Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 18 of 138  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subject
  2408   Tuesday, January 24, 2023, 08:46 David WangITEStandard OperationTM4UCx#41TM4 has been disconnected in ITE.

TM 4 has been disconnected in ITE.  See attachment for disconnection checklist.

  2407   Tuesday, January 24, 2023, 07:26 David WangConditioning StationStandard Operation  TH floor moping and garbage collelctions.

Plant group and us  finished TH floor mopping and garbage collections last Wednesday. Th moping head had 800 count after using. all garbage were bagged , checked, tagged, and sent to radwaste area.

  2406   Tuesday, January 24, 2023, 07:21 David WangITWMaintenance  ITW pit general clean up.

 ITW  was cleaned with vacuum canister in Jan 10th. HV  cage inside and blue nylon insulators were wiped.  Garbage inside the pits were cleaned out.

  2405   Tuesday, January 24, 2023, 07:17 David WangITEStandard OperationTM4UCx#41TM4 water lines helium pressure test 2023.

TM4 water lines helium pressure test was done yesterday at ITE. All water lines were air purged one day ahead  for the test. No leak  has been found on TM4 waterlines during the test. See attachment for detail

  2404   Wednesday, January 11, 2023, 11:34 Travis CaveSpent Target VaultStandard Operation UC#40Spent Target Move

 UC#40 was moved from the north hot cell to the spent target vault. It was placed in pail #278 put in spot 1B and was 15.6 mSv/hr when removed from the north hot cell.

Also Ta#62 in pail #256 was moved from spot 7B back to 7A where it was originally located. This pail in the future will have to be repacked due to the fact it lacks a reinforcing disc in the bottom of the pail.

attached is vault details.

  2403   Tuesday, January 10, 2023, 10:15 Frank SongSafe Module ParkingStandard OperationTM2UCx40 removedTM2 electrical check with no target attached on SW silo

 TM2 with no target on SW silo be electrical checked right after module moving.

  2402   Monday, January 09, 2023, 14:19 Frank SongITWStandard OperationTM2UCx#40TM2 with UCx40 disconnection in ITW

 TM2 with target UCx40 was disconnected in ITW and moved to NHC.

  2401   Friday, January 06, 2023, 10:38 David WangITWStandard OperationTM2 ITW/TM2 vacuum vessels leak check and TM2 internal cooling lines helium pressure test.

ITW and TM2 primary and secondary vacuum vessel leak check is done. Leak detector is connected to ITW TP1. Base leak rate on leak detector is 0.0 x E-9 atm.cc/sec.   See attachment for the result.  No big issue. Two old leaks we found last year at location D and E disappeared in this check. We did Vacseal resin spray on them last year.  It looks like the Vacseal spray works .  From the result , I can see the o-ring between exit 1 module and T - flange is closing to the end of the life.  There are two small leaks on this o-ring now at A and B location. We plan to change this o-ring next winter shut down. We do vacseal spray on them this year. The big O-ring between tank vessel and T -flange looks still ok. Two small leaks are found on location F and G on this O-ring. Not much we can do on them. The leak on location C and B were sprayed with resin yesterday after leak check. They are leak free after spray on check. I will double check them. Leak on location A will be resin sprayed after TM2 is removed and ITW is under vacuum.   All TM2 internal water-cooling lines are helium pressurized (70 psi) for 5 minutes each. HS shows 2.5 X E-9atm.cc/sec leak rate. The rest lines are 0.0 X E-9 atm.cc/sec.

  2400   Friday, January 06, 2023, 09:41 Adam NewsomeSpent Target VaultStandard Operation  Pails moved to mini-storage vault

The following three pails were moved from the main storage vault to the mini-storage vault:

1. #211, Ta#58 (formerly vault location 3C)
2. #217, ZrC#8 (formerly vault location 3A)
3. #228, UC#37 (formerly vault location 1B)

 

The target index spreadsheet has been updated.

  2399   Friday, December 16, 2022, 16:39 Adam NewsomeCraneStandard Operation  Crane powered off for holidays

[edit 2023-01-03] The crane was powered back on this morning - there do not appear to be any faults and it seems that the crane was unaffected by the power outage.

The ISAC target hall overhead crane was powered off for the holidays. Note that this may result in the commonly observed PLC battery failure issue when the crane is powered back on in the new year.

