Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep)
|
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for beam schedule 130 is under construction, and will be posted later. |
Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS
|
TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far. |
Friday, March 18, 2016, 11:43, chad fisher, South Hot-Cell, Standard Operation, , , SiC#32 dissection
|
SiC#32 has been open for inspection. |
Monday, March 21, 2016, 10:25, David Wang, Conditioning Station, Repair, TM2, , TM2 Helium pressure Test Result in TCS and ITW
|
TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes.
The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr for both ITW and TCS. The test results are:
circuit |
TCS Test Result (atm.cc/sec) 2016-03-021 |
ITW Test Result (atm.cc/sec) 2016-03-02 |
TCS Test Result (atm.cc/sec)
2116-11-24
|
Target Oven + |
5.2 X E-9 |
1.7 X E-8 |
2.0 X E-9 |
Target Oven - |
5.6 X E-9 |
8.7 X E-9 |
2.2 X E-8 |
Tube Heater + |
3.7 X E-8 |
1.7 X E-8 |
2.3 X E -8 |
Tube Heater - |
1.9 X E-8 |
1.5 X E-8 |
8.2 X E-8 |
Coil 2 (P-Q) |
7.2 X E-8 |
6.7 X E-8 |
5.4 X E-9 |
Coil 1 (R-U) |
1.4 X E-8 |
1.3 X E-8 |
2.4 X E-9 |
MSP |
2.3 X E-7, SECOND TIME 2.5 X E-7 |
4 X E-9 |
2.4 X E-7 |
HS |
NO TEST, LINE IS OPEN TO VACUUM. |
GOOD, NO RESPONSE ON LD |
Good, 0.0 X E-9 |
EE |
4.3 X E-9 |
GOOD, NO RESPONSE ON LD |
3.7 X E-8
|
window |
4.5 X E-9 |
GOOD, NO RESPONSE ON LD |
Good , 0.0 X E-9 |
GE |
NO TEST, CONFIRMED IN SHC |
MIDDLE OF E-6 RANGE |
No test. Blanked |
|
|
|
|
2016-11-24: Checked again and added result into this elog. No essential change has been found. MSP still has the biggest leak rate. David |
Monday, March 21, 2016, 11:30, David Wang, Conditioning Station, Repair, TM2, , TM2 and TCS vacuum pumps are stopped
|
I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow moving. |
Monday, March 21, 2016, 15:27, David Wang, Conditioning Station, Repair, TM2, , TM2 has been disconnected at TCS
|
TM2 vacuum system has been disconnected at TCS. Venting is in process now. |
Wednesday, March 23, 2016, 11:32, David Wang, South Hot-Cell, Repair, TM2, , TM2 Helium spray leak check on GE and MSP lines at SHC
|
Chad and I did the helium spray leak check on TM2 GE and MSP water lines at SHC this morning. We confirmed the GE leak on water blocks. We can not found the MSP leak by using the helium spray since its leak rate in TCS is much smaller than GE leak. The leak check process are as below:
Leak detector are calibrated before the check.
GE lines : Base leak rate 0.0 X E-9 atm.cc/sec, base pressure 0.0 XE-4 torr.
Chad sprayed 5 psi helium to GE lines soldering joints for 5 second, no response on leak detector.
Chad sprayed 5 psi helium to GE lines water blocks( between blocks seal surface) for 5 seconds, Leak detector response to 8 XE-9 atm.cc/sec right away.
Chad sprayed 5 psi helium to GE lines soldering joints for 5 seconds again, No response on leak detector.
Chad sprayed 5 psi helium around the source tray and to vacuum duct for 5 seconds more, No response on leak detector.
MSP lines: Base leak rate 0.0X E-9 atm.cc/sec, base pressure 0.0 X E-4 torr. Chad did same thing as he did on GE lines. no response on LD. Chad repeated the test and prolonged the spray time to 10 seconds, No response.
The conclusion: It is pretty clear we have a leak on GE line water blocks seal. MSP lines leak could not be found by helium spray in SHC since it is a small leak.
|
Thursday, March 24, 2016, 13:15, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 and TCS vacuum system has been connected
|
TM1 and TCS vacuum system have been connected. All turbo-pumps are started. The pumping down is fine. |
Tuesday, March 29, 2016, 08:38, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 water lines helium pressure check at TCS
|
TM1 water lines helium pressure check at TCS is done. 70 psi helium was applied to water circuits. Leak detector base leak rate 0.0 x E-9 atm.cc/sec, base pressure 0.0 x E-4 torr. The result shows as below:
Ta+ |
0.0 X E-9 atm.cc/sec |
3minutes stabilizing |
Ta- |
0.0 X E-9 atm.cc/sec |
3minutes stabilizing |
Tube- |
0.0 X E-9 atm.cc/sec |
3minutes stabilizing |
Tube+ |
0.0 X E-9 atm.cc/sec |
3minutes stabilizing |
MSP |
0.0 X E-9 atm.cc/sec |
3minutes stabilizing |
EE |
0.0X E-9 atm.cc/sec |
3minutes stabilizing |
HS |
not tested without caps. |
|
Window |
E-5 range,leak on stem as we knew before. |
10seconds to E-5 |
The results is good so far as we know the window line is leak on stem in service cap. The HS will be tested later with target on.
