  198   Wednesday, April 20, 2016, 10:01 Isaac EarleStandard OperationTarget 1TargetT1/T2 Monitor Electrical Check CompleteMike Russell from Diagnostics Group has
completed an electrical check on the T1 and
T2 profile and protect monitors.  He
  
  269   Wednesday, August 19, 2020, 12:57 Isaac EarleMaintenanceTarget 1CoolingT1/T2 MRO summary for 2020 shutdownThe following work was completed during
the 2020 shutdown period for BL1A (Jan-Aug
2020):
  
  202   Tuesday, June 21, 2016, 09:25 Isaac EarleDevelopmentOtherControlsT1/T2 EPICS System With-Beam Testing With-beam commissioning tests were
completed today by Tony Tateyama and Isaac
Earle.  The test results are attached
 T1T2_EPICS_Section_7_Commissioning_Results.pdf 
  338   Thursday, January 11, 2024, 15:10 Albert KongMaintenanceOtherCoolingT1/T2 Cooling Pkg. Proteus Paddle Wheel Maintenance, CUNO Filter Replacement, and Fitting Inspection The following tasks were performed:

    All electrical, water,
and pneumatic connections to the T1 target
  
  340   Monday, January 15, 2024, 16:47 Albert KongStandard OperationOtherCoolingT1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure The following tasks were completed
in preparation of re-filling the T1 and T2
cooling packages:
 7x 
  98   Friday, January 17, 2014, 10:10 Isaac EarleStandard OperationTarget 1CoolingT1/T2 Cooling Packages & Air Amplifier Shut Off In preparation for Edi to vent the
BL1A vacuum volume, the T1 and T2 cooling
packages were both shut off.  They will
  
  161   Monday, May 25, 2015, 12:48 Isaac EarleRepairTarget 1ControlsT1/T2 Controls System CrashAt 9:15am this morning BL1A tripped off
due to loss of the watchdog signals for the
T1/T2 control system.  Graham Waters
  
  194   Thursday, April 07, 2016, 16:44 Isaac EarleDevelopmentOtherControlsT1/T2 Controls "Assembly Tests" CompletedThe T1/T2 Control System "Assembly
Tests"  (Document 118467 Release
#1, Section 5) have been completed.  The
  
  58   Tuesday, September 25, 2012, 16:31 Isaac EarleRepairTarget 1TargetT1/T2 Controls - The target control software was
modified to reference the correct pot. look-up
table for the target at T1 (T1-MK1)
  
  192   Thursday, March 24, 2016, 15:38 Isaac EarleDevelopmentTarget 1TargetT1/T2 Beryllium Target Test Jig Fabrication CompleteFabrication of the T1/T2 beryllium target
testing jig (TBP1721) was completed today
by Dan MacDonald.  With a target installed
 IMG_6904.JPG 
  168   Friday, July 17, 2015, 10:14 Isaac EarleDevelopmentTarget 1TargetT1/T2 Be Target Failure History & Replacement PlanT1 and T2 beryllium target failure history
was investigated back to 2000 (as far as
XSTRIP records were readily available).  For
 T1_and_T2_Be_Target_History_-_July_17_2015.pdf 
  334   Tuesday, October 17, 2023, 14:25 Albert KongMaintenanceOtherOtherT1/T2 Air Amplifier Spool O-Ring ServicingToday we re-lubricated the o-rings on the
top air amplifier for T1/T2, and replaced
the o-rings on the bottom air amplifier with
 IMG_2576.JPEGIMG_2575.JPEG 
  118   Wednesday, July 02, 2014, 16:56 Isaac EarleRepairTarget 1CoolingT1-P2 and T2-P1 pressure transducers replaced.The T1-P2 (outlet) pressure transducer
was replaced to address an erroneous signal.
 The XTPAGE value now reads as expected.
  
  153   Wednesday, April 22, 2015, 15:17 Isaac EarleDevelopmentTarget 1TargetT1-MK2 wired for version identification The T1-MK2 target was wired for automatic
target version detection by the new PLC control
system (A to C jumper  in POT/CAM MS
  
  251   Wednesday, May 22, 2019, 14:25 Isaac EarleRepairTarget 1TargetT1-MK2 target moved to HC; T1-MK1 target moved to BLAfter extensive
testing over the last 2 weeks it was determined
 T1-MK1_target_info_sheet_-_Installed_May_21_2019.pdf 
  149   Tuesday, April 21, 2015, 12:59 Isaac EarleStandard OperationTarget 1TargetT1-MK2 target moved from storage pit to beam line The T1-MK2 target was transported
from the storage pit to the beamline.  The
target measured approximately 10mSv/hr at
  
  255   Thursday, January 30, 2020, 17:55 Isaac EarleRepairTarget 1TargetT1-MK2 target assembly repair completed in hot cellThe following work was done to the T1-MK2
target in the hotcell between the dates of
May 24, 2019 - Jan 30, 2020 (See E-Log #251
 T1-MK2_-_2020.pdfRHB_8901_Position_1_Entrance_Window.jpgDSC_0047_Position_1_Exit_Window.jpgRHB_8904_Position_4_Entrance_Window.jpgDSC_0022_Position_4_Exit_Window.jpg 
  257   Monday, February 10, 2020, 14:51 Isaac EarleMaintenanceOtherOtherT1-MK2 target and M9BB moved The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit. 
The M9 beam blocker was then moved from the
  
  238   Thursday, May 10, 2018, 15:23 Isaac EarleRepairTarget 1TargetT1-MK2 protect monitor and profile monitor replacedDuring first injection of beam down 1A
problems were encountered with the T1 protect
monitor.  Testing was done by Probes
  
  292   Wednesday, May 25, 2022, 10:15 Adam NewsomeStandard OperationTarget 1TargetT1-MK2 moved from hot cell to storage areaThe T1-MK2 target was moved from the hot
cell to the storage area, in position 5.
Note: manual nudging of the flask was required
  