ID Date Author Category Type Moduledown Target/Number Subject
  2159   Friday, October 30, 2020, 09:02 Travis CaveSpent Target VaultStandard Operation Ta#48,51,54 SiC#35, and UC#25Repacking of the targets.

 Targets Ta#48,51,54 SiC#35, and UC#25 were repacked and placed in the mini vault. In the following order back to front. SiC#35 (240), Ta#54(241), UC#25(244), Ta#48(243), Ta#51(242).

Also during this repacking Ta#60 was also placed in the Spent Target Vault in spot 7B in pail# 239.

Attachment 1: Target_Index_2020-10-30.pdf
Target_Index_2020-10-30.pdf Target_Index_2020-10-30.pdf Target_Index_2020-10-30.pdf
  2161   Thursday, November 05, 2020, 10:23 David WangSpent Target VaultStandard Operation  TM2 old source tray and TM4 optic tray in vault tray#9.

TM2 old source tray and TM4 optic tray are stored together in vault tray#9. The fielding measurement at SHC post 0.5 meter distance:
 

March 1st 2019, maximum 14.6msv/hr, minimum 4.78 msv/hr

Nov 2nd 2020, max 7.11m sv/hr, min 2.5msv/hr.

  2163   Thursday, November 12, 2020, 10:02 Travis CaveSpent Target VaultStandard Operation UC#31Spent Target Move

 UC#31 has been moved from the south hot cell to the spent target vault. It is in spot 8B of the vault in pail # 224 and was 3.71mSv/hr upon removal from the south hot cell.

  2167   Thursday, November 19, 2020, 12:00 Adam NewsomeSpent Target VaultStandard Operation C#2Spent Target Move

C#2 has been moved from the south hot cell to the spent target vault. It is in spot 8A of the vault in pail # 235 and was 185 mSv/hr upon removal from the south hot cell.

The Target Index spreadsheet has been updated on DocuShare.

  2173   Monday, December 21, 2020, 11:22 Adam NewsomeCraneStandard Operation  Crane Shutdown for Power Outage

The Target Hall Crane has been shut down in preparation for the power outage tomorrow (Dec 22). Power will be restored on Dec 23.

 

Dec 23 update: power has been restored. The crane appears to be in working condition as there is no fault indicator on the PLC.

  2174   Thursday, December 24, 2020, 09:00 Matthew GareauNorth Hot-CellDevelopment   NHC USB connection

24/Noc/2020

USB was discovered to be in the reverse direction and will need to be change around to become operational

 

01/Dec/2020

USB was pulled from conduit

While attempting to re-pull the USB in the correction direction, the ethernet cable was damaged and need to be replaced,

(thanks to the Hubert's team for the wire help) 

It was decided that it was too problematic to re-pull the wires with all other wires in the way. Therefore all the wires were removed from the operator control panel, and pulled so that the USB, USB power cord, and ethernet could be re-pulled all together.

However, even once all the wires were re-pulled and reconnected it was discovered that the USB had become damaged, and was removed again.

 

23/Dec/2020

- A new conduit was added through to the NHC, for only the USB

- USB was fed through, reconnected, and tested

- Putty will need to be added around the conduit to ensure a good seal into NHC

  2180   Friday, January 22, 2021, 12:34 David WangITEStandard Operation  ITE HV test.

ITE annual HV test is done. No module in station. The bias power supply has been ramped up to 49KV on control page. We still have voltage limit issue on this PS at 48KV so it only can go to 47.7 KV on PS panel. No major spark during test.. The test result is same as last year test which was did in March 2020. 

  2182   Monday, January 25, 2021, 12:33 David WangITWStandard Operation  ITW bias HV test

Ramp up ITW bias to 57KV. no spark. 200uA leaking current at 57KV. The test is done without target module in station.   ITW water circuits are looped in pit.  EE , EL are switched off during the test. 

  2183   Wednesday, January 27, 2021, 14:30 David WangCoolingDevelopment  High active water system purging

High active water are purged to holding tank at B2  level. There should be around 48 gallons are purged out of system. No purging on dump circuits on both ITW/ ITE.

  2185   Wednesday, February 10, 2021, 11:34 David WangAssembly/Bench TestStandard Operation  Old resin can and 2A window RH clamp field measurement at silo.

Old resin can:  0.5 meter 360 degree rotation above silo area, 350u sv/hr.   On contact  3.0 to 3.5 msv/hr.  It was replaced during 2017 winter shut down, and stored in silo since then.

2a window RH clamp: 0.5 meter, 160 usv/hr.  On contact, hottest spot 3.5msv/hr, general,1.8 msv/hr. 

 Both of them were raise out of storage silo with TH crane. Pole monitor was used for field check.

