  265   Thursday, March 14, 2013, 11:25 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Turbos Started

 Turbos started at 11:14. TP1S achieved full speed in less than 2 minutes. TP1 and 2 tripped at 9 minutes. Restarted and reached at speed after another 1 minute 20 seconds.

Attachment 1: turbo_started_1115.JPG
turbo_started_1115.JPG
Attachment 2: vacuum_running_1124.JPG
vacuum_running_1124.JPG
  540   Tuesday, November 12, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM2 Turbo pumps started

 The turbo pumps have been started on TM2 and the conditioning station.

  2417   Tuesday, February 14, 2023, 11:36 David WangAssembly/Bench TestRepair  Turbo pump BVs o-ring replacement.

Five of used  internal leaked  TP BVs are serviced and repaired. Internal plunge  o-ring and case o-ring are replaced on all five BVs. Leak checked valves after  . They are ok to be used as spare parts.  The are active parts stored in TH now.

  270   Tuesday, March 19, 2013, 09:55 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Turbo pump 1 replaced roughing started

 David replaced the broken turbo pump this morning and I have started roughing at 9:54.

  360   Thursday, May 23, 2013, 14:08 Bevan MossConditioning StationStandard OperationTM4Ta #40Turbo Pumps on

 The turbo pumps have been turned on and are running

  513   Friday, October 18, 2013, 15:55 Bevan MossConditioning StationStandard OperationTM4 Turbo Pumps are on

 The Turbo pumps are now running on TCS

  308   Friday, April 19, 2013, 13:32 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Started

 Both Turbo Pumps are now operational.

  309   Friday, April 19, 2013, 15:25 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Started

Bevan Moss wrote:

 Both Turbo Pumps are now operational.

 Turbo pumps 1 and 2 both found randomly off, have been restarted

  340   Friday, May 10, 2013, 14:05 Bevan MossConditioning StationStandard OperationTM3No Source TrayTurbo Pumps On

The turbo pumps are on. TP1 and TP2 once again timed out and had to be restarted before they would stay on.

  304   Wednesday, April 17, 2013, 15:17 Bevan MossConditioning StationStandard OperationTM3N/ATurbo Pumps Failed

 Both Turbo pumps on TM3 have failed. They were both attempted to start in soft mode. TP2 could only achieve ~19kpm and TP1 ~10kpm. I have turned off the scroll pump and vented through the turbo pumps.

  305   Friday, April 19, 2013, 10:48 Bevan MossConditioning StationMaintenanceTM3N/ATurbo Pump 2 replaced

 Turbo Pump 2 has been replaced on TM3. I got a count of 350 on the sleeve of my tank suit.

  306   Friday, April 19, 2013, 10:48 Bevan MossConditioning StationMaintenanceTM3N/ATurbo Pump 2 replaced

 Turbo Pump 2 has been replaced on TM3. I got a count of 350 on the sleeve of my tank suit.

  39   Tuesday, October 25, 2011, 16:57 Bevan MossConditioning StationStandard OperationTM4 Turbo Pump 1 issues

Roughing on TM1 started at ~15:00 today by ~16:30 the module had reached a pressure of ~200 mTorr and the turbo pumps were turned on. TP1 failed to achieve normal operation and we running at approximately 4KRPM and 50W with 6.1 A of current draw. TP2 was able to achieve normal operation. The controller for TP1 was then powered off and back on but that failed to resolve the issue. The controllers for TP1 & 2 were then switched at which point TP1 again failed normal operation and TP2 achieved it, thus eliminating the controller as the issue. The turbo pumps have been turned off and the roughing pump left on for overnight in case Vacuum group wishes to do any additional diagnosis. 

  267   Monday, March 18, 2013, 12:03 Bevan MossConditioning StationRepairTM4CS Test Target #1Turbo Pump 1 Failure and Venting

 Over the weekend Turbo pump one failed. It was attempted to restart the turbo in soft start but that also failed. Although the Vacuum was good enough to operate both Turbos are required to pass commissioning. As such the pumps were turned off at ~10:00 today. Venting started at 12:00.

  271   Tuesday, March 19, 2013, 13:49 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Tubros Started

 Turbo Pumps have been started and are in normal operation. TP1 which has recently been replaced was started in soft start and had no issues. TP2 was started normally and tripped prior to reaching speed. It was left for a while and restarted. When restarted it was still at 17KRPM, it reached normal operation.

  41   Friday, October 28, 2011, 09:30 chad fisherSouth Hot-CellRepairTM4 Tube Heater + Leak Check C.B.

Base Pressure: 0.0x10-4

Stable Leak Rate: 0.0x10-9

Leak check of tube heater circuit, containment box side was performed.

Initail check at tube heater block on source tray yeilded a response 60 sec after the 2 second spray of helium. The response was very small and recovered immediately.

This area was checked twice more but the reponse could not be recreated.

Joint at the waterblocks was tested with an intial 2 sec spray. No response after 60 sec.

Waterblock joint was tested again with a 4 second spray. No response after 60 sec.

 

 

 

  1675   Thursday, January 04, 2018, 13:28 Anders MjosConditioning StationMaintenance  Troubleshooting IG1S

TCS:IG1S is reporting vacuum levels that seem to be too low (1E-10 to 1E-8 Torr). The gauge was connected to the controller for IG1, which showed the same value. A degas was performed for ~5 min.

  1896   Thursday, March 21, 2019, 09:56 chad fisherSouth Hot-CellRepairTM2 Tray insertion

This morning new water block fasteners and gas line capture nut fasteners were inserted into the hot cell. Window waterline blank off was removed from TM2, surfaces inspected and given a polish with Veltex (30 seconds, 70 psi) as there was a small bit of c seal residue. Transfer try with new source tray has been latched to the module.

Attachment 1: 20190321_091833.jpg
20190321_091833.jpg
Attachment 2: 20190321_094625.jpg
20190321_094625.jpg
  1883   Tuesday, March 05, 2019, 14:29 chad fisherSouth Hot-CellRepair  Tray Transfer Fixture Repair Complete

Repair of the tray transfer fixture is complete (minus testing).

A distorted ball nut lock plate was replaced and thread loc added. to the ball nut/plate assembly. Testing will take place tomorrow once the thread lock has a chance to cure.

Attachment 1: 20190305_130312.jpg
20190305_130312.jpg
Attachment 2: 20190305_132303.jpg
20190305_132303.jpg
Attachment 3: 20190305_133800.jpg
20190305_133800.jpg
Attachment 4: 20190305_141346.jpg
20190305_141346.jpg
  2754   Monday, January 27, 2025, 08:27 om David WangSouth Hot-CellMaintenance parasite targetTransfer parasite target from SHC to NHC.

A parasite target has been transferred from SHC to NHC. It is a job to reduce SHC field for coming SHC entry job. The transfer is successful.