  1443   Thursday, March 02, 2017, 15:02 Isaac EarleNorth Hot-CellDevelopment  NHC roughing filter installed

 The roughing filter assembly (RFM0001D) has been installed at the ventilation exhaust hole on the NHC partition wall.  The filter used is Model # 332-528-002 supplied by BGE Service & Supply Ltd (see PO # TR123998).  Installation and removal of the filter using the manipulators will be tested after they have been installed.

 

IMG_8014.JPG

 

IMG_8018.JPG

 

IMG_8019.JPG

  1444   Monday, March 06, 2017, 08:01 David WangCoolingRepair  HALCW resin tank replacement.

HALCW resin tank has been replaced. The old tank is stored in middle-west silo now. The field on old resin tank bottom is about 3.5 msv/ hr(on contact). By shielding it into silo and putting two lead blankets on the top cover of the silo,The general field 1 feet above this silo is 25usv/hr. And, The field around the silo area are less affected. This old tank will stay there as long as possible.  For the new resin tank during preparation, It was found that on return line side, the 1.25" pipe thread plug with return line tube  was very difficult to be installed onto the female thread adapter which is welded onto to tank body. It was jammed in half way of threading onto tank at manufacturer. This plug was removed out first and inspected. The first and second male threads were galled.  Maico repaired the thread on a lathe. The female thread on the tank was tapped. A tight spot was found during the tap. After that, the return line plug could be installed onto the tank properly.  The new tank was installed into the vessel and connected back to HALCW system. Water are refilled into new tank. During refill air were trapped into the system. This caused  pump restarting problem. By Several times of starting up the pump, stopping the pump and venting,  Most air were breathed out of  system. Finally,The system was restarted by supply water to ITW( without module) only. ITE and resin can circuits were brought back to system after that without problem.

 Before removing the old tank, We drained water out of old tank to decay tank. Since the resin tank is largely filled with  resin, and water are soaked into resin, we only can drain out less than 10 liters water out of tank. Also, The drain caused some part of return line on pumps have to been drained. This is the main reason air was trapped in system during the new resin tank water refilling. For the future replacement, we should not drain water in old tank. It does not worth to do it. 

Attach TH HALCW resin tank replacement procedure here.

2022-02-17 reload replacement procedure and draining schematic.

Attachment 1: new_resin_tank_installation_004.JPG
new_resin_tank_installation_004.JPG
Attachment 2: new_resin_tank_installation_005.JPG
new_resin_tank_installation_005.JPG
Attachment 3: new_resin_tank_installation_006.JPG
new_resin_tank_installation_006.JPG
Attachment 4: new_resin_tank_installation_008.JPG
new_resin_tank_installation_008.JPG
Attachment 5: new_resin_tank_installation_010.JPG
new_resin_tank_installation_010.JPG
Attachment 6: new_resin_tank_installation_012.JPG
new_resin_tank_installation_012.JPG
Attachment 7: new_resin_tank_installation_013.JPG
new_resin_tank_installation_013.JPG
Attachment 8: HALCW_Resin_Tank_Replacement_Procedure..docx
Attachment 9: HALCW_Resin_Tank_Replacement_Procedure..pdf
HALCW_Resin_Tank_Replacement_Procedure..pdf HALCW_Resin_Tank_Replacement_Procedure..pdf HALCW_Resin_Tank_Replacement_Procedure..pdf
Attachment 10: HALCW_resin_can_replacement__procedure..pdf
HALCW_resin_can_replacement__procedure..pdf
Attachment 11: resin_tank_draining.pdf
resin_tank_draining.pdf
  1445   Tuesday, March 07, 2017, 09:25 David WangITWRepair  ITW HALCW 2" return line ball valve seals replacement.

