  Test-Stand, Page 18 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Target/No.# Sourcedown Station Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  808   Tuesday, August 18, 2020, 12:07 Aaron SchmidtTest FEBIADHP-FEBIAD  38295-842752-5In progressRP check & Mass magnet check.Tuesday, August 18, 2020, 12:05: RP1 on
Tuesday, August 18, 2020, 12:10:
RP1 off
  
  812   Thursday, September 03, 2020, 11:28 Aaron Schmidt-HP-FEBIAD  38295-842752-5In progressLeak check 2.0Out Gas & MB1 check (Or leak check
2.0)
Ref: https://elog.triumf.ca/TIS/Test-Stand/809
  
  815   Tuesday, October 13, 2020, 12:34 Aaron Schmidt HP-FEBIAD  38295-842752-5In progressMB1 Check.He & Ar calibrated leak bottles in.
Tuesday, October 13, 2020, 12:33:
Roughing.
 MB1_Check_Oct_-_2020.docx 
  857   Monday, February 22, 2021, 18:25 Fernando Maldonado HP-FEBIAD    DoneFEBIAD parameter scansMonday, February 22, 2021, 17:48 Roughing
Monday, February 22, 2021, 18:17:
Turbos on.
 ESC_-_Feb_23_FEBAID_parameter_initial_checks.docxER-580-290-30kV-m28_2021-2-23.txt 
  863   Wednesday, March 10, 2021, 14:57 Aaron Schmidt HP-FEBIAD   42752-5In progressEmittance meter test with FEBIADWednesday, March 10, 2021, 14:54: Roughing.
Wednesday, March 10, 2021, 14:57:
BV1A open.
  
  928   Wednesday, May 25, 2022, 15:48 Aaron SchmidtSiC#42HP-FEBIADITWTM244692-944378-5In progressConditioning SiC#42Wednesday, May 25, 2022, 15:46: Roughing.
Wednesday, May 25, 2022, 16:21: TP1B
on.
 ER-580-290-30kV-m28.txtSiC#42.docxSiC#42_Conditioning_-_R.docx 
  932   Saturday, June 18, 2022, 10:04 Aaron SchmidtSiC#43HP-FEBIADITWTM242464-144378-16In progressConditioning SiC#43Note: SiC#42 replacement.
Saturday, June 18, 2022, 09:54: Roughing.
Saturday, June 18, 2022, 10:08: Data
 SiC#43_Conditioning_-_R.docxER-580-290-30kV-m27.txtSiC#43.docx 
  934   Thursday, June 23, 2022, 11:00 Aaron SchmidtSiC#44HP-FEBIADITETM437978-144378-24In progressConditioning SiC#44Thursday, June 23, 2022, 10:58: Roughing.
Thursday, June 23, 2022, 11:03: BV1A
open.
 SiC#44_-_R.docxER-580-290-30kV-m28.txtSiC#44.docx 
  952   Monday, December 19, 2022, 12:49 Carla Babcock HP-FEBIAD     HP-FEBIAD testsMonday, December 19, 2022, 12:06 : Tomislav
changed the polarity of the anode power supply
last week and everything has been closed
  
  962   Monday, April 17, 2023, 14:08 Aaron SchmidtTiC#6HP-FEBIADITWTM244692-1045235-12In progressConditioning TiC#6Monday, April 17, 2023, 14:03: Roughing.
Monday, April 17, 2023, 14:08: BV1A
open.
  
  965   Friday, May 05, 2023, 06:49 Aaron SchmidtTiC#6HP-FEBIADITWTM244692-1045235-12In progressConditioning TiC#6Ceramic elbow installed on the anode.
Friday, May 05, 2023, 06:47: Roughing.
Friday, May 05, 2023, 07:24: TP1B
 TiC#6_Anode_&_Coil_checks.docx 
  996   Friday, February 16, 2024, 10:30 Aaron SchmidtSiC# (Stock)HP-FEBIAD  45447-445235-21In progressConditioning stock SiC HP FEBIADFriday, February 16, 2024, 10:30: Roughing
Friday, February 16, 2024, 17:38:
TP1B on. 
 Stock_SiC_Elog_996_HP-FEBIAD_Cathode_BM_-_HV_&_Coil.docxHP-FEBIAD_Elog_996_-_Ramp_up_&_mass_scans.docxStock_SiC_Elog_996_HP-FEBIAD_Cathode_BIAS_mode_-_2.docx 
  1007   Friday, April 26, 2024, 13:49 Aaron SchmidtTiC#7HP-FEBIADITWTM445447-545235-15In progressConditioning TiC#7FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B
  
  1016   Wednesday, July 31, 2024, 18:50 Aaron SchmidtTiC SpareHP-FEBIADITWTM445447-242752-7In progressConditioning Spare for TiC#7Wednesday, July 31, 2024, 18:47: Roughing.
Wednesday, July 31, 2024, 19:24:
TP1B on.
  
  1   Wednesday, June 29, 2011, 15:30 John Wong       Testing Yield station elogABC 123 blah blah blah...   
  4   Thursday, September 15, 2011, 09:20 Anders Mjos       ISAC TestStand old e-loglink
to old e-log
  
  9   Friday, September 23, 2011, 15:38 Rick Maharaj       test stand ventedTest stand vented   
  10   Friday, September 23, 2011, 16:40 Anders Mjos      Problems/Solutions9-pin connectors swapped on source trayFriday, September 23, 2011, 16:3: The connection
on the 9-pin connector for FEBIAD targets
showed burn marks from the previous FEBIAD
  
  12   Monday, September 26, 2011, 14:56 John Wong      Problems/Solutions9-pin connectors swapped on source tray

    

       
            
 9-pin-connector.jpg 
  13   Monday, September 26, 2011, 16:14 Anders Mjos      Problems/SolutionsFixed leak on water line for HS, added Kapton insulation
    While testing SiC#26 a leak
was discovered on the water line to the heat
shield. The leak was in the right joint (see
 Water_Leak.pdfKapton.pdf 