ID Date Author Category Type Moduledown Target/Number Subject
  1669   Thursday, December 21, 2017, 15:11 Anders MjosConditioning StationMaintenance  Powered down devices

Powered down mechanical pumps in ISAC-I Experimental hall, vacuum gauge and turbo pump controllers in ISAC-I B2 North Hot Cell service area

  1671   Tuesday, January 02, 2018, 10:46 David WangITE/ITW CoolingStandard Operation  Start High active water system.

High active water system  was  checked before restart. A small water leak on resin can supply valve was found. It is fixed. MP1 and MP2 were started and checked separately. System pressure and flow rate are normal.MP1 is in operation now. 

  1673   Tuesday, January 02, 2018, 14:47 Anders MjosConditioning StationStandard Operation  Pumping on secondary vacuum

Tuesday, January 02, 2018, 14:45: TP1S started

  1674   Tuesday, January 02, 2018, 15:17 Anders MjosConditioning StationMaintenance  Tested chiller

Tested all 3 compressors and MP2

  1675   Thursday, January 04, 2018, 13:28 Anders MjosConditioning StationMaintenance  Troubleshooting IG1S

TCS:IG1S is reporting vacuum levels that seem to be too low (1E-10 to 1E-8 Torr). The gauge was connected to the controller for IG1, which showed the same value. A degas was performed for ~5 min.

  1676   Tuesday, January 16, 2018, 06:50 David WangITE/ITW CoolingStandard Operation  Field measurement on old resin tank in silo

The old resin tank has been stored in silo since last year March.  Without crane the tank up, We use the pole monitor measured the field around the bottom of the tank in silo. The average contact field on the bottom is about 4.0msv/hr. @0.5meter , the field is about  900usv/hr. It is still too hot to remove it.

  1678   Wednesday, January 17, 2018, 06:51 David WangConditioning StationStandard Operation  Stop TCS vacuum pumps

I stopped TCS vacuum pumps for coming TM3 move.

  1684   Wednesday, January 31, 2018, 10:32 David WangCraneStandard Operation  Target Hall crane annual inspection.

Gordon crane technician Tom finished annual TH crane inspection today. Everything is normal. The main hoist brake gaps are checked on both side. They are good still.

  1689   Wednesday, February 28, 2018, 14:47 David WangITEStandard Operation  leak check ITE primary and secondary vacuum vessel.

2018-02-27: Anders and I finished leak check on ITE primary and second vacuum vessel seals. LD connected to ITE BV2 valves between. LD, Base Leak rate 1.2 xE-9atm.cc/sec, base pressure 0.0XE-4torr. There is a leak has been found on TM4 service cap KF25 blank off. The o-ring on the blank off will be changed later. It is an easy fix . Other seals are good. The big T tank seal on secondary vessel is leak checked as well. It is still fine.  Helium pressure on TM4 water lines will be fulfilled at TCS to save dose.

2018-02-28 Leak checked ITW today, LD connected to ITW BV2 valves between LD base LR0.0XE-9 atm.cc/sec. base pressure 0.0Xe-4torr. There is leak has been found on exit module 1 service cap  on  topcover plate   o-ring. The leak is located on the south side of east edge on exit 1. This is the side module 2 is close beside. The leak rate is up to middle of E-8atm.cc/sec  range with 1-2 second helium spray. The leak and leak position are double checked and confirmed.  To completely fix this leak, the o-ring for top cover plate need to be replaced on service cap.It will be a major shut down job.  The  leak is close to ITW TP3 so it is less affect on beam line elevation vacuum.  Vacuum group experts will be consulted to see if we could leave it to next year shutdown.  Other seals are good including big T-tank seal on secondary vessel. TM2 source tray will be replaced this yea rso no helium pressure test on water lines is needed at this moment.

  1690   Monday, March 05, 2018, 13:47 Travis CaveSpent Target VaultRepair ManySpent Target Assay

 The spent target assay was aborted today after the first target was finished due to the very old computer that controls the camera and the vault door effectively died. The vault door had to be closed using the emergency door closing winch which worked so it passed that test.