Leaking seals on ITW HALCW 2" return line ball valve have been replaced. 8 liter waters are drained out for this job. Water are drained into a thick plastic bag.  The bag is tie strapped , labeled, and put into a yellow garbage bin in MAA. Water sample is given to RPG. After analyzing, RPG will give instruction on how to deal with it. Since we just refilled NALCW to system before this job, the active level on sample is very low. We may dump them into active sump.  After seals change, The system is refilled . I started pump and set everything back to normal configuration. NO leak has been found on new seals. The HALCW system is operating good so far.

  1446   Tuesday, March 07, 2017, 14:41 David WangITEMaintenance  ITE dump plug water circuit is closed for ITE IG1S small surge.

It is closed @ 2:35PM by closing supply side valve first , the return side valve of ITE dump plug .

Opened ITE dump plug circuit valves @4:28PM. ITE IG1S still at 1XE-6. No change before and after of circuit closing and reopeneing.

  1448   Friday, March 10, 2017, 09:19 chad fisherSouth Hot-CellStandard Operation  South Hot Cell Field Measurements

The fields in the hot cell have been measured by means of a pole monitor through the tool port. Field was measured to be 25 uSv/h.

  1449   Tuesday, March 14, 2017, 07:34 chad fisherSouth Hot-CellMaintenance  Hot Cell Fields

I have re-measured the fields in the hot cell. Fields at shield door Al cover are 101 uSv\h, in cell at the east manipulator are 245 uSv\h, and the largest field is 1.84 mSv\h...this appears to be the high current fasteners removed from the last target.

  1450   Tuesday, March 14, 2017, 11:46 chad fisherSouth Hot-CellMaintenance  'Z' motion cable dry run

Did a dry run with the latest procedure with Dan Mcdonald. Elapsed time was approximately 30 min.

  1451   Wednesday, March 15, 2017, 07:45 chad fisherSouth Hot-CellMaintenance  South Hot Cell Fields

I have moved the suspected "hot" items in the hot cell and placed them under some lead bricks. I have re-measured the fields and it has been reducded to 90 uSv\h at the manipulator repair area and 110 uSv/h at the previous 1.82 mSv\h area.

  1453   Thursday, March 16, 2017, 12:24 chad fisherSouth Hot-CellMaintenance  West 'Z' motion cable replacement

The west 'Z' motion cable on the east manipulator has successfully been replaced. The job took slightly less than an hour (including inspection of the scissor table hoses) and I received 0.075mSv. Scissor table hoses appear to be fine and also didn't "shed" or flake at all when checked by hand.

  1454   Tuesday, March 21, 2017, 10:05 Travis CaveSpent Target VaultStandard Operation  Spent target assay.

All target in the ISAC spent target vault have been either assayed or had their fields measured or both.

Attachment 1: Vault_Storage_March_20_2017.pdf
Vault_Storage_March_20_2017.pdf Vault_Storage_March_20_2017.pdf Vault_Storage_March_20_2017.pdf Vault_Storage_March_20_2017.pdf
  1459   Thursday, March 23, 2017, 11:22 Grant MinorCraneMaintenance  Target Hall crane 20 ton hoist noise / smell - inspection by Gordon Crane & Hoist

Strange noise and a burning brake type smell was observed yesterday by David and Anders when running the main 20 ton hoist locally.  A service call was arranged today with Gordon Crane.  No major issues were found.  A more detailed summary is in the attached e-mail correspondence.  Gordon Crane will issue a formal report, but they recommend replacing both sets of brake disks and brake calipers. - Grant

