Monday, October 05, 2015, 15:25, Isaac Earle, Standard Operation, Other, Other, Old T2 Protect Monitor Cassette Update
|
The T2 protect monitor cassette removed in April 2015 (see E-log #154) was surveyed today. It was approximately 3mSv/hr at 0.5m and 15mSv/hr
on contact. It is unlikely that this monitor will ever be cool enough for hands-on elevation adjustment that it requires, therefore it has been bagged,
labeled, and transferred to the east hot cell for storage. |
Friday, March 11, 2022, 15:06, Adam Newsome, Maintenance, Target 2, Cooling, O-rings on T2 cooling package water reservoir changed
|
The four o-rings on top of the T2 cooling package water reservoir were changed as per the recommended 5 year replacement schedule. |
Friday, March 11, 2022, 15:05, Adam Newsome, Maintenance, Target 1, Cooling, O-rings on T1 cooling package water reservoir changed
|
The four o-rings on top of the T1 cooling package water reservoir were changed as per the recommended 5 year replacement schedule. |
Tuesday, August 30, 2022, 14:24, Adam Newsome, Maintenance, Other, Hot Cell, Nuclear Ventilation - Filter Change
|
Mechanical Services Group changed the pre-filter in the ventilation system on Aug. 29, 2022 as per work permit C2022-08-29-2.
It is recommended that Mechanical Services change the HEPA filter as soon as possible. These filters are on order with approximately 7 month lead |
Thursday, July 09, 2015, 13:51, Isaac Earle, Development, Other, Target, New T1 and T2 Beryllium Targets Ordered
|
An order for new T1 and T2 beryllium targets was submitted to the TRIUMF machine shop today. A total of seven T2 targets and twleve T1 targets
were ordered to match existing stock of wire EDM target shells. All required materials were supplied. Completion by October 30, 2015 was requested.
|
Thursday, September 08, 2016, 17:26, Isaac Earle, Development, Other, Active Sump, New Active Sump High Level Switch and Electronics Installed
|
To address the deficiencies identified in E-Logs #204 and #205 the old active sump high level switch was replaced with Omega LV164SS model (316SS stem
and float, 4' length, standard mount) using adaptor flange TRH1316 to mount to the top flange of the sump. A new electrical box was also installed
(circuit diagram attached in PDF format). The circuit was designed by Don Jackson and wired by Travis Cave. Connection to the RCR Lab PLC was |
Wednesday, March 15, 2017, 16:13, Isaac Earle, Standard Operation, Other, Active Sump, Meson Hall Hot Cell Lab Active Sump Water Released
|
On March 13th in the morning the Meson Hall Hot Cell Lab active sump reached the high level sensor. The system responded as expected: high
level panel warning light illuminated, siren sounded, and MCR notified via "B1 RCR1 RM6 WARN". A 1L sample was delivered to RPG for analysis.
After approval, the sump was pumped out over the following two days. The procedure in Document #64834 was followed for sampling and pump-out. |
Thursday, July 28, 2022, 12:51, Adam Newsome, Repair, Other, Hot Cell, Meson Hall Hot Cell - Nuclear Ventilation Issue
|
It was reported today by Peter Bratt that the nuclear ventilation system for the hot cell is not functioning. At this time, the cause of the issue is
unknown. Remote Handling and Electrical Services are investigating. This e-log will be updated when the issue is resolved.
|
Wednesday, May 03, 2023, 10:06, Adam Newsome, Maintenance, Other, Hot Cell, Meson Hall Hot Cell - Nuclear Ventilation HEPA Filter Changed, Operational
|
The HEPA filter in the nuclear ventilation system for the Meson Hall Hot Cell was changed and tested by mechanical services under work permit C2023-04-25-14.
|
Wednesday, June 06, 2012, 08:48, Isaac Earle, Repair, Target 1, Target, Manipulator Repair Complete
|
Repair of the west side hot cell manipulator was completed and the manipulator was re-installed into the hot cell. No contamination was found
in the lab, on the manipulator support frame, or on any tools. A 'y' motion lock was also installed on the east manipulator and all accessible pulleys
and rollers were lubricated. |
Friday, June 29, 2012, 14:18, Isaac Earle, Repair, Target 1, Target, Manipulator Repair Complete
|
Repair of the west side hot cell manipulator was completed and the manipulator was re-installed into the cell. The z-motion slave tapes,
upper counterweight tapes, and lower counterweight tapes were replaced on both sides.
