Wednesday, April 10, 2013, 12:13: Stopped turbos in preparation for venting the chamber.
Wednesday, April 10, 2013, 13:05: Venting
Wednesday, April 10, 2013, 13:37: Ta#40 installed with 130 in lbs torque on all bolts.
Wednesday, April 10, 2013, 13:37: Roughing
Wednesday, April 10, 2013, 13:58: Started turbos
Wednesday, April 10, 2013, 14:07: Turbos at speed
Wednesday, April 10, 2013, 14:08: Vacuum at 9.2E-6 Torr
Thursday, April 11, 2013, 08:26: Opened cooling water. Vacuum stable at 2.2E-7 Torr
Monday, April 15, 2013, 08:40: HV conditioned to 30kV TSG:BIAS:RDCUR at 37 uA
Monday, April 15, 2013, 08:46: Started Target Heat Ramp 580A / 230A
Monday, April 15, 2013, 13:30: Target at temperature TGHT:RDCUR=574A, TBHT:RDCUR=230A
Monday, April 15, 2013, 15:10: Mass scan
Monday, April 15, 2013, 16:21: Target will be left at temperature overnight.
Tuesday, April 16, 2013, 08:40: Mass scan
Tuesday, April 16, 2013, 13:08: Started Target Cooling Sequence
Wednesday, April 17, 2013, 08:43: High voltage BIAS to zero
Wednesday, April 17, 2013, 08:47: Turbos off
Wednesday, April 17, 2013, 16:20: Target will likely be removed tomorrow Thursday.
Thursday, April 18, 2013, 11:13 : Venting
Thursday, April 18, 2013, 11:17: Water lines purged
Thursday, April 18, 2013, 11:29: Chamber vented. Target Removed |