  2471   Thursday, August 03, 2023, 12:24 Jason ZhangCraneDevelopment  Cleanup of camera installation on target hall crane, installation of replacement laser The cleanup of
the ISAC Target Hall crane and installation
 LaserProgramCalibrationLocation.pngSICK_Laser_Upgrade_Calibration.xlsxInstallation_IMG.png 
  818   Monday, December 08, 2014, 15:22 Anders MjosConditioning StationDevelopmentTM2 Circuit D water testMonday, December 08, 2014, 14:00: Dan M
and Anders connected the water supply to
circuit D and installed the module cover.
 TCS_Heater_Transmission_Power.xlsxCircuit_D_test_results_for_TM2_status_meeting_2014-12-11.pdfHeated_water_leak_test_plan.pdfHeated_water_leak_test_Circuit_D_RESULTS.docx 
  605   Monday, February 24, 2014, 11:05 chad fisherSouth Hot-CellRepairTM2 Circuit D blank offThe blank off with the o-ring has been
removed, manipulator fixed, circuit D water
block sealinhg surfaces cleaned and blank
  
  766   Thursday, October 16, 2014, 15:40 Anders MjosConditioning StationMaintenance  Chiller unitNOTE: If there is a problem with
the chiller unit (ie Fault 1 or Fault 2),
a power cycle may reset the VFDs for the
 TCS_Cooling_System.pdf 
  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance will be performed Tuesday October
6th
Tuesday, October 06, 2015: Maintenance
  
  2218   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  Chiller maintenanceA contractor on site today for chiller
maintenance. CP2 and CP3 circuit is leaking
and shall not be used. CP1 can still be used.
  
  359   Thursday, May 23, 2013, 14:07 Bevan MossConditioning StationRepair  Chiller Unit Repaired ESC came today and "repaired"
the chiller. There was something wrong with
the VFD controller. The were able to get
  
  317   Tuesday, April 23, 2013, 16:11 Bevan MossConditioning StationMaintenanceTM3N/AChiller Fault 2 During Testing it was noticed that
Fault 2 was indicated and one of the compressors
would not run. Fault 2 does not indicate
  
  1958   Tuesday, August 06, 2019, 01:13 Carla BabcockConditioning StationRepairTM4Dummy HP SIS targetChecks on EE line leak fix and window line leak (not fixed)TM4 has developed 4 leaks so far:

    Line B - seems to be solved
with an indium gasket (some testing already
  
  1631   Thursday, September 28, 2017, 15:34 Anders MjosConditioning StationDevelopmentTM2 Changes to MP3 startup Due to problems with the regulating
valve WPV1, the VFD (Variable Frequency Drive)
for the pump has been programmed to do a
  
  1576   Wednesday, July 05, 2017, 11:18 Anders MjosConditioning StationMaintenanceTM4Ta#52Changed electrical configuration to cathode bias John Chow configured TCS to cathode
bias mode (IRH1538). The anode P/S is in
positive mode.
  
  71   Monday, January 16, 2012, 09:30 David WangITEMaintenance  Changed all old inducion coils for flow sensors in ITEI had changed all old induction coils for
flow sensors in ITE .I checked all ITE water
signals on control boards in electrical room.They
  
  1862   Thursday, January 24, 2019, 10:34 David WangITWMaintenance  Changed 24VDC plugs of TP solenoid valves in ITW3 damaged 24VDC plugs of TP solenoid valves
are replaced. Inspected other plugs. All
of them are in good condition now. 
  
  215   Wednesday, November 14, 2012, 11:04 David WangITERepairTM4 Change ITE dump water circiut flow wheelI changed ITE dump water circuit flow wheel
due to its poor performance. The new flow
wheel works fine. The signal on electrical
  
  2368   Wednesday, September 28, 2022, 12:58 Matthew GareauNorth Hot-CellRepair  Chad repaired the right operator side manipulatorOn 26/Sept/2022
Chad disassembled the right operator
side manipulator, and noticed that gears
 IMG_20220926_091024~2.jpgIMG_20220926_091040.jpgIMG_20220926_091047.jpgIMG_20220926_091153.jpg 
  899   Monday, April 27, 2015, 16:12 Keith C NgSouth Hot-CellDevelopmentTM2 Ceramic Standoffs in TM2 source tray steerer assemblyOn drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001".
 IMG_3106.JPG 
  1129   Tuesday, November 24, 2015, 13:54 chad fisherSouth Hot-CellRepair  Cell DeconDecon/removal of large solid waste was
performed on Wednesday November 18th."Hot"
activated items included containment box
  
  1136   Wednesday, November 25, 2015, 14:16 chad fisherSouth Hot-CellRepair  Cell DeconCell (table) was systematically cleaned
with a swiffer and resulting piles of contaminated
waste placed in pail with spent Ta target.
 20151125_100512.jpg20151125_101620.jpg 
  518   Tuesday, October 22, 2013, 16:52 Bevan MossConditioning StationRepair  Canbus base card for BIAS  The base card in the canbus BIAS
module was determined to be faulty. Dave
Morris removed a card VECC to repair the
  
  366   Monday, May 27, 2013, 16:01 Bevan MossConditioning StationRepair  CanBUS card During HV conditioning of TM4 with
Ta#40 there was a spark at ~43 kV that caused
the Bias card to "fry". Dave Morris
  