  RH-ISAC, Page 126 of 138  Not logged in ELOG logo
ID Date Author Category Type Moduledown Target/Number Subject
  2185   Wednesday, February 10, 2021, 11:34 David WangAssembly/Bench TestStandard Operation  Old resin can and 2A window RH clamp field measurement at silo.

Old resin can:  0.5 meter 360 degree rotation above silo area, 350u sv/hr.   On contact  3.0 to 3.5 msv/hr.  It was replaced during 2017 winter shut down, and stored in silo since then.

2a window RH clamp: 0.5 meter, 160 usv/hr.  On contact, hottest spot 3.5msv/hr, general,1.8 msv/hr. 

 Both of them were raise out of storage silo with TH crane. Pole monitor was used for field check.

  2186   Wednesday, February 10, 2021, 13:30 David WangSafe Module ParkingStandard Operation  TM2 and TM4 electrical check without targets.

 TM2 at SMP under vacuum. TM4 at silo.  Frank and I did the tests. Everything is fine on TM4 check.  On TM2,  all mega test at 500V are around 200K ohms which is so abnormal. We will move TM2 to TCS and  start investigation there.

  2187   Friday, February 12, 2021, 07:07 David WangITEMaintenance  ITW and ITE clean up.

Vacuum cleaned ITW and ITE station. 

  2188   Tuesday, February 16, 2021, 14:00 Adam NewsomeCraneDevelopment  Crane pendant upgrade

The crane pendant for the main hoist was upgraded to a FLEX EX2 style pendant by Canco Cranes. The installation work was performed by Matt at Canco, supervised by Tom Kauss, David Wang, and Adam Newsome. Installation work was performed in two phases since the initial installation did not provide adequate range and an antenna issue needed to be resolved (I2021-01-14-1, and I2021-02-16-1).

Items installed include:

  • New pendant
  • New antennae
  • New receiver box, mounted on main crane control panel in the crane control room

The old receiver control box will be kept for some time in case there is a need to revert to the previous system for some reason.

The new system was tested by David Wang - including using the pendant at the far end of the target hall where range was previously an issue. Everything is reported to be in working condition. Remote mode is functioning as expected.

 

 

  2189   Thursday, February 18, 2021, 12:33 David WangITERepair  ITE:TP1S

ITE TP1S new pump is installed today. Reset pump life time on controller to 0 hr.

  2190   Thursday, February 18, 2021, 12:59 David WangAssembly/Bench TestMaintenance  TM3 source tray and old resin can storage in lower cyclotron basement

TM3 old source tray, old target hall high active water resin tank, and  old 2A window RH clamp are transferred from TH to cyclotron lower vault basement 10 and 10A location for storage. They are placed beside and in front of old TM1 and TM2 source tray boxes which stored there in 2018. 

  2191   Tuesday, February 23, 2021, 09:00 David WangAssembly/Bench TestMaintenance   target staion vacuum pumps inspection.

Edi and I inspected roughing pump ITM MP1, primary backup pump ITHMP1, and secondary backup pump ITHMP2. We checked oil level and color on all pumps.  Refilled lubricant to ITMMP1. ITHMP1 and MP2 oil level is fine. ITH MP1 oil color is darker than MP2. But, both them are ok still. Shielding block has been restored after the job.

  2192   Thursday, February 25, 2021, 10:09 Frank SongITERepair  Disconnect Entrance Module in ITE

 David and I disconnected entrance module in ITE by following the procedure # 190510. And, the yoke was installed and left on for remote handling later. 

  2193   Tuesday, March 02, 2021, 08:12 David WangConditioning StationStandard Operation   TCS leak check.

TCS leak check: TCS IG1S1.6 XE- 6 torr. LD  0.0XE-9atm.cc/sec.We used a long pole to spray helium to TCS vacuum seals on diagnostic box and vessel body. Lots helium have been sprayed around the check area.  no leak has been found.

  2194   Thursday, March 04, 2021, 11:20 David WangITWMaintenance  ITW water flow wheels and coils replacement.

ITW water flow wheels and coils are replaced. Wheels and coils on Oven, Tube, HS, EE, MSP, Febiad coil, containment box window, dump,dump plug, 2A window, and tank return circuits are replaced with new parts.

