38
|
Thursday, June 07, 2012, 18:08 |
Isaac Earle | Repair | Target 1 | Target | Hot Cell Manipulator Broken Tape | A tape snapped on the west side manipulator
today while working on the T1-MK2 target
repair. The tape travels through to |
|
|
37
|
Wednesday, June 06, 2012, 08:58 |
Isaac Earle | Maintenance | Target 2 | Target | T2 Monolith Leak Check | While leak checking components in
the M20 front end on May 25th, the top of
the T2 monolith was also checked by flooding |
|
|
36
|
Wednesday, June 06, 2012, 08:48 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the hot cell. No |
|
|
35
|
Wednesday, May 30, 2012, 15:39 |
Isaac Earle | Repair | Target 1 | Target | West Side Manipulator Removed from Hot Cell | The west side manipulator was removed
from the hot cell using the new manipulator
removal frame. The operation went smoothly |
|
|
34
|
Monday, May 28, 2012, 17:17 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Water Loss Update | The T2 cooling package, the top of
the T2 monolith, and the Hansen water connections
which connect the package to the target were |
|
|
33
|
Thursday, May 24, 2012, 18:26 |
Isaac Earle | Repair | Target 2 | Cooling | Water Leak From T2 Cooling Package (Disconnected from Target) | Today I noticed a "NOT OK"
signal from T2 water expansion tank warning
level sensor. I checked the water level |
|
|
32
|
Monday, April 23, 2012, 09:55 |
Isaac Earle | Repair | Target 1 | Target | Hot Cell Manipulator Broken Cable | While working on the leak repair
of the T1-MK2 target in the hot cell on Friday
April 20th, a cable snapped on the slave |
|
|
31
|
Thursday, April 12, 2012, 15:19 |
Isaac Earle | Maintenance | Target 2 | Target | T2 Target Water Drained | In preparation for extended periods
of the T2 volume being vented during the
M20 repair, the T2 water package was shut-off, |
|
|
30
|
Wednesday, April 11, 2012, 17:02 |
Isaac Earle | Repair | Target 2 | Target | T2 Vacuum Interlock & Expansion Tank Level Sensor | The problem with the T2 vacuum interlock
was fixed by restarting the "Crate TG1"
control panel microprocessor. The T1 |
|
|
29
|
Thursday, April 05, 2012, 15:22 |
Isaac Earle | Maintenance | Target 1 | Target | T1 & T2 Profile and Protect "Blip" Test | Diagnostics group completed their
"blip" signal response tests on
the T1 and T2 profile and protect monitors. |
|
|
28
|
Thursday, April 05, 2012, 12:14 |
Isaac Earle | Repair | Target 1 | Target | T1 & T2 Profile Monitors | Controls Group replaced the wiring and
wire harness for the profile monitor limit
switches on T2. The monitor was actuated |
|
|
27
|
Wednesday, April 04, 2012, 15:51 |
Isaac Earle | Repair | Target 2 | Target | BL1A Update | Vacuum interlock defeat jumpers were removed
for T1 and T2. The interlock was tested
by venting the T1 and T2 volumes. Both |
|
|
26
|
Tuesday, April 03, 2012, 15:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1 Ladder Position Look-up Tables Updated | Graham Waters has activated the appropriate
target ladder position look-up tables for
the T1-MK1 target which was installed in |
|
|
25
|
Monday, April 02, 2012, 15:18 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Installed in Beam Line | The T1-MK1 target was transferred
from the storage pit to the beam line. Services
were hooked up and the cooling package was |
|
|
24
|
Tuesday, March 27, 2012, 13:14 |
Isaac Earle | Repair | Target 1 | Target | Water removal from T1 monolith | All water was removed from the base of
the target hole in the T1 monolith using
a suction tube device and wypalls. Video |
|
|
23
|
Friday, March 23, 2012, 14:50 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Leak - Update | The T1-MK2 target was transferred from
the beam line to the hot cell. Water
was seen in the bottom of the target pipe |
|
|
22
|
Thursday, March 22, 2012, 13:58 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | Vacuum group pumped down on the T1
& T2 volumes (because there is no cold
trap on the T1 pump) for approximately 1 |
|
|
21
|
Wednesday, March 21, 2012, 17:28 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | The water level in the T1 cooling
package expansion tank was checked again
today approximately 24 hours after it was |
|
|
20
|
Tuesday, March 20, 2012, 10:31 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package - Potential Water Leak | The T1 expansion tank warning level sensor
had tripped and the level was approximately
1cm from the base of the tank. No trip |
|
|
19
|
Tuesday, March 06, 2012, 15:27 |
Isaac Earle | Repair | Target 1 | Target | Quick Connect Fittings on T1 Target | The air hoses for the profile monitor
supply line were inspected and no cracking
was found (was found on T2). The quick |
|