Entry  Wednesday, September 27, 2017, 09:14, Laura Lambert, SiC#37, HP-FEBIAD, ITE, TM4, 39530-10, , Ready, SiC#37 target description Target_Description.JPG
 Wednesday, September 27, 2017, 09:13
See attachment for target description.

 
Entry  Tuesday, May 30, 2017, 15:15, Laura Lambert, SiC#36, HP-FEBIAD-CTL, , TM2, 41369-10, , Ready, SiC#36 target description SiC#36_Target_Description.JPG
 Tuesday, May 30, 2017, 15:12
See attachment for target description.

 
Entry  Friday, September 02, 2016, 14:45, John Wong, SiC#34, LP-IG-LIS, , , 39814-V2-1, , Ready, SiC#34 Target Description  SiC34_target_description.JPG
 Friday, September 02, 2016, 14:43
See attachment for target description 

 
Entry  Wednesday, June 29, 2016, 11:49, Laura Lambert, SiC # 33, HP-SIS, , , 41369-4, , Ready, SiC#33 target description elog_target_description.JPG
 Wednesday, June 29, 2016, 11:47
See attachment for target description.

 
Entry  Thursday, September 24, 2015, 13:42, Laura Lambert, SiC#32, HP-FEBIAD, , , 39530-5, , Ready, SiC#32 target description elog_snapshot.JPG
 Thursday, September 24, 2015, 11:46
See attachment for target description.

 
Entry  Wednesday, April 29, 2015, 15:39, Laura Lambert, SiC#31, HP-SIS, , , 38817-7, , Ready, SiC#31 Target description final_density_measurements.JPGdensity_measurements.xlsxSiC_density_Jan_10_'14_cast_-_Copy.xlsxSiC_density_Oct_31_'14_cast.xlsx
 Wednesday, April 29, 2015, 15:30
SiC#31 HP-SIS target description: 
Total SiC foils = 520 discs 
Entry  Wednesday, April 30, 2014, 16:36, John Wong, SiC#30, HP-FEBIAD, ITE, TM3, 38481-8, , Spent, SiC#30 Target description  SiC#30_density_measurements.xlsx
Wednesday, April 30, 2014, 15:16
Note:
This target was built in 2011.  The endcaps were replaced after they got vaporized in Evap#1 during the sintering process, and the target
Entry  Wednesday, July 10, 2013, 18:41, John Wong, SiC#29, HP-FEBIAD-CTL, ITE, TM4, 38481-6, 39956-4, Spent, SiC#29 - Target description SiC#29_density_measurements_final.xlsx
Wednesday, July 10, 2013, 18:32 
SiC#29 HP-FEBIAD-CTL target description: 
Total SiC foils = 510 discs 
Entry  Tuesday, March 19, 2013, 13:32, John Wong, SiC#28-RFQ, LP-SIS, , TM4, LP-RFQ (NEW), , Spent, SiC#28-RFQ target description SiC#28_RFQ_density_measurements.xlsx
 Tuesday, March 19, 2013, 12:28
SiC#28 - RFQ target description: 
Total SiC foils = 325 discs
Entry  Wednesday, August 01, 2012, 09:37, Pierre Bricault, ITE-TM4-UO#3, LP-FEBIAD, ITE, TM4, , , Problems/Solutions, Short has developed while lowering the cathode heater 
 On tuesday July we lower the cathode heater to swap the anode-cathode bias. While lowering the cathode heater a short on the anode developed. 
The polarity swap was not possible because the target/tube assembly has also a short to common. 
We return the configuration has it was and we added two 100 Ohms: 5 W resistor between the common and the heaters to prevent current to flow back
Entry  Friday, September 23, 2011, 17:03, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Spent, Run finished 
Friday, September 23, 2011, 16:54:

    Cu-gaskets used for leak checking target had a leak rate of about  10-8  10-9 atm cc/sec. Replaced
with silver plated SS gaskets and no leak detected above 10-11 atm cc/sec.
    The target can not hold high voltage when it is sitting
    Reply  Monday, October 17, 2011, 14:45, John Wong, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Spent, Run finished EE_after_teststand.jpgSiC#26_specification.png


    
        
            Anders Mjos wrote:
        
        
            
            Friday, September 23, 2011, 16:54:
Entry  Thursday, October 11, 2012, 11:41, John Wong, NiO#1, HP-FEBIAD, ITE, TM4, 38481-7, 39069-1/10(lid), Spent, NiO target description  
(Should have posted this before my long vacation... Anyway, it's for documentation)
Thursday, October 11, 2012, 11:38
 
Entry  Friday, August 30, 2013, 14:45, John Wong, NiO#2, HP-FEBIAD, , , 39530-6, 39069-4, Spent, NiO target description 
Friday, August 30, 2013, 14:38 
NiO/Ni#2                                            
Average
Entry  Tuesday, October 27, 2020, 12:53, Aaron Schmidt, Nb#9, LP-SIS, ITE, TM4, 44508-2, , Ready, Nb#9 LP-SIS target description Nb#9_Target_Loading_data.pdf
 Nb#9 LP-SIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm
Entry  Wednesday, September 12, 2012, 01:53, John Wong, Nb#7, LP-SIS, , , 39165-6, , Spent, Nb#7 target description Nb#7_target_description.jpg
 Wednesday, September 12, 2012, 02:10
Nb#7 target description: 
Total Nb foils = 400 discs
    Reply  Monday, June 11, 2012, 13:46, John Wong, Nb#6, LP-SIS, ITW, TM1, 38634-4, 36833-1, Spent, Nb#5 run finished 


    
        
            John Wong wrote:
        
        
            
             
Entry  Monday, February 13, 2012, 16:00, John Wong, Nb#6, LP-SIS, ITW, TM1, 38634-4, 36833-1, Spent, Nb#5 ready in the Conditioning Station 
 

Monday, February 13, 2012, 16:00 
Nb#5 target description:
Entry  Thursday, August 24, 2023, 14:16, Aaron Schmidt, Nb#11, LP-IG-LIS, ITW, TM2, 45447-9, , In progress, Nb#11 Target description Nb#11_Target_Loading_Data.pdf
Nb#11 LP-IG-LIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm (0.001")
Entry  Friday, June 23, 2023, 09:02, Aaron Schmidt, Nb#10, LP-IG-LIS, ITW, TM2, 45447-7, , , Nb#10 target description. 
 Nb#10 LP-IG-LIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm (0.001")