ID Date Author Categorydown Type Specific Subject Text Attachments
  131   Monday, December 22, 2014, 14:31 Isaac EarleMaintenanceTarget 2Water LeakDrop in T2 water levelThis morning at 5:30am the T2 cooling package
expansion tank switched to WARNING LEVEL
NOT OK.  There was no change in BL1A
  
  139   Monday, February 02, 2015, 16:06 Isaac EarleMaintenanceTarget 2CoolingT2 MRO Status- T2-MK2 target (currently in the T2 monolith)
purged with air
  
  186   Monday, January 25, 2016, 16:54 Isaac EarleMaintenanceTarget 1CoolingT1 MRO WorkThe following work was performed at the
T1 cooling package and target between January
18-21, 2016:
  
  219   Tuesday, April 11, 2017, 17:02 Isaac EarleMaintenanceTarget 2CoolingT2 Cooling System MRO The following work has been completed
on the T2 cooling package:
- T2 system drained to South TNF
  
  228   Tuesday, August 29, 2017, 12:17 Isaac EarleMaintenanceTarget 1TargetT1-MK1 and T2-MK1 Hansen water fittings replaced The #6 male Hansen fittings for the
T1-MK1 and T2-MK1 targets (both currently
stored in the target storage pit) were replaced
  
  236   Tuesday, April 10, 2018, 11:20 Isaac EarleMaintenanceOtherCoolingT1 and T2 cooling package shutdown MRO work The following work was performed
on the T1 and T2 cooling packages during
the 2018 shutdown:
  
  237   Friday, April 13, 2018, 14:21 Isaac EarleMaintenanceOtherOtherM20 beam blocker MRO and T1/T2 final checksThe M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule.  Both air cylinders were found
  
  247   Thursday, January 10, 2019, 13:51 Isaac EarleMaintenanceTarget 1CoolingT1 and T2 cooling packages inspectedThe T1 and T2 cooling packages were inspected
today while running.  No water leaks
were observed at either package including
  
  249   Tuesday, February 26, 2019, 10:55 Isaac EarleMaintenanceTarget 1CoolingT1 and T2 MRO work and solenoid valve change summaryThe following work was completed between
Jan 16 - Feb 19, 2019:

    T1 and T2 cooling packages
  
  256   Wednesday, February 05, 2020, 14:53 Isaac EarleMaintenanceTarget 1CoolingT1 & T2 cooling package MRO work completed Annual MRO work on the T1 and T2
cooling packages is now complete.  The
following tasks were performed:
  
  257   Monday, February 10, 2020, 14:51 Isaac EarleMaintenanceOtherOtherT1-MK2 target and M9BB moved The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit. 
The M9 beam blocker was then moved from the
  
  261   Monday, March 23, 2020, 16:13 Isaac EarleMaintenanceOtherOtherM9 beam blocker MRO completedM9 beam blocker MRO work was completed
in the hot cell today.  This included
replacement of the main shaft seals and replacement
  
  269   Wednesday, August 19, 2020, 12:57 Isaac EarleMaintenanceTarget 1CoolingT1/T2 MRO summary for 2020 shutdownThe following work was completed during
the 2020 shutdown period for BL1A (Jan-Aug
2020):
  
  274   Friday, April 09, 2021, 12:42 Matthew GareauMaintenanceTarget 2CoolingChanged the paddle wheel, o ring, and shaft in the Collimator A flow meter at the T2 packageWith the assistance of Maico we changed
the paddle wheel, o ring, and shaft in the
Collimator A flow meter (Q4) at the T2 package.
  
  276   Thursday, February 17, 2022, 13:03 Matthew GareauMaintenanceTarget 1TargetT1 MK2 wire scanner and protect monitor test removal and reattachment with pin straightening this Work was done on 09 Dec 2021.
Since Isaac Earle was leaving Triumf
he was giving us (maico, chad, adam, and
 IMG_20211207_140443.jpgIMG_20211207_140508.jpgIMG_20211207_140735.jpgIMG_20211207_122631.jpgIMG_20211207_142836.jpg 
  277   Thursday, March 10, 2022, 11:18 Adam NewsomeMaintenanceTarget 2CoolingChanged paddle wheel, o-ring, and shaft in flow sensors at T2 cooling packageThe paddle wheels, o-rings, and shafts
were changed at the T2 cooling package for
the following sensors:
 PXL_20220310_173802512.jpgPXL_20220310_173759444.jpg 
  278   Thursday, March 10, 2022, 13:57 Adam NewsomeMaintenanceTarget 1CoolingChanged paddle wheel, o-ring, and shaft in flow sensors at T1 cooling packageThe paddle wheels, o-rings, and shafts
were changed at the T1 cooling package for
the following sensors:
  
  279   Friday, March 11, 2022, 15:05 Adam NewsomeMaintenanceTarget 1CoolingO-rings on T1 cooling package water reservoir changedThe four o-rings on top of the T1 cooling
package water reservoir were changed as per
the recommended 5 year replacement schedule.
  
  280   Friday, March 11, 2022, 15:06 Adam NewsomeMaintenanceTarget 2CoolingO-rings on T2 cooling package water reservoir changedThe four o-rings on top of the T2 cooling
package water reservoir were  changed as
per the recommended 5 year replacement schedule.
  
  281   Friday, March 11, 2022, 15:08 Adam NewsomeMaintenanceTarget 1CoolingFilters replaced: T1 cooling systemAll filters were replaced for the T1 cooling
system: demineralizing resin circuit, target
water system, and M15. 
  