  2196   Thursday, March 04, 2021, 16:30 Isaac EarleNorth Hot-CellDevelopment  NHC gas delivery lines leak checked

 The North Hot Cell gas delivery lines (labeled 1, 2, and 3 on the hot and cold side panels) were leak checked today.  5psi helium gas was applied to each line in turn with the appropriate solenoid valve opened and a Staubli connector with plastic tubing and the leak check wand attached to the matching connector inside the cell.  The end of the wand was sealed using tape.  The Agilent G8601 leak detector was used on "sniffing" mode to check for escape of helium gas from all joints and connectors.  With the sniffing line attached the leak detector test port pressure was 3.9E-1 Torr and the baseline leak rate was 1.7E-6 Torr*L/s.  There was no response while testing all of the three lines.  For all three there was a leak detector response after disconnecting the Staubli fitting, which confirmed that the lines were properly charged with helium.

  2198   Thursday, March 11, 2021, 11:42 Frank SongITEMaintenance  ITE water flow wheels and coils replacement.

 ITE water flow wheels and coils are replaced. Wheels and coils on Oven, Tube, HS, EE, MSP, Febiad coil, containment box window, dump, dump plug, 2A window, and tank return circuits are replaced with new parts.

  2199   Friday, March 12, 2021, 11:36 Travis CaveSouth Hot-CellMaintenance East Entrance ModuleEntrance module move

 The East Entrance Module has been moved from the East Target Station to the South Hot Cell.

  2200   Monday, March 15, 2021, 13:01 Isaac EarleCraneDevelopment  Plate & pin lift assembly load testing (ITA6550)

In mid-2020 design analysis was completed on the steel plate & pin assemblies (ITA6550) used to connect the ISAC target hall crane hook block to the module lifting yoke assembly ITA0494.  The released design note is Document-184431.  

In November 2020 fabrication was completed on two full plate & pin assemblies (photos attached below).  As per the relevant ASME standards (identified in the design note), each assembly has been identified with serial numbers (#1 and #2).  Material test reports for the steel plate and round bar material used for fabrication are attached in PDF format.  For both materials the tested tensile yield strength (from the MTR) exceeds the value used in design calculations (from Document-184431):  117ksi vs 100ksi for the plate material;  138si vs 103ksi for the round bar material.

On February 8, 2021 both plate and pin assemblies were load tested by David Wang and Frank Song.  The total load applied to each was 31,400 lbs (as per the ISAC target hall crane load cell) which exceeds the 125% of rated capacity (31,250 lbs) required for the test.  The lifts were conducted successfully and no deformations or other damage to the assemblies were observed.  Photos of the load test are also attached.

Both plate & pin assemblies are now certified for use up to their rated capacity.  As specified on drawing ITA6550 and in Document-184431, a monthly visual inspection must be performed to check for structural deformation, cracks, excessive wear, and loose or missing fasteners.  In addition, an annual inspection must be performed to check for structural deformation, cracks, excessive wear, loose or missing fasteners, and missing or illegible markings or safety labels.  A written record of the annual inspection must be documented and kept readily available.

 

  2201   Wednesday, March 17, 2021, 09:10 Travis CaveITEStandard Operation  Entrance module move

 The east entrance module is now back at the east target station.

  2202   Wednesday, March 17, 2021, 11:43 Frank SongITERepair  Re-connect Entrance Module in ITE

 David and I re-connect Entrance module at ITE after the monitor been replaced at SHC. 

  2204   Thursday, March 25, 2021, 08:55 Anders MjosConditioning StationMaintenance  Filters inspected and cleaned on water circuit

By Curtis. See Work Permit I2021-03-24-1 for details.

  2205   Thursday, March 25, 2021, 10:38 David WangSpent Target VaultStandard Operation C#1Remove pail 237 spent target C#1 from storage vault to mini storage.

Pail 237 only has 200u sv/hr field at 0.5 meter. On contact measurement: 0.9 to 1.6 m sv/hr.and less than 80 count contamination outside the pail.   It is moved to mini storage. We will transfer this pail to cyclotron vault and store it there later.

  2206   Friday, March 26, 2021, 12:22 Adam NewsomeCraneDevelopment  Aux Hoist Pendant Upgrade

The crane pendant for the auxiliary hoist was upgraded to a FLEX EX2 style pendant by Canco Cranes. The installation work was performed by Canco, supervised by Tom Kauss and David Wang. Installation work was performed in one day (I2021-03-26-1).

Items installed include: new pendant (2 motion, 2 speed)

The existing antenna and receiver box located in the Target Hall were used.

The new system was tested by David Wang. Everything is reported to be in working condition.

  2207   Monday, April 12, 2021, 13:45 Anders MjosCoolingMaintenance  New T installed for instrumentation loop on HALCW system

Adrian and co installed a new T to be able to add an instrument loop for O2 and pH monitoring on the low conductivity water systtem (photo). See WP I2021-04-09-4