  686   Friday, September 21, 2018, 11:41 Aaron SchmidtUC#26LP-IG-LISITETM4 42132-1In progressConditioning Heat Shield for UC#26Friday, September 21, 2018, 11:40: Roughing
Friday, September 21, 2018, 11:41:
Doors sealed for roughing.
 TS-2018-09-21-14-53.rgaUC#26.docx 
  689   Monday, October 15, 2018, 14:38 Aaron Schmidt      Problems/SolutionsAnode / Cathode PS to NegativeMonday, October 15, 2018, 13:00-14:00 Anode
/ Cathode BIAS PS polarity reversed by John
Chow.
  
  690   Monday, October 22, 2018, 07:18 Aaron Schmidt       TS restart after power outageFriday, October 19, 2018, 10:00 (Approx):
Site wide power outage. TS completely shut
down. 
  
  694   Tuesday, November 06, 2018, 08:52 Aaron Schmidt      In progressPump down empty chamberTuesday, November 06, 2018, 08:50: Roughing
Tuesday, November 06, 2018, 08:51:
Doors sealed.
  
  696   Thursday, November 08, 2018, 14:13 Aaron Schmidt       Ar & Ne gas bottle replacement.Thursday, November 08, 2018, 14:05: Fresh
/ recently calibrated Neon & Argon bottles
installed.
 GasLeak_Datasheet.pdf 
  697   Monday, November 19, 2018, 14:22 Aaron Schmidt      Problems/SolutionsVacuum issues.





Normal
0
  
  698   Wednesday, December 05, 2018, 10:22 Aaron Schmidt      Problems/SolutionsRGA Filament & Ionizer replacementRGA Ionizer & Filament replaced as
per SRS RGA manual.
The ionizer was found to be dirty
 12x 
  699   Thursday, December 06, 2018, 11:02 Aaron Schmidt      Problems/SolutionsFC0 Bellows Replacement.Thursday, December 06, 2018, 11:02: Turbo
pumps (TP6 & TP2) off on beamline side.
IG6 off.
 20181206_Old_Bellows.jpg20181210_112528.jpg20181210_115310.jpg20181211_New_Bellows_installed.jpg 
  704   Wednesday, January 09, 2019, 09:10 Aaron Schmidt       Cathode to Anode. PS to PositiveWednesday, January 09, 2019, 09:09: Upper
HV cage set to Anode / Positive as per dwg
ISK4523D Rev 6.
  
  705   Thursday, January 10, 2019, 11:38 Aaron Schmidt       Power outtage prepThursday, January 10, 2019, 11:32: Power
down TS. Lock out.
Thursday, January 10, 2019, 11:36:
  
  706   Monday, January 14, 2019, 09:47 Aaron Schmidt       TS restart after power outageMonday, January 14, 2019, 09:00: Epics
white out
Ref: Fault report  11993 (11981
  
  707   Monday, January 21, 2019, 10:55 Aaron Schmidt       2019 Anode tests FM-1Monday, January 21, 2019, 10:50: RGA on.
Monday, January 21, 2019, 10:54:
Waterlines opened. No response on RGA. Vacuum
  
  708   Thursday, January 24, 2019, 08:42 Aaron Schmidt       IG6 fix (w/ instruction)TMS:IG6 had continued communication errors
post power outage & would not switch
on. After a power loss, IG6 switches automatically
  
  709   Friday, February 22, 2019, 11:11 Aaron Schmidt LP-FEBIAD     Gas line backing pump testsBacking "mini pump" testing.
-Open gas lines & auto ramp (If
using HV, close up the back)
  
  710   Friday, March 01, 2019, 14:51 Aaron Schmidt LP-FEBIAD     Gas lines test & Emissions measurement prepFriday, March 01, 2019, 14:50:
SV5 replaced with a new valve.
SV1 disconnected from the He line
 gas-lines-changes.jpgGas_line_backing_pump_test_2019.docxTS-2019-03-05-09-45.rgaTS-2019-03-06-08-00.rga 
  711   Thursday, March 07, 2019, 07:55 Aaron Schmidt LP-FEBIAD    Problems/SolutionsTS restart - Troubleshoot BIAS sparkThursday, March 07, 2019, 07:48: IV4 reset,
BV6 & TMS TP6 reset.
Turbo pump restarted.
 BIAS_spark_out_issue_-_2019.docxTS-2019-03-07-07-51.rga 
  712   Monday, March 11, 2019, 13:56 Aaron Schmidt      DoneTGHT PS replacedMonday, March 11, 2019, 13:55: The TGHT
PS was replaced.
Brought up to 20 A. Operation. ok.
  
  713   Thursday, March 21, 2019, 08:33 Aaron Schmidt       Pump down TSThursday, March 21, 2019, 08:32: Roughing.   
  714   Tuesday, March 26, 2019, 10:44 Aaron Schmidt      Problems/SolutionsEZL PS replaced. TestEZL checked. OK @ 5kV
BIAS PS issues.
2.3kV on screen. Read back on PS
 New_EZL_PS_testing_-_2019.docx 
  715   Wednesday, March 27, 2019, 11:01 Aaron Schmidt      Problems/SolutionsBIAS PS replaced. TestWednesday, March 27, 2019, 10:25: BIAS
@ 1 kV
952V - 548uA on controls readback
 NEW_BIAS_PS_testing_-_2019.docx 