  ID Date Authordown Category Type Module Target/Number Subject
  2500   Wednesday, November 08, 2023, 12:14 Frank SongSouth Hot-CellStandard OperationTM4UCx#43electrical check/leak check

 TM4 with new target UCx#43 was electrical and leak checked on SHC.

Attachment 1: TM4_electric_and_leak_checked_after_UCx#43_installed_2023-11-08.pdf
TM4_electric_and_leak_checked_after_UCx#43_installed_2023-11-08.pdf
  2528   Monday, January 22, 2024, 14:12 Frank SongITEStandard OperationTM4UCx#43module disconnection

 TM4 with spent target UCx#43 was disconnected in ITE and is ready moved to SHC. see attachment pls.

Attachment 1: TM4_with_UCx43_disconnected_in_ITE_2024-01-22.pdf
TM4_with_UCx43_disconnected_in_ITE_2024-01-22.pdf TM4_with_UCx43_disconnected_in_ITE_2024-01-22.pdf TM4_with_UCx43_disconnected_in_ITE_2024-01-22.pdf
  2573   Tuesday, April 30, 2024, 08:00 Frank SongSouth Hot-CellStandard OperationTM4Lp-Febiad emptyelectrical check/leak check

 David Wang made E/L checking before module moving to ITW. read attachment pls.

Attachment 1: TM4_with_Lp-Febiad_empty_target_checking_on_SHC_2024-04-29.pdf
TM4_with_Lp-Febiad_empty_target_checking_on_SHC_2024-04-29.pdf TM4_with_Lp-Febiad_empty_target_checking_on_SHC_2024-04-29.pdf
  2587   Wednesday, May 08, 2024, 14:01 Frank SongITWMaintenance  Annual clean up for ITW Faraday cage

The ITW Faraday Cage has been cleaned, this is part of Winter Shut Down job happens in ISAC-1 Electric maintenance room annually.

  2597   Thursday, May 23, 2024, 10:59 Frank SongITEStandard OperationTM3UCx#44shielding blocks transfer

 the five shielding blocks have been moved from storage area to ITE and is ready for beam delivery.

submitted WP# I2024-05-22--1

actived  WP # I2024-05-23-4

  2602   Tuesday, May 28, 2024, 13:49 Frank SongITWStandard OperationTM4UCx#45Module Connection

 TM4 with new target UCx#45 was connected in ITW this morning. pls see attachment uploaded with.

Attachment 1: TM4_with_UCx#45_connection_in_ITW_20240528.pdf
TM4_with_UCx#45_connection_in_ITW_20240528.pdf TM4_with_UCx#45_connection_in_ITW_20240528.pdf TM4_with_UCx#45_connection_in_ITW_20240528.pdf TM4_with_UCx#45_connection_in_ITW_20240528.pdf
  2607   Monday, June 10, 2024, 11:02 Frank SongITWStandard OperationTM4UCx#45shielding blocks transfer

 5 shielding blocks have been transferred from ITE to ITW. 

Doc # 181007

 

  2610   Friday, June 14, 2024, 11:18 Frank SongITEStandard OperationTM3UCx#44module disconnection

 TM3 with target UCx#44 was disconnected in ITE. 

Attachment 1: TM3_with_UCx#44_disconnection_in_ITE_2024-06-14.pdf
TM3_with_UCx#44_disconnection_in_ITE_2024-06-14.pdf TM3_with_UCx#44_disconnection_in_ITE_2024-06-14.pdf TM3_with_UCx#44_disconnection_in_ITE_2024-06-14.pdf
  2625   Tuesday, June 25, 2024, 12:49 Frank SongITEStandard OperationTM3SiC#46Module Connection

 TM3 with new target SiC#46 was connected in ITE.

Attachment 1: TM3_with_SiC#46_connection_in_ITE_2024-06-25.pdf
TM3_with_SiC#46_connection_in_ITE_2024-06-25.pdf TM3_with_SiC#46_connection_in_ITE_2024-06-25.pdf TM3_with_SiC#46_connection_in_ITE_2024-06-25.pdf TM3_with_SiC#46_connection_in_ITE_2024-06-25.pdf
  2628   Tuesday, July 02, 2024, 11:38 Frank SongITE/ITW/Storage AreaStandard Operation  shielding blocks transfer

 5 shielding blocks have been moved from ITW to ITE, MAA area has been secured.

