Subject: Power outtage prep 

Thursday, January 10, 2019, 11:32: Power down TS. Lock out.

Thursday, January 10, 2019, 11:36: RGA switched off full.

Thursday, January 10, 2019, 11:38: All ion gauge and turbos off. BV's closed.


Friday, January 11, 2019, 07:30: Vent TS.

Friday, January 11, 2019, 08:10: Purge FS#5 waterlines and close off main supply / return.

Friday, January 11, 2019, 08:12: Closed PV1 & PV2. Shut off the roughing pumps.