Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-Meson Hall, Page 14 of 19  Not logged in ELOG logo
ID Date Author Category Type Specific Subjectdown Text Attachments
  83   Friday, May 31, 2013, 16:07 Isaac EarleRepairTarget 1TargetPower Supply Fan Failure Today (May 31, 2013) I was contacted
regarding a burning smell and high temperatures
around the T1/T2 controls racks.  Erwin
 IMG_1440.JPGIMG_1441.JPGIMG_1442.JPG 
  297   Wednesday, July 06, 2022, 12:52 Adam NewsomeOtherOtherHot CellPotential hot cell window oil leakSome oil was noticed around the hot cell
window, on the control panel, and on the
ground below the control panel. A leak is
  
  163   Friday, June 19, 2015, 17:11 Isaac EarleDevelopmentOtherControlsPLC Test of Ultrasonic Level SensorThe new T1/T2 level sensors
(Omega LVCN414) were hooked up to the PLC
 Overnight_Level_Sensor_PLC_Test.jpg 
  177   Monday, October 05, 2015, 15:25 Isaac EarleStandard OperationOtherOtherOld T2 Protect Monitor Cassette Update The T2 protect monitor cassette removed
in April 2015 (see E-log #154) was surveyed
today.  It was approximately 3mSv/hr
  
  280   Friday, March 11, 2022, 15:06 Adam NewsomeMaintenanceTarget 2CoolingO-rings on T2 cooling package water reservoir changedThe four o-rings on top of the T2 cooling
package water reservoir were  changed as
per the recommended 5 year replacement schedule.
  
  279   Friday, March 11, 2022, 15:05 Adam NewsomeMaintenanceTarget 1CoolingO-rings on T1 cooling package water reservoir changedThe four o-rings on top of the T1 cooling
package water reservoir were changed as per
the recommended 5 year replacement schedule.
  
  301   Tuesday, August 30, 2022, 14:24 Adam NewsomeMaintenanceOtherHot CellNuclear Ventilation - Filter ChangeMechanical Services Group changed the pre-filter
in the ventilation system on Aug. 29, 2022
as per work permit C2022-08-29-2.
  
  166   Thursday, July 09, 2015, 13:51 Isaac EarleDevelopmentOtherTargetNew T1 and T2 Beryllium Targets OrderedAn order for new T1 and T2  beryllium
targets was submitted to the TRIUMF machine
shop today.  A total of seven T2 targets
  
  207   Thursday, September 08, 2016, 17:26 Isaac EarleDevelopmentOtherActive SumpNew Active Sump High Level Switch and Electronics InstalledTo address the deficiencies identified
in E-Logs #204 and #205 the old active sump
high level switch was replaced with Omega
 IMG_7381.JPGIMG_7386.JPGRH_HC_Lab_Active_Sump_High_Level_Sensor_-_Electrical_Schematic.pdf 
  215   Wednesday, March 15, 2017, 16:13 Isaac EarleStandard OperationOtherActive SumpMeson Hall Hot Cell Lab Active Sump Water Released On March 13th in the morning the
Meson Hall Hot Cell Lab active sump reached
the high level sensor.  The system responded
  
  298   Thursday, July 28, 2022, 12:51 Adam NewsomeRepairOtherHot CellMeson Hall Hot Cell - Nuclear Ventilation IssueIt was reported today by Peter Bratt that
the nuclear ventilation system for the hot
cell is not functioning. At this time, the
  
  328   Wednesday, May 03, 2023, 10:06 Adam NewsomeMaintenanceOtherHot CellMeson Hall Hot Cell - Nuclear Ventilation HEPA Filter Changed, OperationalThe HEPA filter in the nuclear ventilation
system for the Meson Hall Hot Cell was changed
and tested by mechanical services under work
  
  36   Wednesday, June 06, 2012, 08:48 Isaac EarleRepairTarget 1TargetManipulator Repair Complete Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the hot cell.  No
  
  46   Friday, June 29, 2012, 14:18 Isaac EarleRepairTarget 1TargetManipulator Repair Complete Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the cell.  The
  
  62   Tuesday, November 13, 2012, 16:26 Isaac EarleRepairTarget 1TargetManipulator Repair Complete Repair of the west side manipulator
in the west hot cell was completed today.
 Part of the repair was done by entering
  
  91   Tuesday, November 12, 2013, 11:49 Isaac EarleRepairTarget 1TargetMH Hot Cell Lab Manipulator Overhaul Complete overhaul of all manipulators
in the Remote Handling Hot Cell Lab in the
Meson Hall was performed by Peter Dudley
  
  14   Wednesday, January 25, 2012, 13:26 Isaac EarleMaintenanceTarget 2TargetM9BB Returned to Beam LineM9 beam blocker returned to beam line.
T2 target disconnected, picked up
using flask, and returned to beam line as
  
  250   Tuesday, April 16, 2019, 15:35 Keith C NgRepairOtherM9M9 project post shutdown summary Completed work at m9 beam line:
- Removed existing service stand
and associated cable and water services.
  
  262   Monday, April 06, 2020, 15:02 Isaac EarleStandard OperationTarget 2M9M9 beam blocker returned to beamlineThe M9 beam blocker was returned to the
beamline today using the RH shielded transport
flask.  The top flange o-ring was replaced
  
  261   Monday, March 23, 2020, 16:13 Isaac EarleMaintenanceOtherOtherM9 beam blocker MRO completedM9 beam blocker MRO work was completed
in the hot cell today.  This included
replacement of the main shaft seals and replacement
  
ELOG V2.9.2-2455