  2631   Thursday, July 04, 2024, 11:45 Frank SongITWStandard OperationTM4UCx#45module disconnection

TM4 with spent target UCx#45 was disconnected in ITW and moved to SHC.

 TM4 move from ITW to SHC is smooth.

Attachment 1: TM4_with_Spent_Target_UCx#45_disconnection_in_ITW_2024-07-04.pdf
TM4_with_Spent_Target_UCx#45_disconnection_in_ITW_2024-07-04.pdf TM4_with_Spent_Target_UCx#45_disconnection_in_ITW_2024-07-04.pdf TM4_with_Spent_Target_UCx#45_disconnection_in_ITW_2024-07-04.pdf
  2642   Tuesday, July 16, 2024, 13:14 Frank SongITWStandard OperationTM4TiC#7Module Connection

 TM4 with TiC#7 was connected in ITW, all TPs are running at full speed.

Attachment 1: TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf
TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf
Attachment 2: MicrosoftTeams-image_(65).png
MicrosoftTeams-image_(65).png
  2645   Wednesday, July 24, 2024, 10:10 Frank SongITE/ITW/Storage AreaStandard Operation  shielding blocks transfer

 5 shielding blocks have been transferred from ITE to ITW. MAA is secured again after moving.

  2646   Tuesday, August 06, 2024, 09:16 Frank SongITEStandard OperationTM3SiC#46module disconnection

 TM3 with spent target SiC#46 was disconnected in ITE and ready to move to TCS soon.

Attachment 1: TM3_with_SiC#46_disconnection_in_ITE_2024-08-0106.pdf
TM3_with_SiC#46_disconnection_in_ITE_2024-08-0106.pdf TM3_with_SiC#46_disconnection_in_ITE_2024-08-0106.pdf TM3_with_SiC#46_disconnection_in_ITE_2024-08-0106.pdf
  2649   Friday, August 09, 2024, 08:11 Frank SongITWStandard OperationTM4TiC#7module disconnection

 TM4 with spent target TiC#7 (dead) was disconnected in ITW and ready to move to TCS.

Attachment 1: TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf
TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf
  2650   Friday, August 09, 2024, 16:15 Frank SongSouth Hot-CellRepairTM3TiC#8electrical check/leak check

 TM3 with replaced target TiC#8 has been checked on SHC before moving to ITW. Pls see attachment

Attachment 1: electrical_and_leak_check_of_TM3_with_new_target_TiC#8_replaced_at_SHC_20240809.pdf
electrical_and_leak_check_of_TM3_with_new_target_TiC#8_replaced_at_SHC_20240809.pdf
  2656   Tuesday, August 13, 2024, 08:39 Frank SongSouth Hot-CellStandard OperationTM2Ta#67electrical check/leak check

 TM2 with new target Ta#67 had been electric/leak checked before moving to ITE. See attachment pls.

Attachment 1: TM2_with_Ta@67_electric_and_leak_check_on_SHC.pdf
TM2_with_Ta@67_electric_and_leak_check_on_SHC.pdf
  2657   Tuesday, August 13, 2024, 14:18 Frank SongITEStandard OperationTM2Ta#67Module Connection

 TM2 with new target Ta#67 was connected in ITE, all TP are running at their full speed now.

Attachment 1: TM2_with_Ta#67_connection_in_ITE_20240813.pdf
TM2_with_Ta#67_connection_in_ITE_20240813.pdf TM2_with_Ta#67_connection_in_ITE_20240813.pdf TM2_with_Ta#67_connection_in_ITE_20240813.pdf TM2_with_Ta#67_connection_in_ITE_20240813.pdf
  2662   Friday, August 16, 2024, 13:29 Frank SongSouth Hot-CellStandard OperationTM4Ta#68electrical check/leak check

 New target Ta#68 is installed on TM4 and be leak/electric checked. Pls see attachment.

Attachment 1: TM4_with_Ta#68_electric_and_leak_check_on_SHC_2028-08-16.pdf
TM4_with_Ta#68_electric_and_leak_check_on_SHC_2028-08-16.pdf
  2666   Monday, August 19, 2024, 15:29 Frank SongITW/ITEStandard OperationTM2Ta#67shielding blocks transfer

 5 shielding blocks have been transferred from ITW to ITE, MAA has been secured after moving.