ID Date Author Categorydown Type Module Target/Number Subject
  44   Friday, October 28, 2011, 14:42 Bevan MossSouth Hot-CellMaintenanceTM4 Leak check on service cap feed through

 After Chad and Davids leak check results from the containment box it was decided to perform a leak check on the feed through stem in the service cap. This is a known point of failure on TM1 and the same design flaw is likely in TM4. Once the service cap was open a visual inspection was performed and some oxidization of the copper line on the tube heater (+) circuit was observed (see attached pictures). The leak check was performed with the cart at a base pressure of 0.0 x 10^-4 Torr and base leak rate of 0.0 10 x 10^-9 atm cc/sec. A total of 4 joints were checked and no response was found. The service cap was then flooded with helium and once again no response was found. It was decided to give the module a clean bill of health, make note of the baseline test from the conditioning station, and continue to monitor the circuit.  

Attachment 1: IMG_1906.JPG
IMG_1906.JPG
Attachment 2: IMG_1905.JPG
IMG_1905.JPG
Attachment 3: IMG_1908.JPG
IMG_1908.JPG
  45   Monday, October 31, 2011, 08:51 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26 High PoweredModule move

TM#4 with SiC#26 HP moved from the south hot cell to the conditioning station.

  52   Wednesday, November 16, 2011, 07:44 chad fisherSouth Hot-CellStandard OperationTM1TaC#1TaC#1 Removal and inspection

November 15, 2011 removed TaC#1 from TM1 and inspected TM1 for any obivous signs of trouble (Problems with EE at end of run).

Upon starting removal of the high current conductor fastener on A+ (Left oven leg) it became clear right away that the oven of the target was broken as the leg moved as soon as the fasten was loosened.

Inspection of TM1 with the target removed yeilded no obvious signs of trouble, save a piece of capton tape found on the sliding tray directly below the service tray.

 

  53   Wednesday, November 16, 2011, 07:46 chad fisherSouth Hot-CellStandard OperationTM1TaC#1Inspection of TaC#1

Inspection of TaC#1 showed that the oven was indeed broken on the A+ (left oven leg) side of the central block.

See the following for pictures.

https://documents.triumf.ca/docushare/dsweb/View/Collection-7438

  56   Friday, November 18, 2011, 09:44 Travis CaveSouth Hot-CellStandard OperationTM1UCx#3Electrical check

Electrical checks of TM#1 with UCx#3 have been completed. They all appear to be with in operational range. All megger checks were done at 500 volts. See attached file for details.

Attachment 1: ITW_UC#3_Elec_check.PDF
ITW_UC#3_Elec_check.PDF
  57   Friday, November 18, 2011, 09:56 chad fisherSouth Hot-CellStandard OperationTM1UCx#3UCx#3 Installation

UCx#3 has been installed on TM1.

Leak check also complete.

Base Leak Rate 0.0 x 10-9

Pressure 0.0x10-4

Two checks on upper heat shield joint - no response (2 sec spray/check)

Two checks on lower heat shield joint - no response(2 sec spray /check)

10 sec flood of all heat shield joints - no response

Electrical check coomplete.

  73   Monday, March 12, 2012, 09:19 Travis CaveSouth Hot-CellStandard OperationTM1UCx#3module move

TM#1 with UC#3 was moved from the west maa to the south hot cell, move went well

  74   Monday, March 12, 2012, 10:03 chad fisherSouth Hot-CellStandard OperationTM1UC#3UC#3 Removal

UC#3 was removed from TM1 this morning. Upon removing the oven heater bolts BOTH legs fell demonstrating that both sides of the oven tube have broken off from the central block.

Target was put into a can under argon for disposal after the module is removed from the cell.

The source tray looked to be in very good, clean condition.

IMG_0610.JPG

Attachment 2: IMG_0616.JPG
IMG_0616.JPG
  75   Monday, March 12, 2012, 11:54 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule moved

TM#1 has been moved from the south hot cell to the north east silo, move went well.

  76   Tuesday, March 13, 2012, 09:42 chad fisherSouth Hot-CellStandard OperationTM1UCx#3UCx#3 Autopsy

An autopsy was performed on UCx#3 yesterday afternoon. This autopsy followed the plan written by Anders. Indeed, both sides of the target oven had seperated from the central block.Pictures were taken by Anders and Pierre.

After the disection the target was placed back in a can under argon. Any small piece were placed in a zip lock bag and also put in the can under argon.

  77   Tuesday, March 13, 2012, 09:43 chad fisherSouth Hot-CellStandard OperationTM1UCx#3UCx#3 to spent vault

UCx#3 was packaged into a spent can, double bagged and the bag and cans filled with argon as much as possible. Lid was attached and can moved to the storage vault. The target was placed in in Pail 93, and placed into slot 1C of the vault, it was 11.7mSv/hr when removed from the south hot cell. See attached file for latest vault details

Attachment 1: Vault_Storage_March_13_2012.pdf
Vault_Storage_March_13_2012.pdf Vault_Storage_March_13_2012.pdf Vault_Storage_March_13_2012.pdf Vault_Storage_March_13_2012.pdf
  78   Tuesday, March 13, 2012, 12:24 Anders MjosSouth Hot-CellStandard OperationTM1UCx#3UCx#3 Autopsy

chad fisher wrote:

An autopsy was performed on UCx#3 yesterday afternoon. This autopsy followed the plan written by Anders. Indeed, both sides of the target oven had seperated from the central block.Pictures were taken by Anders and Pierre.