  2398   Friday, December 16, 2022, 16:35 Adam NewsomeSpent Target VaultStandard Operation  Pails measured, moved to mini-storage vault

The following five pails were moved to the mini-storage vault today under work permit I2022-12-16-1:

  • #239 (formerly vault location 7A): 1.38 mSv/h @ 1m
  • #245 (formerly vault location 6B): 1.56 mSv/h @ 1m
  • #264 (formerly vault location 6A): 748 uSv/h @ 1 m
  • #267 (formerly vault location 1C): 708 uSv/h @ 1 m
  • #268 (vault location 7C): 809 uSv/h @ 1 m

The mini-storage vault is now full and ready for transfer to F-308 flasks.

The following measurements were made on other pails:

  • #211 (vault location 3C): 4.21 mSv @ 1 m
  • #217 (vault location 3A): 1.05 mSv/h @ 1 m
  • #246 (vault location 6C): 1.98 mSv/h @ 1m
  • #274 (vault location 1A): 4.78 mSv/h @ 1 m
  • #228 (vault location 1B): 3.86 mSv/h @ 1 m
  • #256 (vault location formerly 7A, now 7B): 3.60 mSv/h @ 1 m
  • #260 (vault location 5B): 1.46 mSv/h @ 1 m

The target index spreadsheet has been updated to reflect these changes. See attached PDF print.

  2397   Thursday, December 01, 2022, 13:45 Carla BabcockNorth Hot-CellStandard OperationTM4C#4Post irradiation inspection C#4

Post irradiation inspection of C#4 which was running in TM4/ITE was conducted at the NHC on Nov. 22 2022.

The yields from this target had been dropping and its behaviour was erratic, with the voltages on the tube and target jumping all over the place sometimes. The ion current on the FCs followed the voltages. We took this to mean the target container was breaking down.

Upon inspection we found the container looked pretty damaged - highly crystallized and distorted. The container had gone banana-shaped, but not in the usual direction. It had curved  in the direction of the ion source (see photos). The heat shield and other surrounding components were super clean, no deposits or marks at all.

  2396   Thursday, December 01, 2022, 08:20 Frank SongITEStandard OperationTM4UCx#41Module Connection

 TM4 with UCx#41 was connected in ITE on Tuesday (2022-11-29) 

  2395   Tuesday, November 29, 2022, 11:03 Adam NewsomeITEStandard OperationTM4C#4TM4 Move - TCS to ITE

TM4 was moved from the Conditioning Station to the East Target Station with C#4.

  2394   Thursday, November 24, 2022, 11:32 Adam NewsomeSpent Target VaultStandard OperationTM4C#4C#4 Spent Target Moved to Storage Vault

C#4 spent target was moved to the storage vault, in pail 277. Dose rate at approximately 1 m when leaving the hot cell was 164 mSv/h. The pail has been placed in vault location 4C. See updated vault layout attached.

  2393   Wednesday, November 23, 2022, 12:10 Adam NewsomeConditioning StationStandard OperationTM4UCx#41TM4 Move - NHC to TCS

TM4 was moved from the North Hot Cell to the Target Conditioning Station with UCx#41.

  2392   Wednesday, November 23, 2022, 11:27 Frank SongNorth Hot-CellStandard OperationTM4UCx#41electric and leak check after new target installed

 an electric check and leak check done on NHC, TM4 with new target UCx#41 is ready moving to TCS.

  2391   Tuesday, November 22, 2022, 14:53 Carla BabcockNorth Hot-CellMaintenanceTM4 Multipin connector alignment pin on TM4 module loose

The pin on TM4 has become loose again, making it very difficult to remove the multipin connector with the last target, C#4. For the installation of the next target, UCx#41, we will drill out the hole on the target side bracket so that it doesn't contact the multipin pin. Will try to remove this pin by force in January, or if needed change out the whole multipin bracket.

  2390   Tuesday, November 22, 2022, 12:41 Frank SongNorth Hot-CellStandard OperationTM4C#4electrical check

 TM4 with C#4 is checked on NHC right after moving from ITE.

  2389   Tuesday, November 22, 2022, 10:37 Adam NewsomeNorth Hot-CellStandard OperationTM4 TM4 Move - ITE to NHC

TM4 was moved from ITE to NHC with C#4.

ELOG V2.9.2-2455