The service cap air to vacuum seals also have been checked. The PNG1 panel and side round panel close to shutter are leak. The o-rings on them need to be replaced.
On March 30th -2016, I doubled checked the air to vacuum seal on the TM1 service cap. The side round panel is leak free actually. The PNG1 panel is leak at the bottom side. Confirmed.
On march 31th-2016, The o-ring(1-1/ 2275) on TM1 PNG1 side panel has been replaced today. The o-ring slot and mating surfaces are cleaned, and new o-ring is installed. The panel is put back to TM1 and all bolts are tightened.
See attachments. |
Wednesday, March 30, 2016, 08:40, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule
|
update the schedule according to changes.See attachment1, 2. |
Wednesday, March 30, 2016, 15:49, David Wang, Assembly/Bench Test, Repair, TM2, , TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. 7x
|
On each water circuit in side the service cap, there are 4 soldering stems which two of them are inside blue nylon insulator and other two are connected to service tray. Each stem has two soldering spots. See attachment pictures for detail location. I sprayed 15 psi helium on each soldering spots on stems for 20second on each circuit. I sprayed tons of helium inside each blue nylon.No any leak has been found during the check. The leak detector base leak rate:0.0 XE-9 atm.cc/sec, base pressure:0.0X E-4 torr. The circuit which I checked are :TA+, Ta-, Tube+, Tube-, PQ (coil 2), RU( coil1), EE, MSP, GE. The HS and window circuit are opened at this moment so they can not be checked. |
Friday, April 01, 2016, 14:41, David Wang, Conditioning Station, Standard Operation, TM1, , TM1 and TCS vacuum system has been connected. TCS control page white out.
|
I can not start the TCS pumps due to control page white out. Control group is working on this issue.
Control group fixed the white out problem. I started all turbo-pumps. The pumping down is good so far. The TM1 IG1 is broken. I will check it on next Monday. It could be a broken filament. Then, the filament will be replaced. |
Monday, April 04, 2016, 11:14, David Wang, Conditioning Station, Standard Operation, TM1, , Helium pressure test on TM1 HS line at CS
|
New UCx target is installed on the module. 70psi helium,3 minutes. NO response on LD. LD is pumped to bottom LR and LP during test. |
Tuesday, April 05, 2016, 12:36, David Wang, ITW, Standard Operation, TM1, , TM1 vacuum system has been connected in ITW.
|
All turbo -pumps are started. |
Tuesday, April 05, 2016, 12:40, David Wang, ITE, Standard Operation, TM4, , I stopped ITE turbo pumps this morning
|
The ITE and TM4 have been vented with Argon . TM4 vacuum system is disconnected in ITE. |
Friday, April 08, 2016, 07:10, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 vacuum has been connected in ITE.
|
All turbo pumps are started yesterday. The pumping down is good over night. |
Friday, April 08, 2016, 08:13, Anders Mjos, ITE/ITW Cooling, Maintenance, , , High Active Water Resistivity
|
The high active water resistivity took a long time to recover after the upgrade to the water cooling circuit. The system needed about a month (from end February to end March) to recover to nominal values. See attached plot of archiver data.
TM1 has now been connected in ITW and the water resistivity remains > 8 MOhm cm, which should allow normal operation. However, the resin is suspected to be approaching end of life. Work is ongoing to get a new replacement resin tank. |
Friday, April 08, 2016, 08:48, David Wang, ITW, Standard Operation, , , ITW water signal interlock check.
|
I did a ITW water signals interlock check with ISAC opp. They are checked once a year before first beam on.
2016-04-13 Same test is done on ITE also. Everything is good. |
Friday, April 08, 2016, 13:16, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule
|
Update schedule weekly .see attachment 1,2 |
Monday, April 11, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM4, , Helium pressure test on TM4 HS line at CS with new Lp Ta target
|
70 psi helium , 2 minutes. Base leak rate 0.0x E-9 atm.cc/sec. base pressure 0.0XE-4 torr. no response on LD.The line is good. |
|