  ID Date Author Category Type Module Target/Number Subject Text Attachments
  2653   Friday, August 09, 2024, 19:01 David WangITWStandard OperationTM3TiC#8.TM3 has been connected in ITW.TM3 has been connected in ITW. See attachment
for checklist.
 TM3_TiC#8_connection_in_ITW_checklist.pdf 
  2652   Friday, August 09, 2024, 18:20 David WangITWStandard OperationTM3TiC#8TM3 has been moved from SHC to ITW.With TiC # 8 installed, TM3 has been moved
from SHc to ITW. The move is smooth. 
  
  2651   Friday, August 09, 2024, 18:18 David WangITWStandard OperationTM4TiC#7Tm4 has been moved from ITW to SMP.Tm4 has been moved from ITW to SMP. the
move is successful. 
  
  2650   Friday, August 09, 2024, 16:15 Frank SongSouth Hot-CellRepairTM3TiC#8electrical check/leak check TM3 with replaced target TiC#8 has
been checked on SHC before moving to ITW.
Pls see attachment
 electrical_and_leak_check_of_TM3_with_new_target_TiC#8_replaced_at_SHC_20240809.pdf 
  2649   Friday, August 09, 2024, 08:11 Frank SongITWStandard OperationTM4TiC#7module disconnection TM4 with spent target TiC#7 (dead)
was disconnected in ITW and ready to move
to TCS.
 TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf 
  2648   Thursday, August 08, 2024, 13:58 David WangSouth Hot-CellStandard OperationTM3SiC #46TM3 SiC#46 electrical check at SHC with target on (After operation)ABCD is short to 60KV bias. Othjer are
ok.  see attachment.
Found afterwards that this short
 TM3_Sic_46_after_run_E_check.pdf 
  2647   Thursday, August 08, 2024, 11:41 David WangSouth Hot-CellStandard OperationTM3SiC #46Tm3 was moved from ITE to TCS this Tuesaday, then to SHC this morning.Tm3 was moved from ITE to TCS this Tuesday,
then to SHC  this morning. Both moves
are successful.
  
  2646   Tuesday, August 06, 2024, 09:16 Frank SongITEStandard OperationTM3SiC#46module disconnection TM3 with spent target SiC#46 was
disconnected in ITE and ready to move to
TCS soon.
 TM3_with_SiC#46_disconnection_in_ITE_2024-08-0106.pdf 
  2645   Wednesday, July 24, 2024, 10:10 Frank SongITE/ITW/Storage AreaStandard Operation  shielding blocks transfer 5 shielding blocks have been transferred
from ITE to ITW. MAA is secured again after
moving.
  
  2644   Thursday, July 18, 2024, 11:22 Travis CaveSpent Target VaultStandard Operation UC#45Spent Target Move The UC#45 target was moved from the
south hot cell to the spent target vault.
It was place in Pail#292 spot 1A of the vault,
 Target_Index_2024-07-18.pdf 
  2643   Wednesday, July 17, 2024, 15:06 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround Complete - SHC/NHC AreaA safety walkaround for July 2024 was completed
for the B2 level by A. Newsome. No deficiencies
to report.
  
  2642   Tuesday, July 16, 2024, 13:14 Frank SongITWStandard OperationTM4TiC#7Module Connection TM4 with TiC#7 was connected in ITW,
all TPs are running at full speed.
 TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdfMicrosoftTeams-image_(65).png 
  2641   Tuesday, July 16, 2024, 11:15 David WangITWStandard OperationTM4TiC #7 febiad. TM4 has been moved from TCS to ITW. TM4 has been moved from TCS to ITW. 
the move is smooth.
  
  2640   Tuesday, July 16, 2024, 11:15 David WangITWStandard OperationTM4TiC #7 febiad. TM4 has been moved from TCS to ITW. TM4 has been moved from TCS to ITW. 
the move is smooth. 
  
  2639   Friday, July 12, 2024, 08:51 Riley SykesSafe Module ParkingMaintenance  SMP chain guard SS washers were added to all slotted
holes on SMP chainguard cover plate
  
  2638   Wednesday, July 10, 2024, 10:44 Riley SykesSouth Hot-CellMaintenance  Spring idler install New spring idlers were installed
onto rotational chain drive for SHC roof.
Operation ran smoothly in both directions
 Image.jfifImage_(2).jfif 
  2637   Wednesday, July 10, 2024, 09:55 Adam NewsomeSafe Module ParkingMaintenance   Annual electrical and mechanical inspection of Safe Module Parking An annual electrical and mechanical inspection
was performed on the   SMP today by Adam
Newsome, Travis Cave, Riley Sykes, Maico
 PXL_20240710_160636341.jpgPXL_20240710_160506424.jpg 
  2636   Tuesday, July 09, 2024, 16:14 Carla BabcockITERepair  Attempts to reduce ITE:EL trips from HV sparksITE:EL has been tripping off due to HV
sparks. Usually this also trips ITE:Q1/2.
These are sitting in side-by-side racks.
 8x 
  2635   Monday, July 08, 2024, 10:40 David WangConditioning StationStandard OperationTM4TiC#7TM4 has been moved from SHC to TCS.TM4 has been moved from SHC to TCS. The
move is successfully. 
  
  2634   Friday, July 05, 2024, 14:13 Adam NewsomeWaste Package/ShipStandard Operation   F-308 flask loading - five flasks loaded Today (2024-07-05), five flasks were loaded
in preparation for  shipment with the following
targets: SiC#43 (Pail 272), SiC#44 (Pail
 Target_Index_2024-07-05.xlsm 