After the disection the target was placed back in a can under argon. Any small piece were placed in a zip lock bag and also put in the can under argon.

Pictures are available on DocuShare:

https://documents.triumf.ca/docushare/dsweb/View/Collection-8189

ISAC e-log entries:

https://web.accel.triumf.ca/isac_elog/Elog_shift_view.pl?shiftid=10803

See attachment for autopsy plan.

 

 

Attachment 1: Inspection_of_UCx#3_in_the_South_Hot_Cell.docx
  86   Tuesday, April 17, 2012, 10:15 chad fisherSouth Hot-CellStandard OperationTM1Nb#6Target inserted into south hot cell

Nb#6 has been inserted into the south hot cell in preparation for ionstallation onto TM1. During the pre-insertion inspection I noticed that I could see the foil installed into the ionizer tube and that in did not seem to be seated or concentric to the tube itself. I had Anders and Friedhelm check this and they deemed that it was ok.

  87   Tuesday, April 17, 2012, 11:30 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule moved

TM#1 moved from conditioning station to the south hot cell, the module had a field of 16mSv/hr.  The move was not without excitement as the crane decided on its own to move 2 inches west on two occasions during the move.On the second time that the errant moved happened I hit the E-stop on the crane kill the power, the first time it happen it stopped the errant movement on its own.

  88   Thursday, April 19, 2012, 09:36 Travis CaveSouth Hot-CellStandard OperationTM1Nb#6Electrical check

Electrical check has been completed of TM#1 with Nb#6 attached. Our new micro-ohm meter was also used for the first time for this test.

Attachment 1: Elec_Check_TM1_Nb6.PDF
Elec_Check_TM1_Nb6.PDF
  89   Thursday, April 19, 2012, 09:48 David WangSouth Hot-CellStandard OperationTM1LP SIS Nb 6leak check heat shield circuit

Chad and I did a leak check on TM1 Nb5 target heat shield circuit. The leak detector was connected to heat shield circuit.The pumping down  of the  circuit is very smooth.Base leak rate is 0.0xE-9atm.cc/sec,and the base pressure is 0.0xE-4 torr. Chad checked the helium flow downstairs .He sprayed helium to both up and down VCR joints 2seconds each time. There is no any response on leak detector(30 seconds waiting time). Both joints did the same test twice, no response . Finally, he flushed helium around the target for 10 seconds,and i didnt see any response on leak detector either.The heat shield circuit on TM1 Nb5 target is leak tight at this stage.

  100   Tuesday, May 15, 2012, 11:45 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26Electrical check

Results of the electrical check of TM#4 with SiC#26 attached post beam.

Attachment 1: TM#4_SiC#26_FEBIAD_post_beam.PDF
TM#4_SiC#26_FEBIAD_post_beam.PDF TM#4_SiC#26_FEBIAD_post_beam.PDF TM#4_SiC#26_FEBIAD_post_beam.PDF TM#4_SiC#26_FEBIAD_post_beam.PDF
  101   Tuesday, May 15, 2012, 12:14 chad fisherSouth Hot-CellStandard OperationTM4SiC#26SiC#26 removal TM4 degredation

SiC#26 was removed from target module #4 this morning. Target shows the now standard arc marks on the 9 pin connector housing...pictures to follow.

Of greater concern is the amount of "plating out" or "arc" marks on both the insulators and connductor of the TM4 source tray. I will again warn that the source trays historically have a life expectancy, and that TM4 continues to show visual signs that the current source tray is rapidly approaching the end of its useful life!

I understand that one of this years goals is to retrofit TM3; however I fear TM4(and possibly TM1) may fail before this can be released. With the current absence of backup source trays and modules I fear we leave the ISAC program in a very vulnerable position.

 

 

 

Attachment 1: RHB_2236.JPG
RHB_2236.JPG
Attachment 2: RHB_2237.JPG
RHB_2237.JPG
Attachment 3: RHB_2238.JPG
RHB_2238.JPG
Attachment 4: RHB_2239.JPG
RHB_2239.JPG
Attachment 5: RHB_2240.JPG
RHB_2240.JPG
Attachment 6: RHB_2241.JPG
RHB_2241.JPG
Attachment 7: RHB_2242.JPG
RHB_2242.JPG
Attachment 8: RHB_2243.JPG
RHB_2243.JPG
Attachment 9: RHB_2244.JPG
RHB_2244.JPG
Attachment 10: RHB_2245.JPG
RHB_2245.JPG
Attachment 11: RHB_2246.JPG
RHB_2246.JPG
Attachment 12: RHB_2247.JPG
RHB_2247.JPG
Attachment 13: RHB_2248.JPG
RHB_2248.JPG
Attachment 14: RHB_2249.JPG
RHB_2249.JPG
Attachment 15: RHB_2250.JPG
RHB_2250.JPG
Attachment 16: RHB_2251.JPG
RHB_2251.JPG
Attachment 17: RHB_2251.JPG
RHB_2251.JPG
Attachment 18: RHB_2252.JPG
RHB_2252.JPG
Attachment 19: RHB_2253.JPG
RHB_2253.JPG
  102   Tuesday, May 15, 2012, 14:29 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule move

TM#4 moved from the south hot cell to the north east storage silo. No issues with the move.

  104   Thursday, May 17, 2012, 14:08 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule move

TM#4 has been moved from the north east silo to the south hot cell for target installation.  No problems with the move.