575
|
Tuesday, April 04, 2017, 14:33 |
Aaron Schmidt | | | | | | | | Power supply failure to E-rig | Wednesday, March 29, 2017, 15:15: DAC power
supply appears to have failed. Pop sound
and electrical smoke/smell noticed. |
|
|
576
|
Thursday, April 06, 2017, 12:06 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | | | In progress | Tri-Coil CTL-FEBIAD test | Thursday, April 06, 2017, 12:06: Roughing.
Thursday, April 06, 2017, 13:07:
Turbo pumps on. |
|
|
577
|
Monday, April 10, 2017, 15:12 |
Anders Mjos | | | | | | | Problems/Solutions | Vacuum leak on front door | The vacuum behaved erratic over night with
excursion up into the mid 10^-6 Torr range.
To investigate the chamber was vented. With |
|
|
578
|
Wednesday, April 12, 2017, 16:04 |
Anders Mjos | | | | | | | Problems/Solutions | Leak on FS#3 COIL and EE | A water to vacuum leak has been found on
FS#3. The leak is not detected on the leak
detector, but can be seen as an increase |
|
|
579
|
Tuesday, April 18, 2017, 07:46 |
Aaron Schmidt | | | | | | | Problems/Solutions | TSG:TP1B & TSG:BV1B tripped | Tuesday, April 18, 2017, 07:30: TSG : TP1B
Tripped on Saturday.
Tuesday, April 18, 2017, 07:40: TSG |
|
|
580
|
Tuesday, May 02, 2017, 14:03 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. (FS#3 out) | Check to fit lines FS#3
Tuesday, May 02, 2017, 14:00: Rouging.
Wednesday, May 03, 2017, |
|
|
581
|
Thursday, May 04, 2017, 13:49 |
Aaron Schmidt | UC#20 | LP-IG-LIS | | | | | | Conditioning Heat shield for UC#20 (1) | Thursday, May 04, 2017, 13:48: Roughing.
Thursday, May 04, 2017, 14:09: Turbos
on. |
|
|
582
|
Friday, May 05, 2017, 14:28 |
Aaron Schmidt | UC#20 | LP-IG-LIS | | | | | | Conditioning Heat shield for UC#20 (2) | New O-rings installed on FS#3.
Friday, May 05, 2017, 14:24: Roughing.
Friday, May 05, 2017, 14:34: Waterlines |
|
|
583
|
Wednesday, May 10, 2017, 15:07 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. (FS#3 out) | FS#3 lines blanked off.
Wednesday, May 10, 2017, 14:40: Roughing
Wednesday, May 10, 2017, 15:05: Turbos |
|
|
584
|
Tuesday, May 16, 2017, 14:25 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | | | | Tri-Coil CTL-FEBIAD test III | Coil loose (Remove lid, Tighten and place
lid again)
Tuesday, May 16, 2017, 14:24: Roughing. |
8x |
|
585
|
Wednesday, May 17, 2017, 10:17 |
Anders Mjos | | HP-FEBIAD-CTL | | | | | Problems/Solutions | Sparking between new coil line and ground electrode | Wednesday, May 17, 2017, 10:17: Sparking
around 20 kV. Will need to vent to increase
gap between water lines. |
|
|
586
|
Monday, May 22, 2017, 09:43 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | | | | Tri-Coil CTL-FEBIAD test IV | Monday, May 22, 2017, 09:41: Roughing.
Monday, May 22, 2017, 10:00: Turbo
pumps started. |
|
|
587
|
Wednesday, May 24, 2017, 11:12 |
Anders Mjos | | | | | | | Problems/Solutions | FEBIAD Anode bias configuration | The Test Stand has been configured
for Anode bias. John Chow changed the power
supply and the electrical connections have |
|
|
589
|
Saturday, June 03, 2017, 09:34 |
Anders Mjos | | | | | | | Problems/Solutions | FEBIAD Cathode bias configuration |
|
|
|
590
|
Tuesday, June 06, 2017, 09:22 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Tuesday, June 06, 2017, 09:21: roughing.
Friday, June 09, 2017, 08:50:
Ion gauge off. Turbo pumps off. |
|
|
591
|
Wednesday, June 07, 2017, 12:49 |
Aaron Schmidt | | | | | | | | Gas bottles | Gas bottles for FEBIAD testing were
exchanged yesterday around 1:30. One Neon
& one Argon bottle were removed. |
|
|
593
|
Friday, June 16, 2017, 11:23 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. | Friday, June 16, 2017, 11:22: roughing.
Friday, June 16, 2017, 14:28: Turbo
pumps on |
|
|
600
|
Wednesday, July 19, 2017, 09:13 |
Aaron Schmidt | Ta Targets | | | | | | Done | Ion Peaks | Attached is a recent list of Ta targets
with their extracted ions peaks. |
|
|
601
|
Thursday, August 03, 2017, 17:00 |
Anders Mjos | | | | | | | Problems/Solutions | Vacuum system tripped on power interruption | Thursday, August 03, 2017, 17:00:
Restarted TPs |
|
|
603
|
Thursday, August 17, 2017, 12:45 |
Anders Mjos | | | | | | | Problems/Solutions | TBHT power supply removed | The Xantrex 10V 600 A power supply
for the TBHT has been moved to ITE to replace
the failed TGHT power supply |
|
|