monday, April 17, 2023, 14:08: BV1A open.
Monday, April 17, 2023, 14:32: TP1B on.
Entry  Wednesday, April 26, 2023, 08:46, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-6, 45235-20, , Testing TiC#5 assembly w/ an empty target TiC#5_empty_container_run.docxScreenshot_from_2023-04-27_21-54-15.png
Anode remade with a ceramic "elbow-cube". Empty target oven in use for testing.
Wednesday, April 26, 2023, 08:44: BV1B open. Roughing.
Wednesday, April 26, 2023, 08:46: BV1A open
Entry  Monday, May 01, 2023, 14:31, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-5, 45235-20, In progress, Conditioning TiC#5 TiC#5_-_44692-5_Anode_&_Coil_checks.docxTiC#5_-_44692-5_Conditioning.docx
New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B on 