Message ID: 2470     Entry time: Tuesday, August 01, 2023, 09:06
Author: Adam Newsome 
Category: Crane 
Type: Development 
Module:  
Target/Number:  
Subject: Measuring Tape and Camera Removed from Target Hall Crane 

In an effort to clean up the camera installation on top of the ISAC target hall crane to resolve a fault, the position measuring tape and its associated camera were removed from the target hall crane on July 31, 2023.

 

Still to do: clean up power bar installation.