Attachment 1: Target_Hall_crane_main_hoist_problem_-_A_Mjos_-_22_Mar_2017.pdf
Target_Hall_crane_main_hoist_problem_-_A_Mjos_-_22_Mar_2017.pdf
Attachment 2: Update_-_Target_Hall_20T_Hoist_Inspection_-_G_Minor_-_23_Mar_2017.pdf
Update_-_Target_Hall_20T_Hoist_Inspection_-_G_Minor_-_23_Mar_2017.pdf Update_-_Target_Hall_20T_Hoist_Inspection_-_G_Minor_-_23_Mar_2017.pdf Update_-_Target_Hall_20T_Hoist_Inspection_-_G_Minor_-_23_Mar_2017.pdf
Attachment 3: Re__Update__Target_Hall_20T_Hoist_Inspection_-_David_Wang_-_23_mar_2017.pdf
Re__Update__Target_Hall_20T_Hoist_Inspection_-_David_Wang_-_23_mar_2017.pdf Re__Update__Target_Hall_20T_Hoist_Inspection_-_David_Wang_-_23_mar_2017.pdf Re__Update__Target_Hall_20T_Hoist_Inspection_-_David_Wang_-_23_mar_2017.pdf Re__Update__Target_Hall_20T_Hoist_Inspection_-_David_Wang_-_23_mar_2017.pdf
  1461   Friday, March 24, 2017, 11:12 Keith C NgSpent Target VaultStandard Operation  2A window transfer

Transfered the 2A window from the ISAC Storage Vault to the Cyclotron Vault Tunnel Storage area. RPG storage form attached.

Attachment 1: 2017mar24_vault_tunnel_storage_form(1).pdf
2017mar24_vault_tunnel_storage_form(1).pdf
  1462   Friday, March 24, 2017, 11:19 Keith C NgSpent Target VaultStandard Operation 2A3 windowWindow now in vault

Travis Cave wrote:

The 2A3 window now has a lid, and lift yolk on it and it has been installed in the spent target vault in spot 2A. The lid is a normal unmodified and has no sealant on it.

The pail containing window was transferred from the Storage Vault to the Cyclotron Vault Tunnel Storage 2017 Mar 24. It was placed in a brick bunker along the north wall and marked with item #1434. RPG storage form is attached.

Highest field measured at 0.5 m was 3000 uSv/h with an estimate of 4000 uSv/h on contact with the pail. Pail exterior was not contaminated. See attached storage form for details.

 

Attachment 1: 2017mar24_vault_tunnel_storage_form(1).pdf
2017mar24_vault_tunnel_storage_form(1).pdf
  1463   Friday, March 24, 2017, 13:21 Travis CaveSpent Target VaultStandard Operation 2A window2A window has been removed from the vault.

2A window has been removed from the vault and moved over the cyclotron vault tunnels.  Attached is the updated storage vault list.

Attachment 1: Vault_Storage_March_24_2017.pdf
Vault_Storage_March_24_2017.pdf Vault_Storage_March_24_2017.pdf Vault_Storage_March_24_2017.pdf Vault_Storage_March_24_2017.pdf
  1464   Monday, March 27, 2017, 06:33 David WangITEStandard Operation  ITE clean up

ITE clean up is done.  HV cage inside is wiped.

  1465   Monday, March 27, 2017, 12:55 David WangSpent Target VaultRepair  S/W silo rust clean up

Rust on S/W silo and cover plate stored at silo area are cleaned up.

Attachment 1: rust_removal_at_sw_silo_001.JPG
rust_removal_at_sw_silo_001.JPG
Attachment 2: rust_removal_at_sw_silo_002.JPG
rust_removal_at_sw_silo_002.JPG
Attachment 3: rust_removal_at_sw_silo_003.JPG
rust_removal_at_sw_silo_003.JPG
Attachment 4: rust_removal_at_sw_silo_004.JPG
rust_removal_at_sw_silo_004.JPG
Attachment 5: rust_removal_at_sw_silo_005.JPG
rust_removal_at_sw_silo_005.JPG
  1476   Tuesday, April 04, 2017, 14:39 David WangCraneStandard Operation  Crane check main hoist on jogging with shielding plug lifted.

Today, I checked TH crane main hoist  when shielding plug is installed into ITE pit. I did  some jogging actions on main hoist during the operation. Everything looks fine. No burning smell, no strange noise. An outside crane expert suggest that jogging is the worst working situation for crane. We have to use jogging actions during our crane operation. But, we could try to use less jogging when operate the crane.