  2186   Wednesday, February 10, 2021, 13:30 David WangSafe Module ParkingStandard Operation  TM2 and TM4 electrical check without targets.

 TM2 at SMP under vacuum. TM4 at silo.  Frank and I did the tests. Everything is fine on TM4 check.  On TM2,  all mega test at 500V are around 200K ohms which is so abnormal. We will move TM2 to TCS and  start investigation there.

Attachment 1: TM2_and_TM4_electrical_check_without_target.pdf
TM2_and_TM4_electrical_check_without_target.pdf TM2_and_TM4_electrical_check_without_target.pdf
  2187   Friday, February 12, 2021, 07:07 David WangITEMaintenance  ITW and ITE clean up.

Vacuum cleaned ITW and ITE station. 

  2188   Tuesday, February 16, 2021, 14:00 Adam NewsomeCraneDevelopment  Crane pendant upgrade

The crane pendant for the main hoist was upgraded to a FLEX EX2 style pendant by Canco Cranes. The installation work was performed by Matt at Canco, supervised by Tom Kauss, David Wang, and Adam Newsome. Installation work was performed in two phases since the initial installation did not provide adequate range and an antenna issue needed to be resolved (I2021-01-14-1, and I2021-02-16-1).

Items installed include:

  • New pendant
  • New antennae
  • New receiver box, mounted on main crane control panel in the crane control room

The old receiver control box will be kept for some time in case there is a need to revert to the previous system for some reason.

The new system was tested by David Wang - including using the pendant at the far end of the target hall where range was previously an issue. Everything is reported to be in working condition. Remote mode is functioning as expected.

 

 

Attachment 1: PXL_20210216_183711834.jpg
PXL_20210216_183711834.jpg
  2189   Thursday, February 18, 2021, 12:33 David WangITERepair  ITE:TP1S

ITE TP1S new pump is installed today. Reset pump life time on controller to 0 hr.

  2190   Thursday, February 18, 2021, 12:59 David WangAssembly/Bench TestMaintenance  TM3 source tray and old resin can storage in lower cyclotron basement

TM3 old source tray, old target hall high active water resin tank, and  old 2A window RH clamp are transferred from TH to cyclotron lower vault basement 10 and 10A location for storage. They are placed beside and in front of old TM1 and TM2 source tray boxes which stored there in 2018. 

  2191   Tuesday, February 23, 2021, 09:00 David WangAssembly/Bench TestMaintenance   target staion vacuum pumps inspection.

Edi and I inspected roughing pump ITM MP1, primary backup pump ITHMP1, and secondary backup pump ITHMP2. We checked oil level and color on all pumps.  Refilled lubricant to ITMMP1. ITHMP1 and MP2 oil level is fine. ITH MP1 oil color is darker than MP2. But, both them are ok still. Shielding block has been restored after the job.

  2192   Thursday, February 25, 2021, 10:09 Frank SongITERepair  Disconnect Entrance Module in ITE

 David and I disconnected entrance module in ITE by following the procedure # 190510. And, the yoke was installed and left on for remote handling later. 

  2193   Tuesday, March 02, 2021, 08:12 David WangConditioning StationStandard Operation   TCS leak check.

TCS leak check: TCS IG1S1.6 XE- 6 torr. LD  0.0XE-9atm.cc/sec.We used a long pole to spray helium to TCS vacuum seals on diagnostic box and vessel body. Lots helium have been sprayed around the check area.  no leak has been found.

  2194   Thursday, March 04, 2021, 11:20 David WangITWMaintenance  ITW water flow wheels and coils replacement.

ITW water flow wheels and coils are replaced. Wheels and coils on Oven, Tube, HS, EE, MSP, Febiad coil, containment box window, dump,dump plug, 2A window, and tank return circuits are replaced with new parts.

  2196   Thursday, March 04, 2021, 16:30 Isaac EarleNorth Hot-CellDevelopment  NHC gas delivery lines leak checked

 The North Hot Cell gas delivery lines (labeled 1, 2, and 3 on the hot and cold side panels) were leak checked today.  5psi helium gas was applied to each line in turn with the appropriate solenoid valve opened and a Staubli connector with plastic tubing and the leak check wand attached to the matching connector inside the cell.  The end of the wand was sealed using tape.  The Agilent G8601 leak detector was used on "sniffing" mode to check for escape of helium gas from all joints and connectors.  With the sniffing line attached the leak detector test port pressure was 3.9E-1 Torr and the baseline leak rate was 1.7E-6 Torr*L/s.  There was no response while testing all of the three lines.  For all three there was a leak detector response after disconnecting the Staubli fitting, which confirmed that the lines were properly charged with helium.