131
|
Monday, December 22, 2014, 14:31 |
Isaac Earle | Maintenance | Target 2 | Water Leak | Drop in T2 water level | This morning at 5:30am the T2 cooling package
expansion tank switched to WARNING LEVEL
NOT OK. There was no change in BL1A |
|
|
139
|
Monday, February 02, 2015, 16:06 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 MRO Status | - T2-MK2 target (currently in the T2 monolith)
purged with air
|
|
|
186
|
Monday, January 25, 2016, 16:54 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 MRO Work | The following work was performed at the
T1 cooling package and target between January
18-21, 2016: |
|
|
219
|
Tuesday, April 11, 2017, 17:02 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 Cooling System MRO | The following work has been completed
on the T2 cooling package:
- T2 system drained to South TNF |
|
|
228
|
Tuesday, August 29, 2017, 12:17 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 and T2-MK1 Hansen water fittings replaced | The #6 male Hansen fittings for the
T1-MK1 and T2-MK1 targets (both currently
stored in the target storage pit) were replaced |
|
|
236
|
Tuesday, April 10, 2018, 11:20 |
Isaac Earle | Maintenance | Other | Cooling | T1 and T2 cooling package shutdown MRO work | The following work was performed
on the T1 and T2 cooling packages during
the 2018 shutdown: |
|
|
237
|
Friday, April 13, 2018, 14:21 |
Isaac Earle | Maintenance | Other | Other | M20 beam blocker MRO and T1/T2 final checks | The M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule. Both air cylinders were found |
|
|
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
|
256
|
Wednesday, February 05, 2020, 14:53 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 cooling package MRO work completed | Annual MRO work on the T1 and T2
cooling packages is now complete. The
following tasks were performed: |
|
|
257
|
Monday, February 10, 2020, 14:51 |
Isaac Earle | Maintenance | Other | Other | T1-MK2 target and M9BB moved | The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit.
The M9 beam blocker was then moved from the |
|
|
261
|
Monday, March 23, 2020, 16:13 |
Isaac Earle | Maintenance | Other | Other | M9 beam blocker MRO completed | M9 beam blocker MRO work was completed
in the hot cell today. This included
replacement of the main shaft seals and replacement |
|
|
269
|
Wednesday, August 19, 2020, 12:57 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1/T2 MRO summary for 2020 shutdown | The following work was completed during
the 2020 shutdown period for BL1A (Jan-Aug
2020): |
|
|
274
|
Friday, April 09, 2021, 12:42 |
Matthew Gareau | Maintenance | Target 2 | Cooling | Changed the paddle wheel, o ring, and shaft in the Collimator A flow meter at the T2 package | With the assistance of Maico we changed
the paddle wheel, o ring, and shaft in the
Collimator A flow meter (Q4) at the T2 package. |
|
|
276
|
Thursday, February 17, 2022, 13:03 |
Matthew Gareau | Maintenance | Target 1 | Target | T1 MK2 wire scanner and protect monitor test removal and reattachment with pin straightening | this Work was done on 09 Dec 2021.
Since Isaac Earle was leaving Triumf
he was giving us (maico, chad, adam, and |
|
|
277
|
Thursday, March 10, 2022, 11:18 |
Adam Newsome | Maintenance | Target 2 | Cooling | Changed paddle wheel, o-ring, and shaft in flow sensors at T2 cooling package | The paddle wheels, o-rings, and shafts
were changed at the T2 cooling package for
the following sensors: |
|
|
278
|
Thursday, March 10, 2022, 13:57 |
Adam Newsome | Maintenance | Target 1 | Cooling | Changed paddle wheel, o-ring, and shaft in flow sensors at T1 cooling package | The paddle wheels, o-rings, and shafts
were changed at the T1 cooling package for
the following sensors: |
|
|
279
|
Friday, March 11, 2022, 15:05 |
Adam Newsome | Maintenance | Target 1 | Cooling | O-rings on T1 cooling package water reservoir changed | The four o-rings on top of the T1 cooling
package water reservoir were changed as per
the recommended 5 year replacement schedule. |
|
|
280
|
Friday, March 11, 2022, 15:06 |
Adam Newsome | Maintenance | Target 2 | Cooling | O-rings on T2 cooling package water reservoir changed | The four o-rings on top of the T2 cooling
package water reservoir were changed as
per the recommended 5 year replacement schedule. |
|
|
281
|
Friday, March 11, 2022, 15:08 |
Adam Newsome | Maintenance | Target 1 | Cooling | Filters replaced: T1 cooling system | All filters were replaced for the T1 cooling
system: demineralizing resin circuit, target
water system, and M15. |
|