  1479   Wednesday, April 05, 2017, 11:57 David WangITEMaintenance  ITE target module flange o-ring repalcement

ITE target module tank flange o-ring was replaced yesterday before TM4 moving. ITE: IG1S reading looks fine so far. 

  1482   Thursday, April 06, 2017, 15:11 Grant MinorCraneMaintenance  Target Hall Crane 20 ton hoist - Report by Gordon Crane 5-Apr-2017

-------- Forwarded Message --------

Subject:

ISAC Hoist Brake Repair

Date:

Wed, 05 Apr 2017 20:42:49 -0700

From:

Aidan C. Gordon <aidan@gordoncrane.com>

To:

Curtis Ballard <ballard@triumf.ca>, Neil Wong <nwong@triumf.ca>

CC:

Peter Neumann <peter@gordoncrane.com>, Shelley Cherkowski <Shelley@gordoncrane.com>

 

Hi Curtis

 

Further to the emergency service call at the Isac Target Hall on Thursday March 23rd, we advise as follows:

 

It was reported that the hoist was making an unusual noise and that there was a strong brake odour during operation.

The lift was completed using the auxiliary hoist.

 

A man-lift was arranged and Senior Service Technician Tom Kauss attended site the next morning to troubleshoot.

He determined that one of two hoist brakes (walkway side) had a strong odour and on closer examination it appeared that the 

brake lining material was breaking down and particulate lining material was getting caught between the lining and the discs.

These lining fragments were rubbing and burning off during the hoist operation.

The end cover of the brake had an accumulation of brake lining fragments 

The lining was not overly worn, but appears to be becoming friable, perhaps with age or exposure to radiation.

 

The brake was cleaned with compressed air to remove the friable material and thoroughly tested. 

A test load of approximately 10 tons was lifted and the hoist handled the load without issue

The brake fragment issue did not recur while we on site and the hoist was recommissioned for use.

 

To guard against the likely recurrence of this condition on this critical application crane, and as both brakes have seen identical conditions in operation, 

we recommend that both brake assemblies be replaced.

The brake assembly would include the brake coil, friction discs, steel brake discs and the brake springs

TRIUMF does not have a spare brake on hand, therefore one of the removed brakes could be rebuilt and kept on hand. 

 

Two (2) each  XL-60009637 Complete Brake Assemblies   $ 5,706.00  Each

 

One (1) only XL-60009674 Brake Repair Kit $ 2,435.00

            For Rebuild

 

One (1) only XL-52272125 Brake Spring Kit $     59.72 For Rebuild

Installation & Testing of New Brakes estimated at: $ 1,250.00 Lot

We have one brake in stock in our Vancouver Service Depot. A second brake is available Ex-Ontario

FOB Site

Applicable Taxes Extra

Quote Valid for 30 days, subject to prior sale.

 

We are available next week to perform this work on site.

Please let us know if you have any questions or if you would like us to proceed.

 

Best Regards

          Aidan

 

------------------

Aidan C. Gordon

General Manager

aidan@gordoncrane.com

Gordon Crane & Hoist Inc.

Celebrating 34 years of Excellence (1983-2017)


www.gordoncrane.com

Toll Free 1-866-HOIST-IT

              (1-866-464-7848)

Tel:  (604) 324-2441

105-8475 Ontario St

Vancouver BC  V5X 3E8


Privilege and Confidentiality Notice
The information in this email is intended for the named recipients only. It may contain privileged and confidential information. If you have received this email in error, any use, copying or dissemination of its contents is prohibited. Please notify the sender immediately by telephone at the number indicated on this page to arrange destruction and/or return of the email.  Your co-operation is appreciated. Thank you.

  1483   Thursday, April 06, 2017, 15:16 Anders MjosConditioning StationMaintenance  Installation of new break out box to accommodate both ITM:MP2 and TCS:MP1

Installation by Marshall. Dave M from controls adjusted circuitry to get TCS:MP1 to start.

Work is being done in preparation for the Module Move Ventilation SAS project