Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 50 of 53  Not logged in ELOG logo
Entry  Thursday, May 25, 2023, 13:47, Aaron Schmidt, , , , , , , , Rough down empty chamber 
Entry  Wednesday, May 31, 2023, 15:19, Aaron Schmidt, SiC#46, HP-SIS, , , 44692-2, 45235-6, In progress, Conditioning SiC#2023A (Spare, renamed SiC-23B) - No salts SiC#2023A_-_No_Salts.docx
Entry  Thursday, June 08, 2023, 14:22, Aaron Schmidt, , , , , , , , Rough down empty chamber 
Entry  Monday, July 10, 2023, 15:01, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Entry  Thursday, July 13, 2023, 07:37, Aaron Schmidt, , , , , , , , Tests - Aurelia L 
Entry  Thursday, July 13, 2023, 18:29, Aurelia Laxdal, , LP-SIS, , , , , In progress, Spectrometer tests 
Entry  Wednesday, August 09, 2023, 14:29, Aaron Schmidt, , LP-SIS, , , 45220-6, 45235-3, In progress, Graphite target test 1 (C2023A) Graphite_target_45220-6.docxGraphitetesting_Aug102023.xlsx
Entry  Monday, August 14, 2023, 12:11, Aaron Schmidt, , LP-SIS, , , 45220-11, 45235-3, , Graphite target test 2 (C2023B) Graphitetesting_Aug102023.xlsx
Entry  Wednesday, August 16, 2023, 11:32, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Entry  Tuesday, August 29, 2023, 12:14, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Entry  Thursday, September 28, 2023, 13:42, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Entry  Tuesday, October 10, 2023, 15:46, Aaron Schmidt, Ta#68 (Spare), LP-SIS, , , 45220-3, 45235-11, In progress, Conditioning Ta#68 (Spare) Ta#68-Spare_Conditioning.docx
Entry  Wednesday, October 18, 2023, 15:43, Aaron Schmidt, , LP-SIS, , , 45447-12, 45235-17, In progress, Conditioning UC#43 (empty) w/ gas line UC#43_Conditioning_empty_with_Gas_mod.docxUC#43_HS_with_gas_line_mod_-_Test_2.docxUC#43_HS_with_gas_line_mod_-_HV_Test.docx
Entry  Monday, October 30, 2023, 16:01, Aaron Schmidt, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
Entry  Thursday, November 16, 2023, 09:43, Aaron Schmidt, , LP-SIS, , , , , In progress, Thermal tests 
Entry  Monday, November 27, 2023, 16:09, Ferran Boix Pamies, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
Entry  Tuesday, December 12, 2023, 12:41, Aaron Schmidt, , , , , , , Done, Source Tray / TS inspection 
Entry  Tuesday, December 12, 2023, 16:11, Dave Neilson, Shunt #0, , , , -, -, , P2N Thermal Test 
Entry  Thursday, January 18, 2024, 10:44, Aaron Schmidt, , , , , , , Done, Thermal tests 2 
Entry  Thursday, January 18, 2024, 10:47, Aaron Schmidt, , , , , , , Problems/Solutions, FC0 Solenoid Replaced. 