Friday, July 24, 2015, 10:04, David Wang, ITE, Standard Operation, , , 5 Shielding blocks have been moved from ITE to block storage area.
|
Dan and I moved 5 shielding blocks from ITE to block storage area. The move is smooth. |
Wednesday, February 06, 2013, 14:34, Bevan Moss, Conditioning Station, Development, TM4, CS Test Target #1, 40kV All Common w/o Water Test
|
Today the module was biased to 40kV in the conditioning station. The current draw was 0uA. Sparking started at 27 kV. I have attached the recording
from the strip tool of the vacuum while we were testing. After consulting Pierre if we should take the module to a higher voltage it was decided not to.
The purpose of this test we to check the interaction between the module, cover, new cooling line, EE and EINZEL cables. This test was considered a success |
Thursday, August 17, 2017, 14:38, Isaac Earle, North Hot-Cell, Development, , , 4/6 NHC roof blocks installed 7x
|
Roof blocks IRH1641, IRH1642, IRH1643, and IRH1644 have been fully assembled, labeled, and installed as per drawing IRH1652. Fabrication
of TCS shield block (IRH1646) and NHC module port block (IRH1645) is still in progress.
|
Thursday, February 25, 2016, 06:48, David Wang, ITE, Standard Operation, , , 4 Shielding blocks have been transferred from ITE to block storage area.
|
Dan and I transferred 4 shielding blocks from ITE to block storage area. The ITE pit is opened now. |
Tuesday, January 06, 2015, 11:14, David Wang, ITE, Standard Operation, TM4, , 4 Shielding blocks have been moved out of ITE .
|
4 shielding blocks have been moved out of ITE to block storage area. Fiona did the survey and with me during the move. |
Friday, March 21, 2014, 16:49, Keith C Ng, ITE, Repair, , , 2a3 window - tank flange inspection   
|
Today:
1) Cleaned flange with methanol and cotton glove, appears to be clean.
|
Monday, March 17, 2014, 15:39, Keith C Ng, ITE, Repair, , , 2a3 window - prep and clean
|
Cleaned top of the ITE vacuum flange and top of window clamp. Attempted to clean the bellows/beam pipe through the wall, mostly dust and small particles.
When cleaning bottom of the wall penetration we picked up a stone/fragment and the vacuum stopped. Appears to be a rock of some kind. 800cpm.
Videos on \\trwindata\groups\remote handling\Videos\2014\2014_2A3window folder, videos 3 and 4. |
Tuesday, March 18, 2014, 16:01, Keith C Ng, ITE, Repair, , , 2a3 window - prep and clean 
|
Continued with vacuuming inside wall penetration to remove debris. Changed filter bag in nilfisk vacuum, left old filter in place however vacuum continues
to stall after >5min use. Vacuum gets quite warm before self shutting off. Debris seems to be falling back down on to joint if vacuum is turned off.
Took some screenshots of video showing removed debris and rust(?) on beam pipe. Video located on remote handling group folder. |
Friday, April 11, 2014, 18:17, Keith C Ng, ITE, Repair, , , 2a3 window - install
|
Today:
1) Installed new cradle and shortened beam pipe section in wall penetration.
- Removed tank dust cover from flange and cleaned |
Thursday, March 13, 2014, 16:23, Keith C Ng, ITE, Repair, , , 2a3 window - inspection 
|
Video inspected 2a3 window joint this morning.
Screenshots from video showing debris forming around aluminum cradle and brown/red dust on top of beam pipe.
|
Wednesday, March 19, 2014, 16:48, Keith C Ng, ITE, Repair, , , 2a3 window - beam tube removal 11x
|
Today:
1) Vaccumed top and around clamp. Disconnected clamp from flanges and removed from beam line. Currently bagged and stored in metal pail next to
target pit area. Clamp is 500 µSv @ 1/2 m. |
Wednesday, April 16, 2014, 17:08, Keith C Ng, ITE, Repair, , , 2a3 window - He leak check
|
Helium leak checked 2a3 window after installing using remote line:
- There was a leak found between the target and entrance module at the target pit, rate of 9E-6 atm-cc/sec.
- One test performed with the remote helium line to the window. There was a response but the leak detector was located above the window access |
Tuesday, May 01, 2018, 10:54, Keith C Ng, ITW, Repair, , , 2a2 window installation and beamtube repair 
|
Yesterday we installed the 2a2 window, the drive screw was torqued until 70
ft-lbs and we stopped, the yoke is not fully closed to its hard stop with roughly 7/8" to 3/4" still to go. Similar to identical conditions to
2a3 beamline window install, see https://elog.triumf.ca/TIS/RH-ISAC/647 for that install. Otherwise |
Wednesday, March 12, 2014, 16:33, Keith C Ng, ITE, Repair, , , 2A3 window removal and replacement    
|
prep'ed area for work:
- removed shield plug from window clamp area
- inspected clamp from tunnel side and from top of target station: video recorder was not working, will try again tomorrow. |
Wednesday, May 09, 2018, 08:48, David Wang, ITW, Repair, , , 2A2 winodw leak check on ITW vacuum vessel.
|
Leak detector is connected to ITW TP4. LD Base leak rate 0.0XE-09 atm.cc/sec. Helium line is connected to existing window leak check 1/8 " copper
tube. Applied 18psi helium for 1 minute. No response on LD. The window seal is good on ITW vacuum vessel. |
Friday, May 04, 2018, 11:21, David Wang, ITW, Repair, , , 2A2 winodw leak check in TH
|
Anders and I leak checked new 2A2 window seal on ITW side. Leak detector was connected to ITW TP4. Base leak rate 0.0Xe-9 atm.cc/sec.
base pressure 0.0xe-4 torr. Sprayed 15-20 psi directly underneath 2A2 window by using exist 2a2 window leak check copper tube. The leak detector
got response in 5 seconds when helium was applied. the leak rate was 5xe-6 atm.cc/sec. Once the helium source was closed, the leak rate dropped quickly |
Friday, March 24, 2017, 11:12, Keith C Ng, Spent Target Vault, Standard Operation, , , 2A window transfer
|
Transfered the 2A window from the ISAC Storage Vault to the Cyclotron Vault Tunnel Storage area. RPG storage form attached. |
Friday, March 24, 2017, 13:21, Travis Cave, Spent Target Vault, Standard Operation, , 2A window, 2A window has been removed from the vault.
|
2A window has been removed from the vault and moved over the cyclotron vault tunnels. Attached is the updated storage vault list. |
Friday, April 05, 2019, 13:44, chad fisher, Spent Target Vault, Development, , , 2019 Pail drop tests
|
Drop test performed January 8, 2019 with 25 lb target, UN pail and lug cover. Drop failed. Lug cover half removed. Pictures and video in docushare
collection 24626.
Second test January8, 2019 UN pail, "new" dish cover, old lock lever ring, 25 lb target. Single drop from 1.2m
onto latch, no sealant. No leaks 24 hours later. Pictures in docushare collection 24626
|
Friday, January 22, 2016, 14:24, David Wang, South Hot-Cell, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule (sketch)   
|
Post a sketch of 2016 winter shut down target hall schedule. see attachment 1,2
UPDATE THE SCHEDULE ACCORDING TO CYCLOTRON SIDE JOB. SEE ATTACHMENTS 3,4 |
|