ID |
Date |
Author |
Category |
Type |
Specific |
Subject |
Text |
 |
203
|
Tuesday, June 28, 2016, 08:32 |
Isaac Earle | Other | Other | Active Sump | RH MH Hot Cell Lab Active Sump Overflow | A call was received from the MCR
at approximately 21:30 on Monday June 27th
to report that active drains in the east |
|
202
|
Tuesday, June 21, 2016, 09:25 |
Isaac Earle | Development | Other | Controls | T1/T2 EPICS System With-Beam Testing | With-beam commissioning tests were
completed today by Tony Tateyama and Isaac
Earle. The test results are attached |
|
201
|
Wednesday, June 15, 2016, 11:00 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Moved to Position #1 | Position #4 on the T2-MK2 target
has now reached the maximum beam time. The
target was moved to Position #1 at the nominal |
|
200
|
Friday, May 13, 2016, 15:04 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Position 4 Adjusted to +1.5mm Offset | The T2-MK2 target at Position 4 has been
adjust to approximately +1.5mm offset. This
causes the ladder to be moved downwards, |
|
199
|
Friday, April 22, 2016, 14:45 |
Isaac Earle | Other | Other | Active Sump | RH MH Hot Cell Lab Active Sump Water Released | The Remote Handling Hot Cell Lab Active
Sump has been released to city sewer following
the procedure in Document-64834. The |
|
198
|
Wednesday, April 20, 2016, 10:01 |
Isaac Earle | Standard Operation | Target 1 | Target | T1/T2 Monitor Electrical Check Complete | Mike Russell from Diagnostics Group has
completed an electrical check on the T1 and
T2 profile and protect monitors. He |
|
197
|
Friday, April 15, 2016, 14:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Changes & Return to Beamline | On April 11th the T2-MK2 target was flushed
with water, then overnight with air at 5psi
supply pressure. The target ladder |
   |
196
|
Monday, April 11, 2016, 13:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Transported from BL to HC | The T2-MK2 target was transported from
the beam line to the hot cell using the transfer
flask. The target was measured to be |
|
195
|
Monday, April 11, 2016, 13:51 |
Isaac Earle | Development | Other | Other | Target Transfer Flask Hoist Hook Lower Limit Adjusted | The lower limit of the flask hoist
hook has been adjusted. The travelling
nut for the lower limit was rotated 3 notches |
|
194
|
Thursday, April 07, 2016, 16:44 |
Isaac Earle | Development | Other | Controls | T1/T2 Controls "Assembly Tests" Completed | The T1/T2 Control System "Assembly
Tests" (Document 118467 Release
#1, Section 5) have been completed. The |
|
193
|
Thursday, March 31, 2016, 11:48 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Beryllium Target Manufacturing Complete | Manufacturing of a new batch of T1 and
T2 beryllium targets has been completed.
The job was completed under Machine |
|
192
|
Thursday, March 24, 2016, 15:38 |
Isaac Earle | Development | Target 1 | Target | T1/T2 Beryllium Target Test Jig Fabrication Complete | Fabrication of the T1/T2 beryllium target
testing jig (TBP1721) was completed today
by Dan MacDonald. With a target installed |
|
191
|
Thursday, March 24, 2016, 14:46 |
Isaac Earle | Other | Other | Other | TNF / 500MeV Resin Cans Removed from Storage Pit #1 | Three used TNF / 500MeV system cooling
system resin cans were removed from the Meson
Hall target storage pit (two from Hole #1, |
|
190
|
Wednesday, March 16, 2016, 16:50 |
Isaac Earle | Development | Target 2 | Controls | Preliminary Testing of T2 Control System Complete | Preliminary testing of the new
PLC control system and EPICS interface was |
|
189
|
Monday, March 07, 2016, 18:22 |
Isaac Earle | Development | Target 1 | Controls | Preliminary Testing of T1 Control System Complete | Preliminary testing of the new PLC
control system and EPICS interface was completed
today for the T1 target, T1 cooling package, |
|
188
|
Wednesday, February 24, 2016, 13:03 |
Isaac Earle | Repair | Other | Other | Target Flask 2-Ton Hoist Chain Twist Corrected | A 1/2 turn twist in the target flask
hoist chain has been corrected to address
a deficiency observed by inspectors by Gordon |
|
187
|
Wednesday, February 03, 2016, 17:35 |
Isaac Earle | Standard Operation | Target 2 | Cooling | T2 MRO Work | The following work was performed at the
T2 cooling package and target between Jan
25 - Feb 3, 2016: |
|
186
|
Monday, January 25, 2016, 16:54 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 MRO Work | The following work was performed at the
T1 cooling package and target between January
18-21, 2016: |
|
185
|
Monday, January 18, 2016, 17:19 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 Packages Drained; BL1A Holding Tank Released | The T1 and T2 cooling packages were
drained to the BL1A holding tank on Jan 8
2016. The volumes were 100L and 80L |
|
184
|
Thursday, December 17, 2015, 13:31 |
Grant Minor | Development | Other | Target | T1/T2 Target Cassette - window / end cap manufacturing change (WO 41527) | Isaac Earle has recently been managing
the fabrication of some new Be target cassettes
for the T1 / T2 Meson Hall target ladders |
   |