100cpm contamination was found on the slave arm from a wet wipe. No contamination was found in the lab. |
Tuesday, November 13, 2012, 16:26, Isaac Earle, Repair, Target 1, Target, Manipulator Repair Complete
|
Repair of the west side manipulator in the west hot cell was completed today. Part of the repair was done by entering the hot cell using
double tank suits and supplied air. The repair was then completed on the master side of the manipulator. The manipulator is now operating smoothly.
Two sales representatives from Central Research Labs visited TRIUMF today as they were already in Vancouver on other business. I showed them |
Tuesday, November 12, 2013, 11:49, Isaac Earle, Repair, Target 1, Target, MH Hot Cell Lab Manipulator Overhaul
|
Complete overhaul of all manipulators in the Remote Handling Hot Cell Lab in the Meson Hall was performed by Peter Dudley from Central Research
Laboratories between October 28 - November 8th. Overhaul included replacing all tapes and cables, disassembling, cleaning, lubricating, and rebuilding
the master and slave wrist assemblies, adjusting motion locks, and other repairs/maintenance as required. All 6 manipulator arms in the lab are now |
Wednesday, January 25, 2012, 13:26, Isaac Earle, Maintenance, Target 2, Target, M9BB Returned to Beam Line
|
M9 beam blocker returned to beam line.
T2 target disconnected, picked up using flask, and returned to beam line as training exercise.
Field @ 50cm from T2 target during removal: ~90,000μSv/hr |
Tuesday, April 16, 2019, 15:35, Keith C Ng, Repair, Other, M9, M9 project post shutdown summary
|
Completed work at m9 beam line:
- Removed existing service stand and associated cable and water services. Legacy b1 water services still need to be removed for future magnet installation.
Old service stand is currently in warm cell waiting for disposal. |
Monday, April 06, 2020, 15:02, Isaac Earle, Standard Operation, Target 2, M9, M9 beam blocker returned to beamline
|
The M9 beam blocker was returned to the beamline today using the RH shielded transport flask. The top flange o-ring was replaced before installation.
After installation the "Lift T" assembly was removed, and electrical cable and air supply connected. Correct functionality of the
limit switches was confirmed with the control room. Actuation of the beam blocker could not be tested at this time because control takes place through |
Monday, March 23, 2020, 16:13, Isaac Earle, Maintenance, Other, Other, M9 beam blocker MRO completed
|
M9 beam blocker MRO work was completed in the hot cell today. This included replacement of the main shaft seals and replacement of the air cylinders.
Actuation was tested after replacement and the blocker moved smoothly through the full length of travel with approximately 45psi air pressure. It
is ready for transport back to the beamline. |
Wednesday, May 04, 2022, 11:27, Adam Newsome, Standard Operation, Target 2, M9, M9 and M20 Beam Blocker Actuation Test
|
The beam blockers for M9 and M20 were actuated, and vacuum was monitored to ensure no disruptions. Both actuation tests were successful. Motion was observed
and no abnormalities noted. Cabling and air connections checked: OK.
|
Friday, June 12, 2020, 13:54, Isaac Earle, Development, Other, M9, M9 Q1Q2 water header installed
|
The Q1Q2 water header (TB23481) was mounted this morning as per installation drawing TB23400.
Heat shrink tubing was applied to the B1 power cables (two positive, two negative) over the length of cable in the highest field which was showing
some signs of radiation damage on the insulation. The tubing used was McMaster-Carr PN 75665K932 (Clear PTFE, 4:1 shrink ratio, 1.0" ID before |
Wednesday, March 11, 2020, 10:29, Isaac Earle, Development, Other, M9, M9 Q1Q2 service stand foot plate installed
|
The M9 Q1Q2 "foot" plate (TB23363) has been installed over the floor plate. A nominal gap between the plates of 1/2" was set
before lowering the plate, it was then leveled using the three adjustment bolts resulting in a larger gap. After leveling, the plate was lifted to
remove the spirit levels and lock the position of the leveling bolts. The plate was then re-lowered and the tiedown bolt assemblies (TB23383) were |
|