1188
|
Friday, April 01, 2016, 14:41 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 and TCS vacuum system has been connected. TCS control page white out. | I can not start the TCS pumps due to control
page white out. Control group is working
on this issue. |
|
|
1189
|
Monday, April 04, 2016, 11:14 |
David Wang | Conditioning Station | Standard Operation | TM1 | | Helium pressure test on TM1 HS line at CS | New UCx target is installed on the module.
70psi helium,3 minutes. NO response on LD.
LD is pumped to bottom LR and LP during test. |
|
|
1190
|
Tuesday, April 05, 2016, 07:12 |
David Wang | Conditioning Station | Standard Operation | TM1 | UC#15 | stop CS vacuum pumps. | Stop TCS vacuum pumps . Preparing argon
venting on TM1 and TCS.
7:34 AM, Disconnected TM1 at TCS, |
|
|
1192
|
Tuesday, April 05, 2016, 12:36 |
David Wang | ITW | Standard Operation | TM1 | | TM1 vacuum system has been connected in ITW. | All turbo -pumps are started. |
|
|
1193
|
Tuesday, April 05, 2016, 12:40 |
David Wang | ITE | Standard Operation | TM4 | | I stopped ITE turbo pumps this morning | The ITE and TM4 have been vented with Argon
. TM4 vacuum system is disconnected in ITE. |
|
|
1198
|
Friday, April 08, 2016, 07:10 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 vacuum has been connected in ITE. | All turbo pumps are started yesterday.
The pumping down is good over night. |
|
|
1199
|
Friday, April 08, 2016, 07:13 |
David Wang | ITW | Standard Operation | TM1 | UCx15 | TM1 has been connected in ITW. | After ITW HV test is done, TM1 has been
connected to ITW. Water signals are checked
in electrical room. They are good. |
|
|
1201
|
Friday, April 08, 2016, 08:48 |
David Wang | ITW | Standard Operation | | | ITW water signal interlock check. | I did a ITW water signals interlock check
with ISAC opp. They are checked once a year
before first beam on. |
|
|
1202
|
Friday, April 08, 2016, 13:16 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | Update schedule weekly .see attachment
1,2 |
 |
|
1203
|
Monday, April 11, 2016, 09:42 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Helium pressure test on TM4 HS line at CS with new Lp Ta target | 70 psi helium , 2 minutes. Base leak rate
0.0x E-9 atm.cc/sec. base pressure 0.0XE-4
torr. no response on LD.The line is good. |
|
|
1205
|
Monday, April 11, 2016, 13:44 |
David Wang | Conditioning Station | Standard Operation | TM4 | | I stopped TCS and TM4 vacuum pumps. | The TM4 is still under vacuum at TCS. It
will be vented tomorrow morning.
I disconnected TM4 vacuum system |
|
|
1207
|
Tuesday, April 12, 2016, 11:41 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been connected in ITE. | Tm4 has been connected in ITE. The ITE
and TM4 is under roughing now. ITE
Turbo-pumps have been started. Everything |
|
|
1209
|
Wednesday, April 13, 2016, 10:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TCS is under roughing now. |
|
|
1210
|
Wednesday, April 13, 2016, 10:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TCS is under roughing now.
2016-04-14, Started TCS and TM2 turbo-pumps
yesterday afternoon. Overnight pumping down |
|
|
1212
|
Thursday, April 14, 2016, 12:56 |
David Wang | ITW | Standard Operation | TM1 | | 5 shielding blocks have been moved to ITW. | The ITW is configured to take proton beam. |
|
|
1213
|
Monday, April 18, 2016, 09:07 |
David Wang | Conditioning Station | Repair | TM2 | | venting TCS with argon. | Anders reported a possible air leak on
TM2 and TCS by watching RGA this morning.
I found the quick connector on F terminal |
|
|
1214
|
Friday, April 22, 2016, 14:07 |
David Wang | Conditioning Station | Standard Operation | TM2 | | 2016 Winter Shut Down Target Hall Schedule | Weekly update.This is the last update on
2016 winter shut down schedule. The new TH
schedule for beam130 will be posted |
 |
|
1215
|
Monday, April 25, 2016, 12:18 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) | Post MS project and Excel
target hall schedule for beam schedule 130
see attachments 1,2 |
7x |
|
1216
|
Tuesday, April 26, 2016, 10:47 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 leak check at TCS, water test. | The following water circuits in TM2 are
connected at TCS and running with water
now : target oven+ - ( one circuit), tube |
|
|
1217
|
Thursday, April 28, 2016, 06:28 |
David Wang | Conditioning Station | Maintenance | TM2 | | TCS water system are turned off. | TCS water system worked fine overnight.
I turned off TCS water system at 6:16 AM
this morning. Start of purging TM2 water |
|