Not logged in |
|
|
Friday, September 23, 2011, 16:40, Anders Mjos, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray
|
Monday, September 26, 2011, 14:56, John Wong, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray
|
|
Message ID: 10
Entry time: Friday, September 23, 2011, 16:40
Reply to this: 12
|
Author: |
Anders Mjos |
Target/No.#: |
|
Source: |
|
Station: |
|
Module: |
|
Target Oven W.O#: |
|
Heat Shield W.O#: |
|
Status: |
Problems/Solutions |
Subject: |
9-pin connectors swapped on source tray |
|
|
Friday, September 23, 2011, 16:3: The connection on the 9-pin connector for FEBIAD targets showed burn marks from the previous FEBIAD tests. Corresponding mark was found on the connector on the target side. Because of this the upper and lower 9-pin connectors were swapped to have a clean connector for the next FEBIAD target. |