ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  784   Wednesday, February 12, 2020, 11:04 Aaron Schmidt LP-SIS  41790-943515-1In progressConditioning HSUsing a broken LP-FEBIAD oven for out gassing.
Tentative UC#31*
Wednesday, February 12, 2020, 10:57:
 UC#31.docx 
  783   Tuesday, February 11, 2020, 14:27 Aaron Schmidt       Pump down empty ChamberTuesday, February 11, 2020, 14:27: UC#32
HS removed.
Tuesday, February 11, 2020, 14:27:
  
  782   Friday, February 07, 2020, 14:02 Aaron SchmidtC#(1)LP-SIS  43044-843515-3In progressConditioning C#(1) HSWas for UC# 32* - Schedule change, now
for C#1* - Last HS conditioning revealed
a TGHT to HS lid short. Milled the lid back
 C#1_-_2.docx 
  781   Thursday, January 30, 2020, 15:25 Aaron SchmidtC(#1)LP-SIS  43044-843515-3In progressConditioning C(#1) HSWas for UC# 32* - Schedule change, now
for C#1
Thursday, January 30, 2020, 15:13:
 C#1_-_Short.docx 
  780   Friday, January 24, 2020, 16:01 Anders Mjos      Problems/SolutionsUpgrading BIAS Power Supply


   
        
            
  
  779   Thursday, January 23, 2020, 16:05 Anders Mjos      Problems/SolutionsVacuum tripped due to PLC/EPICS for for the new BIASThursday, January 23, 2020, 16:05: Restarting
vacuum and TPs
  
  778   Tuesday, January 21, 2020, 13:45 Aaron Schmidt      Problems/SolutionsRGA Communications errorTuesday, January 21, 2020, 13:42: The RGA
was unable to connect. Typically connects
on COM4, however it did not register. RGA
  
  777   Tuesday, January 21, 2020, 09:38 Aaron SchmidtSiC#40LP-SIS  43044-843515-8In progressConditioning SiC#40 HSWas intended for UC#31 - Now used for SiC#40*
PEEK SEAL Test piece attached.
Tuesday, January 21, 2020, 09:34:
 SiC#40.docxSiC#40_-_HS_Out_gassing.docxTS-2020-01-21-11-10.rga 
  776   Friday, January 03, 2020, 11:56 Anders Mjos      Problems/SolutionsUpgrading BIAS Power SupplyA new power supply was installed today
by John Chow. Due to differences in pin configuration
of the controls, a change to the cabling
  
  775   Friday, December 20, 2019, 07:59 Aaron Schmidt       Holiday TS shut downFriday, December 20, 2019, 07:58: Turn
off ion gauges. Shut off turbo pumps TP6,
TP2, TP1A, & TP1B. Close backing valves.
  
  774   Monday, December 02, 2019, 16:01 Fernando Maldonado      In progressFerran irradiation copper end plate tests (aka MIST)Friday: Test to validate Ferran's assembly.
The plan is to ramp up to operating current,
apply high voltage, and possibly extract
  
  773   Wednesday, November 27, 2019, 16:01 Fernando Maldonado      Problems/SolutionsNew Controller for TP6Wednesday, November 27, 2019, 15:31: During
HV tests, bias was around 55kV when a spark
occur and almost immediately the controller
  
  772   Friday, November 22, 2019, 19:06 Fernando Maldonado, Ferran Boix Pamies       PEEK seal tests Friday, November 22, 2019, 19:02:
The new design for the PEEK irradiation will
be tested.
  
  771   Friday, November 15, 2019, 10:35 Aaron Schmidt       Pump down empty ChamberFriday, November 15, 2019, 09:35: Roughing.
Friday, November 15, 2019, 10:34:
Turbo pumps on.
  
  770   Friday, November 08, 2019, 14:21 Aaron Schmidt LP-SIS  41790-943515-9In progressNitrogen Bottle leak testFriday, November 01, 2019, 14:00: Nitrogen
bottle installed. Purged waterlines HS /
FS#5. Purge done in conjunction with SiC#38
  
  769   Friday, November 01, 2019, 16:01 Fernando Maldonado LP-SIS  41790-9 43515-9 In progressPeek seal tests on UCx#30 HSFriday, November 01, 2019, 15:47: A symbiotic 
peek seal assembly  was installed on
the manipulator grip to verify the temperature
 UC#30-plus-peak-seal.docxTS-2019-11-01-16-22.rgaTS-2019-11-04-16-12.rgaTS-2019-11-05-08-30.rga 
  768   Thursday, October 31, 2019, 13:22 Fernando Maldonado      Problems/Solutions9pin connector not fully in contact with baseplateThursday, October 31, 2019, 13:20: After
inspecting the interior, the 9 pin bracket
was found not making full contact with the 
 20191031_130003.jpg20191031_130028.jpg 
  767   Thursday, October 31, 2019, 11:37 Fernando Maldonado      Problems/SolutionsProbing anode bias supply on the service capThursday, October 31, 2019, 10:41: Cage
removed. Tape put on the limit switches.
Anode interlock bypassed.
  
  766   Wednesday, October 30, 2019, 14:50 Fernando Maldonado      Problems/SolutionsCathode bias mode configurationWednesday, October 30, 2019, 14:49: John
C. changed the polarity of the anode power
supply to negative, and Fernando M. rewired
  
  765   Monday, October 28, 2019, 09:24 Fernando Maldonado      Problems/SolutionsTSG:CG1A checked with local readerMonday, October 28, 2019, 09:22: The local
reader indicated 42 mTorr while EPICS showed
51mTorr.
  