  1692   Wednesday, March 07, 2018, 10:18 David WangITWStandard Operation  Oil leak on target station vacuum primary back pump.

I can not see oil in sight window of the primary pump during visual inspection. The aluminum tray underneath the pump is filled with oil. The performance on this pump start to drop by watching ITH CG4 reading. A fault report with suggestion is issued to vacuum group.  Everything on secondary pump looks fine.

  1693   Wednesday, March 07, 2018, 10:36 David WangITE/ITW CoolingDevelopment  HALCW resin can flow meter replacment

HALCW resin can flow meter replacement is done. Less that 100 mL water was drained to a small tray during the job. RPG checked the water. Less than 20 counts. Water are dumped the high active sump.   The HALCW MP1 is started. No leak on new gauges and fittings. Old gauge is labeled , bagged, and stored in TH.

  1694   Thursday, March 08, 2018, 14:10 David WangITWMaintenance  Two small water leak has been found in ITW.

Two small water leaks have been found on ITW High active water system. One is from an unused 1/4" copper valve stem. another is on supply 1.5" supply line valve body top sealing. Both of them are seeping water from seal. 1/4" copper valve will be replaced with a new one. 1.5" supply line valve will be replaced by an old valve with all new seals. I have all spare parts in hand.  At present, water supply to ITW are stooped to reduce leak rate. Two aluminum flat tray are put underneath leak valves to hold small amount leak water. Both leak will be fixed in April  mostly.

  1695   Friday, March 23, 2018, 09:34 Travis CaveSpent Target VaultStandard Operation ManySpent Target Assay

 All targets in the ISAC Spent Target Vault have been either assayed and had field measurement done on them or just measurement if to hot to assay.

  1696   Thursday, April 05, 2018, 11:29 David WangITWMaintenance  ITH MP1 replacement

ITH MP1 is replaced today with a new style pump.The new pump is 0.75 inch higher than  old pump on inlet and exhaust so a new solid inlet adapter  (KF50-25) has to been used. For future secondary pump ITH MP1S replacement, we need a new adapter 0.75 inches shorter as well.   The new pumps is started . Everything works fine. Old pumps is drained , bagged, and stored in TH B2 level. All radioactive garbage produced during the job are bagged , tagged, and stored in TH as well.

  1697   Monday, April 09, 2018, 06:36 David WangITWStandard Operation  ITW Turbo -pumps switch off

I asked MCR to switch off ITW TP3,4 TP1s,2s this morning.

  1700   Monday, April 16, 2018, 14:51 Travis CaveSpent Target VaultStandard Operation Ta#55Spent Target Move

 Ta#55 has been moved from the south hot cell to the spent target vault. It was 30.4mSv/hr upon removal from the hotcell, placed in pail #161 and put in spot 7A of the vault.

  1701   Tuesday, April 17, 2018, 11:05 David WangITWRepair  Disconnect ITW entrance module

ITW entrance module has been disconnected.  All connections are labelled before or during disconnection. The 24VDC electrical plug on ITW TP1S is broken . It will be replaced with a new plug. The lift yoke is installed onto module without difficulty.   

  1702   Thursday, April 19, 2018, 10:27 Travis CaveITWMaintenance  Entrance module move

 The west entrance module has been moved from the west target station to the silo.

  1703   Friday, April 20, 2018, 15:33 Keith C NgITWRepair  ITW beam tube repair job

2A2 window has been removed from ITW and beamlines has removed the beamtube from the penetration. The penetration has been sealed with plastic sheeting and duct tape to maintain the ventilation depression between the 2A tunnel and the Target Pit.

Window is currently stored in a lead flask in the target hall. Window fields are 26 mSv/h OC, 1.2 mSv/h at .5m. There is a 10 uSv/h field outside the flask with the window inside it.

Clamp is currently sitting bagged in ITW Station Pit, it is quite corroded.

Tank flange was video inspected but still needs to be cleaned, currently there is a slip on dust cover over the flange to protect it.

Work will resume after the nuclear ventilation comissioning is completed.

 

 

 