ID Date Author Category Type Module Target/Number Subject Text Attachments
  334   Thursday, May 09, 2013, 10:13 chad fisherSouth Hot-CellDevelopment  Mock-up ProgressThe source tray for the mock-up has been
setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the
 IMG_1056[1].JPGIMG_1057[1].JPGIMG_1058[1].JPG 
  333   Wednesday, May 08, 2013, 13:48 chad fisherSouth Hot-CellRepairTM3 IMG wiring checkChecks of the wiring for the IMG are complete
and have passed.
  
  332   Wednesday, May 08, 2013, 10:12 chad fisherSouth Hot-CellRepairTM3 TM3 9 pin wiring removalThe 9 pin wiring has successfully been
removed from TM3.
 IMG_1055[1].JPG 
  331   Tuesday, May 07, 2013, 12:07 David WangITWStandard OperationTM1 I moved 5 shielding blocks from ITE to ITW.Water interlock check  on ITW is done.
All water signals are strong on EL panel. 
ITW is configured to take proton beam.
  
  330   Monday, May 06, 2013, 15:45 Bevan MossConditioning StationRepairTM3 55 pin connector removedTravis and I removed the 55 pin connector
from the service cap today. The feed through
was left in place as a new design for the
 20130506_55_pin_conector_removal_IMG_3530.JPG20130506_55_pin_conector_removal_IMG_3525.JPG20130506_55_pin_conector_removal_IMG_3532.JPG20130506_55_pin_conector_removal_IMG_3535.JPG 
  329   Friday, May 03, 2013, 09:53 chad fisherSouth Hot-CellRepairTM3 9 pin connector wiringWith the aid of nic new manipulator snap
fingers made by Maico the peek cable ties
restraining the 9 pin connector wiring to
 IMG_1047[1].JPGIMG_1048[1].JPGIMG_1050[1].JPG 
  328   Thursday, May 02, 2013, 10:09 chad fisherSouth Hot-CellRepairTM3 Service tray water block leak checkDavid and I preformed a helium leak check
on the service tray waterblocks and verify
that no damage had been done during jig installation.
  
  327   Tuesday, April 30, 2013, 07:51 chad fisherSouth Hot-CellRepairTM3 Coil line flow checkDavid and I checked circuits p and q (the
water cooled coil ciruit) for flow this morning
as, with the source tray still in the module,
  
  326   Tuesday, April 30, 2013, 07:47 chad fisherSouth Hot-CellRepairTM3 TM3 Source Tray RemovalThe source tray has sucessfully been removed
from TM3.
I will put a report in the TM3 rev
 IMG_1043[1].JPG 
  325   Monday, April 29, 2013, 15:58 Bevan MossSouth Hot-CellRepairTM3 Source Tray RemovalChad removed the source tray from TM3  today,
see attached picture (video was also taken).
There was some interference between the window
 20130429_TM3_SOURCE_TRAY_REMOVAL_IMG_0620.JPG 
  324   Friday, April 26, 2013, 14:31 chad fisherSouth Hot-CellRepairTM3 TM3 refurb E.O.D.Service tray side of the waterblock jig
is installed and all locking tabs enagaed
save the heat shield circuit. Locking tab
 IMG_1039.JPG 
  323   Friday, April 26, 2013, 11:20 chad fisherSouth Hot-CellRepairTM3 Water Block Jig (back half)The back half of the water block jig (services
tray side) has been sucessfully located onto
the module.
  
  322   Wednesday, April 24, 2013, 14:09 chad fisherSouth Hot-CellRepairTM3 TM3 Refurbishment E.O.D. Optics tray has been removed from module.
Waterblock jig installation has commenced.
Of note, jig installation on TM3 has proven
  
  321   Wednesday, April 24, 2013, 11:48 chad fisherSouth Hot-CellRepairTM3 TM3 Source Tray RemovalWork on TM3 source tray removal started
at 10:40 am today.
The containment box has been removed,
  
  320   Wednesday, April 24, 2013, 10:36 maicodallavalleSpent Target VaultMaintenance  F-308The F-308's have been serviced and are
ready to be filled. All inspection records
are stored  in docushare.
  
  319   Wednesday, April 24, 2013, 10:14 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 has been moved from the conditioning
station to the south hot cell, move went
well.
  
  318   Wednesday, April 24, 2013, 09:00 Bevan MossConditioning StationDevelopment  New user testing Controls has created a new user group
that can operate the conditioning station
but cannot use any of the bypasses or forces.
  
  317   Tuesday, April 23, 2013, 16:11 Bevan MossConditioning StationMaintenanceTM3N/AChiller Fault 2 During Testing it was noticed that
Fault 2 was indicated and one of the compressors
would not run. Fault 2 does not indicate
  
  316   Tuesday, April 23, 2013, 15:59 Bevan MossConditioning StationStandard OperationTM3N/ASystems off Both the Cooling Package and
Vacuum have been turned off in preparation
for the module move tomorrow
  
  315   Tuesday, April 23, 2013, 15:52 Bevan MossConditioning StationStandard OperationTM3N/AFurther HV Testing Further HV testing was completed
today from ~2:00 until 3:00. The resistivity
of the water was 11.7 - 12.7 Mohm. The EE
 TM3_BIAS_EE_CB_23042013.xlsxTM3_BIA_EE_CD_23042013_RGA_files.zip 