ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1582   Wednesday, July 12, 2017, 11:05 Anders MjosConditioning StationMaintenance  Testing of new high voltage cableThe target hall has been locked-out as
per Document-70039.
Forced IG1, IG1S and IG2 to switch
 2017-07-12_HV_Cable_Test.xlsx 
  1586   Tuesday, July 18, 2017, 15:04 Travis CaveCraneMaintenance  Failure of the ISAC TH Crane Rotate. Earlier in the day it was noted that
the rotate function of the crane had creased
operation. After David has finished the block
  
  1592   Wednesday, August 02, 2017, 15:41 Keith C NgAssembly/Bench TestDevelopment  spare source tray buildAfter re zeroing alignment telescope to
master jig and adjusted parts into place:
 
 20170802_sourcetray_RHB_8264.JPG20170802_sourcetray_RHB_8266.JPG 
  1593   Thursday, August 03, 2017, 15:02 Travis CaveSpent Target VaultStandard Operation SiC#36Spent Target Move The spent SiC#36 has been moved from
the south hot cell to the spent target vault.
 Vault_Storage_August_3_2017.pdf 
  1596   Wednesday, August 09, 2017, 16:39 Isaac EarleNorth Hot-CellDevelopment  NHC drain line into sump identified The NHC drain line was tested by
pouring approximately 10 gallons of water
through the drain grate at the base of the
  
  1599   Tuesday, August 15, 2017, 12:10 Isaac EarleNorth Hot-CellDevelopment  ISAC Active Sump low water level measuredThe ISAC active sump in the Active Service
Room (#002 on B2 level) was pumped out yesterday
using the standard procedure (Section 5.5.2
  
  1600   Thursday, August 17, 2017, 14:38 Isaac EarleNorth Hot-CellDevelopment  4/6 NHC roof blocks installed Roof blocks IRH1641, IRH1642, IRH1643,
and IRH1644 have been fully assembled, labeled,
and installed as per drawing IRH1652.  Fabrication
 7x 
  1601   Friday, August 25, 2017, 16:33 Anders MjosConditioning StationRepair  Testing HV after cooling line repair The BIAS voltage was brought up to
70 kV today and held there for 1h. No sparking
observed.
 2017-08-25_HV_Water_Line_Test.xlsx 
  1608   Wednesday, August 30, 2017, 11:37 Travis CaveSpent Target VaultStandard Operation Ta#52Spent Target moveThe spent Ta#52 target has been moved from
the south hot cell to the spent target vault.
See attached PDF for details.
 Vault_Storage_August_30_2017.pdf 
  1617   Tuesday, September 19, 2017, 10:40 chad fisherSouth Hot-CellMaintenance  South East Manipulator MaintenenceEntered hot cell to preform replacement
of slave tong cable. Existing cable shows
no signs of wear so it has been re-installed.
  
  1630   Thursday, September 28, 2017, 11:59 Travis CaveSpent Target VaultStandard Operation Ta#53Spent Target moveThe spent Ta#53 has been moved to the spent
target vault. See attached file for details.
 Vault_Storage_September_28_2017.pdf 
  1634   Thursday, October 05, 2017, 11:04 Anders MjosITWMaintenance  Installation of new valve for module move ventilationDavid installed the new ball valve and
connections for the SAS project module move
ventilation. SASP0482. Drawing reference
  
  1635   Friday, October 06, 2017, 11:12 Isaac EarleNorth Hot-CellDevelopment  NHC module port shield block and TCS vessel shield block installed The NHC module port shield block
(IRH1645) and the TCS vessel shield block
(IRH1646) were installed yesterday in the
 IMG_0472.jpgIMG_0476.jpgIMG_0479.jpgIMG_0481.jpgIMG_0486.jpg 
  1636   Friday, October 06, 2017, 11:21 Isaac EarleNorth Hot-CellDevelopment  ISAC-1 active sump drain pipe modifiedThe 4" PVC drain line in the ISAC-1
active sump was modified so that the drain
pipe terminates below the low level water
 IMG_0513.jpgIMG_0516.jpgIMG_0517.jpg 
  1637   Friday, October 06, 2017, 13:25 Anders MjosConditioning StationRepair  HV Test HV was brought up to 70 kV for 1
h without sparks to test the new water installation.
 2017-10-06_HV_Water_Line_Test.xlsx 
  1638   Tuesday, October 10, 2017, 10:38 David WangITWStandard Operation   5 shielding blocks have been transferred from ITE to ITW .ITW is configured to take proton beam.   
  1639   Tuesday, October 10, 2017, 10:45 David WangConditioning StationRepair  Re-route TCS water lines.TCS  cooling polyurethane lines have
been re-routed to solve to HV sparking issue
on old configuration between lines and bais
 8x 
  1640   Wednesday, October 11, 2017, 15:50 Keith C NgAssembly/Bench TestStandard Operation  spare source tray build alignment 
 
Spare
  
  1641   Thursday, October 12, 2017, 08:48 Travis CaveSpent Target VaultStandard Operation  Field measurements of the old source trays Field measurements were taken of
the old source trays. The old TM#2 source
tray had a minimum field value of 0.50 mSv/hr
  
  1642   Friday, October 13, 2017, 11:14 Keith C NgAssembly/Bench TestStandard Operation  source tray alignment/buildSource tray is complete for brazing, gas
line bracket is currently missing but can
be made in parallel with tube bending operations.
 20171013_sourcetray_P1030815.JPG20171013_sourcetray_P1030816.JPG20171013_sourcetray_P1030817.JPG20171013_sourcetray_P1030818.JPG 