Message ID: 788     Entry time: Wednesday, March 04, 2020, 17:15
Author: Fernando Maldonado 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: Emittance rig communication 

Wednesday, March 04, 2020, 17:13: EPICS page indicated a sucesful scan but data was empty.

Wednesday, March 04, 2020, 17:13: Power suppply didn't respond to the voltage sweep

Wednesday, March 04, 2020, 17:14: Problem most likely similar to elog entry 531.

Wednesday, March 04, 2020, 17:14: Keiko contacted for a soft reboot.

Wednesday, March 04, 2020, 17:14: Emittance power supply now  responds.