Entry  Tuesday, August 28, 2012, 16:57, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, Updates for NiO#1 at Test Stand 
Entry  Wednesday, August 29, 2012, 11:34, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 heating startup & few checks 
Entry  Thursday, August 30, 2012, 14:34, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 updates 
Entry  Thursday, August 30, 2012, 16:51, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 cooldown started 
Entry  Friday, August 31, 2012, 11:12, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , Done, Finished testing NiO#1 
Entry  Friday, August 31, 2012, 11:39, Anders Mjos, NiO#1, HP-FEBIAD, ITE, TM4, , , Done, Venting vacuum chamber - source change 
Entry  Tuesday, March 19, 2013, 12:34, Anders Mjos, SiC#28, , ITE, TM4, , , Done, Installation of SiC#28 LP-RFQ grab.n5HwXJ.png20130321_heating_and_signal.PNG
   +  Reply  Thursday, March 21, 2013, 15:05, Sebastian Raeder, SiC#28, , ITE, TM4, , , Done, 2nd heating of SiC#28 LP-RFQ - short resolved 20130322_heating.png20130322_massscan_transmission.png20130322_massscan_suppression1.png20130322_suppression2.pnglegs.JPG
Entry  Wednesday, April 10, 2013, 12:14, Anders Mjos, Ta#40, HP-SIS, ITE, TM4, 38295-4, , Done, Conditioning Ta#40 
   +  Reply  Thursday, April 18, 2013, 13:50, Anders Mjos, Ta#40, HP-SIS, ITE, TM4, 38295-4, , Done, Ta#40 stored under vacuum 
Entry  Wednesday, July 10, 2013, 10:21, Anders Mjos, SiC#29, HP-FEBIAD-CTL, ITE, TM4, 38481-6, 39956-4, Done, Testing SiC#29 CTL Target 
Entry  Friday, September 27, 2013, 11:41, Anders Mjos, Ta#41, HP-SIS, ITW, TM4, 39069-5, 38817-10, Done, Ta#41 Conditioning Ta#41_EE_After_Test_Stand.pdf
Entry  Monday, March 17, 2014, 19:10, Anders Mjos, Ta#42, LP-SIS, ITW, TM4, 40282-1, 39956-1 / 39956-9 (base / lid), In progress, Conditioning Ta#42_Test_Stand.docxOMEGA_OM-DAQPRO-5300_21-Mar-14_13.56.35.dlp
Entry  Friday, July 18, 2014, 11:30, Anders Mjos, UC#10, LP-SIS, ITE, TM4, 40282-5, 40316-1, Done, UC#10 Heat Shield Conditioning 
Entry  Friday, August 29, 2014, 14:52, Anders Mjos, Ta#44, HP-SIS, ITE, TM4, 38817-9, 40316-11, Done, Conditioning Ta#44 
Entry  Monday, September 08, 2014, 16:23, Anders Mjos, UC#11, , , TM4, 40282-5, , Done, UC#11 Heat Shield Conditioning Thermocouples.xlsx
Entry  Monday, March 16, 2015, 18:53, Anders Mjos, Ta#45, HP-SIS, ITE, TM4, 38817-5, , In progress, Conditioning Ta#45 Ta#45_Test_Stand.docxTa#45_2015-03-17_Mar_17_2015_09-05-31_AM.ana
Entry  Monday, May 25, 2015, 14:40, Anders Mjos, SiC#31, HP-SIS, ITW, TM4, 38817-7, , In progress, SiC#31 Conditioning SiC#31.docxER30kV580-200.txtER30kV580-230.txt
Entry  Friday, September 11, 2015, 11:43, Anders Mjos, Ta#46, HP-SIS, ITE, TM4, , , Done, Ta#46 conditioning Ta#46.docx
Entry  Wednesday, March 30, 2016, 16:32, Aaron Schmidt, Ta#47, LP-SIS, ITE, TM4, 41790-1, 41120-05, In progress, Conditioning Ta#47 TS-2016-03-30_Ta#47.rgaER-580-230-30kV-m23.txtER-580-230-30kV-m27.txtITE-TM4-Ta#47-LP-SIS_Test_Stand.docxTa#47.docx